Nebraska Department of Roads | |
---|---|
Estimate Summary to Contractor | |
Vendor ID: | 1242 GARCIA-CHICOINE ENTERPRISES, INC. |
Contract ID: | 0557 |
Estimate Number: | 0007 |
Pay Period End Date: | 09.06.2003 |
Contract Location: | ||
STATEWIDE I-80 REST AREA SIGNING | Estimate Type: | PROG |
Contractor: | ||
GARCIA-CHICOINE ENTERPRISES, INC. | Date Let: | 02.06.2003 |
PO BOX 81097 | Date Awarded: | 02.13.2003 |
Date Contract Executed: | 02.19.2003 | |
Date Notice to Proceed: | 02.19.2003 | |
LINCOLN NE 68501-1097 | Date Work Began: | 04.14.2003 |
Phone: | Date Physical Work Completed: | |
(402)434-5444 | Date Accepted: | |
Escrow Agent: | ||
Surety Co: | ||
INLAND INSURANCE COMPANY |
Counties |
---|
BUFFALO |
CASS |
CHEYENNE |
DAWSON |
DEUEL |
KEITH |
KIMBALL |
LANCASTER |
LINCOLN |
SEWARD |
YORK |
Project Number |   | PCT |   | Fed State Project Number |   | Description | |
---|---|---|---|---|---|---|---|
00557 000 |   | 0.000 |   | S-STWD(1023) |   | SIGN |
Total to Date | Prev to Date | This Estimate | ||
Current Contract Amt | Total Earnings | $233,113.10 | $163,678.35 | $69,434.75 |
$294,700.75 | Stockpiled Materials | $.00 | $.00 | $.00 |
Original Contract Amt | Gross Earnings | $233,113.10 | $163,678.35 | $69,434.75 |
$294,700.75 | Retainage | $-2,331.13 | $-1,636.78 | $-694.35 |
Escrow Amount | $.00 | $.00 | $.00 | |
Percent Complete | Securities Encumbered | $.00 | $.00 | $.00 |
79.10% | Net Earnings | $230,781.97 | $162,041.57 | $68,740.40 |
Liquidated Damages | $.00 | $.00 | $.00 | |
Incentives | $.00 | $.00 | $.00 | |
Disincentives | $.00 | $.00 | $.00 | |
Other Contract Adj | $.00 | $.00 | $.00 | |
Appl of Training Adj | $.00 | $.00 | $.00 | |
Training Rates Adj | $.00 | $.00 | $.00 | |
Fuel Adj | $.00 | $.00 | $.00 | |
Bituminous Adj | $.00 | $.00 | $.00 | |
Autopay Adj | $.00 | $.00 | $.00 | |
Gasoline Adj | $.00 | $.00 | $.00 | |
Other Adj | $.00 | $.00 | $.00 | |
Price Adj | $.00 | $.00 | $.00 | |
Substandard Item Adj | $.00 | $.00 | $.00 | |
Asphalt Adj | $.00 | $.00 | $.00 | |
Diesel Fuel Adj | $.00 | $.00 | $.00 | |
Petrol Adj | $.00 | $.00 | $.00 | |
Total for Adjustments | $.00 | $.00 | $.00 | |
Payment | $230,781.97 | $162,041.57 | $68,740.40 | |
Project Manager | Div. Head/Dist. Eng. | |||
Thomsen, Toby | 09.08.2003 | O'Donnell, Les | 09.09.2003 | |
Constr. Estimate Eng. | Materials Eng. | |||
Bartos, Steve | 09.09.2003 | |||
Controller Div. Processed | ||||
Burling, Laurie | 09.09.2003 |
Detailed breakdown of stockpiled materials | ||||
---|---|---|---|---|
Total remaining for contract: | 0.00 |
1. Contracted | |||
---|---|---|---|
2. Current | |||
3. To date | |||
Item Nbr Item Code | Unit Price | 4. This Est | |
Item Description | Units | Qty | Amount |
GROUP 8C SIGNING | |||
0001 0001.08 | 0.50 | 2,190.000 | 1,095.00 |
BARRICADE, TYPE II | BDAY | 2,190.000 | 1,095.00 |
5.000 | 2.50 | ||
0.000 | 0.00 | ||
0002 0001.10 | 0.50 | 192.000 | 96.00 |
BARRICADE, TYPE III | BDAY | 192.000 | 96.00 |
0.000 | 0.00 | ||
0.000 | 0.00 | ||
0003 0001.75 | 3.20 | 2,628.000 | 8,409.60 |
TEMPORARY SIGN DAY | EACH | 2,628.000 | 8,409.60 |
93.000 | 297.60 | ||
0.000 | 0.00 | ||
0004 0030.82 | 29,800.00 | 1.000 | 29,800.00 |
MOBILIZATION | LS | 1.000 | 29,800.00 |
0.988 | 29,442.40 | ||
0.000 | 0.00 | ||
0005 7308.10 | 600.00 | 1.000 | 600.00 |
REMOVE SIGN | EACH | 1.000 | 600.00 |
1.000 | 600.00 | ||
1.000 | 600.00 | ||
0006 7322.01 | 115.19 | 804.220 | 92,638.10 |
TYPE B SIGN | SY | 804.220 | 92,638.10 |
623.864 | 71,862.89 | ||
288.424 | 33,223.56 | ||
0007 7322.05 | 18.37 | 16.330 | 299.98 |
INSTALL TYPE B SIGN | SY | 16.330 | 299.98 |
10.888 | 200.01 | ||
0.000 | 0.00 | ||
0008 7340.00 | 1.14 | 57,475.500 | 65,522.07 |
STRUCTURAL STEEL FOR SIGN SUPPORTS | LB | 57,475.500 | 65,522.07 |
47,901.490 | 54,607.70 | ||
19,615.080 | 22,361.19 | ||
0009 7360.24 | 415.00 | 38.000 | 15,770.00 |
24" SIGN SUPPORT FOOTING | EACH | 38.000 | 15,770.00 |
38.000 | 15,770.00 | ||
0.000 | 0.00 | ||
0010 7360.30 | 535.00 | 88.000 | 47,080.00 |
30" SIGN SUPPORT FOOTING | EACH | 88.000 | 47,080.00 |
88.000 | 47,080.00 | ||
0.000 | 0.00 | ||
0011 7390.10 | 530.00 | 63.000 | 33,390.00 |
REMOVE SIGN, POST, AND FOOTING | EACH | 63.000 | 33,390.00 |
25.000 | 13,250.00 | ||
25.000 | 13,250.00 | ||
GROUP 8C SIGNING | Contracted | 294,700.75 | |
Current | 294,700.75 | ||
In place | 233,113.10 | ||
This Estimate | 69,434.75 | ||
Totals for contract | Contracted | 294,700.75 | |
Current | 294,700.75 | ||
In place | 233,113.10 | ||
This Estimate | 69,434.75 |