Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:2207 UNITED CONTRACTORS, INC.
Contract ID:1121
Estimate Number:0024
Pay Period End Date:04.20.2002
Contract Location:
BNSF IN BEATRICEEstimate Type:PROG
Contractor:
UNITED CONTRACTORS, INC.Date Let:10.19.2000
6678 NW 62ND AVEDate Awarded:11.03.2000
PO BOX 347Date Contract Executed:11.13.2000
Date Notice to Proceed:11.13.2000
JOHNSTON IA 50131Date Work Began:03.12.2001
Phone:Date Physical Work Completed:
(515)276-6162Date Accepted:
Escrow Agent:
Surety Co:
UNITED FIRE & CASUALTY COMPANY
Counties
GAGE
Project Number PCT Fed State Project Number Description
11121 000  0.000 EACBR-EACNH-77-1(115)  GR CONC PAVE CULV BR GDRL ELEC
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$3,377,287.24$3,369,108.30$8,178.94
$3,326,453.84Stockpiled Materials$-.01$-.01$.00
Original Contract AmtGross Earnings$3,377,287.23$3,369,108.29$8,178.94
$3,279,284.06Retainage$-25,000.00$-25,000.00$.00
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
101.53%Net Earnings$3,352,287.23$3,344,108.29$8,178.94
Liquidated Damages-$9,840.00-$8,200.00-$1,640.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$-441.98$-441.98$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments-$10,281.98-$8,641.98-$1,640.00
Payment$3,342,005.25$3,335,466.31$6,538.94
Project ManagerDiv. Head/Dist. Eng.
Kuper, Melvin04.22.2002Sklenar, Michael J04.22.2002
Constr. Estimate Eng.Materials Eng.
Bartos, Steve04.22.2002
Controller Div. Processed
Burling, Laurie04.22.2002
Detailed breakdown of stockpiled materials
Est Nbr:0001
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00314095.00 CONCRETE FACE PANELS
S.P. Initial Payment43,618.0633449
Concrete Face Panels
Total for estimate 0001:43,618.06
Est Nbr:0003
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00314095.00 CONCRETE FACE PANELS
S.P. Adjustment-929.7833449
Concrete Face Panels
S.P. Initial Payment43,618.0633656
Concrete Face Panels
S.P. Initial Payment2,764.7633756
Concrete Face Panels
S.P. Initial Payment0.0033672
Steel Re Strips
S.P. Adjustment0.0033672
Steel Re Strips
Total for estimate 0003:45,453.04
Est Nbr:0004
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00314095.00 CONCRETE FACE PANELS
S.P. Adjustment-18,994.1233449
Concrete Face Panels
S.P. Adjustment0.0033672
Steel Re Strips
Total for estimate 0004:-18,994.12
Est Nbr:0005
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00314095.00 CONCRETE FACE PANELS
S.P. Adjustment-15,939.1233449
Concrete Face Panels
S.P. Adjustment0.0033672
Steel Re Strips
Total for estimate 0005:-15,939.12
Est Nbr:0006
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00314095.00 CONCRETE FACE PANELS
S.P. Adjustment-5,313.0433449
Concrete Face Panels
S.P. Adjustment0.0033672
Steel Re Strips
01076071.11 STEEL SUPERSTRUCTURE
S.P. Initial Payment47,346.0085946
Steel Superstructure
Total for estimate 0006:42,032.96
Est Nbr:0007
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00314095.00 CONCRETE FACE PANELS
S.P. Adjustment-2,442.0133449
Concrete Face Panels
S.P. Adjustment-13,750.4933656
Concrete Face Panels
S.P. Adjustment0.0033672
Steel Re Strips
Total for estimate 0007:-16,192.50
Est Nbr:0008
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00314095.00 CONCRETE FACE PANELS
S.P. Adjustment-29,867.5733656
Concrete Face Panels
S.P. Adjustment-2,764.7633756
Concrete Face Panels
S.P. Adjustment0.0033672
Steel Re Strips
Total for estimate 0008:-32,632.33
Est Nbr:0010
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01076071.11 STEEL SUPERSTRUCTURE
S.P. Adjustment-4,734.6085946
Steel Superstructure
S.P. Initial Payment417,579.0087036
Steel Superstructure
S.P. Adjustment-41,757.9087036
Steel Superstructure
Total for estimate 0010:371,086.50
Est Nbr:0011
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01076071.11 STEEL SUPERSTRUCTURE
S.P. Adjustment-42,611.4085946
Steel Superstructure
S.P. Adjustment-375,821.1087036
Steel Superstructure
Total for estimate 0011:-418,432.50
Total remaining for contract:-0.01
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          L020.00 1.491,506.0002,243.94
EROSION CONTROL m2 1,506.0002,243.94
-0.400-0.59
0.0000.00

0002                          L020.01 6.80454.3003,089.24
EROSION CONTROL, TYPE A m2 454.3003,089.24
0.0000.00
0.0000.00

0003                          L020.09 13.5066.000891.00
EROSION CONTROL, TYPE AAA m2 66.000891.00
0.0000.00
0.0000.00

0004                          L020.10 1.68688.5001,156.68
EROSION CONTROL, TYPE HV m2 688.5001,156.68
8,277.87213,906.82
0.0000.00

0005                          L021.01 24.0054.0001,296.00
EROSION CHECKS, TYPE A BALE54.0001,296.00
0.0000.00
0.0000.00

0006                          L022.13 9.1054.000491.40
FABRIC SILT FENCE-LOW PROFILE HIGH POROSITY m 54.000491.40
0.0000.00
0.0000.00

0007                          L022.14 9.481,029.7009,761.56
FABRIC SILT FENCE-LOW PROFILE LOW POROSITY m 1,029.7009,761.56
393.8013,733.23
0.0000.00

0008                          0030.10 12,000.001.00012,000.00
MOBILIZATION LS 1.00012,000.00
1.00012,000.00
0.0000.00

0009                          1009.00 6,000.001.0006,000.00
GENERAL CLEARING AND GRUBBING LS 1.0006,000.00
1.0006,000.00
0.0000.00

0010                          1010.00 1.833,493.0006,392.19
EXCAVATION m3 3,493.0006,392.19
3,493.0006,392.19
0.0000.00

0011                          1010.10 3.2848,465.000158,965.20
EXCAVATION, BORROW m3 48,465.000158,965.20
25,800.00084,624.00
0.0000.00

0012                          1011.00 4.00520.0002,080.00
WATER kL 520.0002,080.00
0.0000.00
0.0000.00

0013                          1101.00 3.638,363.00030,357.69
REMOVE PAVEMENT m2 8,363.00030,357.69
8,452.00030,680.76
0.0000.00

0014                          1101.25 8.20100.000820.00
SAWING PAVEMENT m 100.000820.00
255.5402,095.43
0.0000.00

0015                          1102.00 4.654,073.00018,939.45
REMOVE ASPHALT SURFACE m2 4,073.00018,939.45
4,073.00018,939.45
0.0000.00

0016                          1107.00 6.00258.0001,548.00
REMOVE WALK m2 258.0001,548.00
344.0002,064.00
0.0000.00

0017                          1114.10 300.0019.0005,700.00
REMOVE RETAINING WALL m 19.0005,700.00
19.0005,700.00
0.0000.00

0018                          1122.87 50.003.000150.00
REMOVE GABION EACH3.000150.00
3.000150.00
0.0000.00

0019                          1124.00 500.001.000500.00
REMOVE BUILDING EACH1.000500.00
AT STA. 34+80 LT. 0.0000.00
0.0000.00

0020                          1124.01 500.001.000500.00
REMOVE BUILDING EACH1.000500.00
AT STA. 37+75 RT. 0.0000.00
0.0000.00

0021                          1125.00 150.001.000150.00
CLEAR TRACT EACH1.000150.00
AT STA. 34+73 TO 34+90 LT. 0.0000.00
0.0000.00

0022                          1125.01 150.001.000150.00
CLEAR TRACT EACH1.000150.00
AT STA. 37+60 TO 37+90 RT. 0.0000.00
0.0000.00

0023                          1701.24 48.89135.0006,600.15
600 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 135.0006,600.15
102.5005,011.23
0.0000.00

0024                          1706.24 100.0034.0003,400.00
600 mm ROUND EQUIVALENT DRIVEWAY CULVERT PIPE, TYPE 2 m 34.0003,400.00
34.0003,400.00
0.0000.00

0025                          6105.02 31.0062.4001,934.40
ROCK RIPRAP, TYPE B Mg 62.4001,934.40
0.0000.00
0.0000.00

0026                          7017.00 11.50106.5001,224.75
REMOVE GUARDRAIL m 106.5001,224.75
106.5001,224.75
0.0000.00

0027                          9110.01 50.0035.0001,750.00
RENTAL OF LOADER, FULLY OPERATED HOUR35.0001,750.00
0.0000.00
0.0000.00

0028                          9110.03 50.0035.0001,750.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR35.0001,750.00
0.0000.00
0.0000.00

0029                          9110.07 50.0035.0001,750.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR35.0001,750.00
0.0000.00
0.0000.00

GROUP 1 GRADINGContracted281,591.65
Current281,591.65
In place195,921.27
This Estimate0.00

GROUP 1A MSE WALLS
0030                          0030.10 13,500.001.00013,500.00
MOBILIZATION LS 1.00013,500.00
1.00013,500.00
0.0000.00

0031                          4095.00 157.001,042.100163,609.70
CONCRETE FACE PANELS m2 1,042.100163,609.70
1,042.100163,609.70
0.0000.00

0032                          4095.10 30.00194.5005,835.00
CONCRETE LEVELING PADS m 194.5005,835.00
194.5005,835.00
0.0000.00

0033                          4095.20 175.00203.70035,647.50
COPING m 203.70035,647.50
203.70035,647.50
0.0000.00

0034                          4350.18 30.00174.9005,247.00
450 mm CORRUGATED METAL PIPE m 174.9005,247.00
174.9005,247.00
0.0000.00

0035                          7110.04 28.00203.1005,686.80
1.2 METER CHAIN-LINK FENCE m 203.1005,686.80
203.1005,686.80
0.0000.00

0036                          7115.04 95.004.000380.00
END POST FOR 1.2 METER CHAIN-LINK FENCE EACH4.000380.00
4.000380.00
0.0000.00

0037                          7116.04 115.001.000115.00
CORNER POST FOR 1.2 METER CHAIN-LINK FENCE EACH1.000115.00
1.000115.00
0.0000.00

0038                          7117.04 115.007.000805.00
PULL POST FOR 1.2 METER CHAIN-LINK FENCE EACH7.000805.00
7.000805.00
0.0000.00

0039                          8024.75 25.004,644.000116,100.00
SELECT GRANULAR BACKFILL FOR MSE WALL m3 4,644.000116,100.00
4,644.000116,100.00
0.0000.00

GROUP 1A MSE WALLSContracted346,926.00
Current346,926.00
In place346,926.00
This Estimate0.00

GROUP 3 CONCRETE PAVEMENT
0040                          L001.02 3,500.001.4905,215.00
SEEDING, TYPE B ha 1.4905,215.00
1.9676,884.50
1.9676,884.50

0041                          L010.00 6.003,392.00020,352.00
SODDING m2 3,392.00020,352.00
3,954.10023,724.60
0.0000.00

0042                          L032.80 100.003.400340.00
HYDROMULCH Mg 3.400340.00
5.307530.70
5.307530.70

0043                          0030.30 21,500.001.00021,500.00
MOBILIZATION LS 1.00021,500.00
1.00021,500.00
0.0000.00

0044                          2001.03 19.50124.9602,436.72
GRAVEL SURFACE COURSE Mg 124.9602,436.72
0.0000.00
0.0000.00

0045                          2010.03 26.4585.2002,253.54
CRUSHED ROCK SURFACE COURSE Mg 85.2002,253.54
346.0179,152.15
16.285430.74

0046                          2020.50 31.352,192.00068,719.20
SURFACING m2 2,192.00068,719.20
150 mm 1,934.45260,645.07
0.0000.00

0047                          3016.21 28.90554.00016,010.60
CONCRETE CLASS 47B-20 SIDEWALKS m2 554.00016,010.60
608.27717,579.21
-19.900-575.11

0048                          3016.23 34.3072.0002,469.60
150 mm CONCRETE CLASS 47B-20 SIDEWALKS m2 72.0002,469.60
69.5232,384.64
0.0000.00

0049                          3020.26 38.151,174.00044,788.10
CONCRETE CLASS 47B-25 DRIVEWAY m2 1,174.00044,788.10
640.77424,445.52
0.0000.00

0050                          3075.31 39.751,046.00041,578.50
205 mm CONCRETE PAVEMENT, CLASS 47B-25 m2 1,046.00041,578.50
1,135.80645,148.29
0.0000.00

0051                          3075.45 40.8512,166.000496,981.10
230 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25 m2 12,166.000496,981.10
13,344.446545,120.63
-0.100-4.09

0052                          7502.04 6.251,225.0007,656.25
100 mm WHITE PREFORMED PAVEMENT MARKING, TYPE 4 m 1,225.0007,656.25
1,250.0007,812.50
0.0000.00

0053                          7503.04 6.251,700.00010,625.00
100 mm YELLOW PREFORMED PAVEMENT MARKING, TYPE 4 m 1,700.00010,625.00
1,694.00010,587.50
0.0000.00

0054                          8029.04 4.9013,212.00064,738.80
AGGREGATE FOUNDATION COURSE 100 mm m2 0.0000.00
0.0000.00
0.0000.00

0055                          9111.00 2.50248.000620.00
WATER kL 248.000620.00
64.345160.87
0.0000.00

0056                          9170.00 500.0017.2388,619.00
EARTH SHOULDER CONSTRUCTION StaM17.2388,619.00
10.4815,240.50
0.0000.00

0057                          9173.20 1.7514,370.00025,147.50
SUBGRADE PREPARATION m2 14,370.00025,147.50
18,513.45632,398.55
69.505121.63

0058                          9188.50 35.00263.0009,205.00
SURFACING UNDER GUARDRAIL m2 263.0009,205.00
125 mm 257.4539,010.86
0.0000.00

0412                          3275.20 4.900.0000.00
CRUSH CONCRETE PAVEMENT m2 5,151.00025,239.90
Crushed concrete Pavement - For Base Course 6,165.66430,211.75
69.505340.57

0413                          3275.20 4.900.0000.00
CRUSH CONCRETE PAVEMENT m2 8,061.00039,498.90
Crushed Concrete Pavement for Base Course 9,995.96048,980.20
0.0000.00

GROUP 3 CONCRETE PAVEMENTContracted849,255.91
Current849,255.91
In place901,518.04
This Estimate7,728.94

GROUP 4 CULVERTS
0059                          P127.24 138.0024.0003,312.00
600 mm ROUND EQUIVALENT CULVERT PIPE, TYPE 2 m 24.0003,312.00
24.0003,312.00
0.0000.00

0060                          P700.15 61.00307.50018,757.50
375 mm STORM SEWER PIPE, TYPE 1,7 OR 8 m 307.50018,757.50
307.50018,757.50
0.0000.00

0061                          P700.18 72.0087.5006,300.00
450 mm STORM SEWER PIPE, TYPE 1,7 OR 8 m 87.5006,300.00
94.5006,804.00
0.0000.00

0062                          P700.24 94.0085.0007,990.00
600 mm STORM SEWER PIPE, TYPE 1,7 OR 8 m 85.0007,990.00
153.70014,447.80
0.0000.00

0063                          P700.30 125.00142.50017,812.50
750 mm STORM SEWER PIPE, TYPE 1,7 OR 8 m 142.50017,812.50
226.00028,250.00
0.0000.00

0064                          P702.48 280.0039.00010,920.00
1200 mm STORM SEWER PIPE, TYPE 1 m 39.00010,920.00
39.00010,920.00
0.0000.00

0065                          P705.24 105.0017.0001,785.00
600 mm STORM SEWER PIPE, TYPE 1 CLASS IV m 17.0001,785.00
17.0001,785.00
0.0000.00

0066                          0030.40 2,750.001.0002,750.00
MOBILIZATION LS 1.0002,750.00
1.0002,750.00
0.0000.00

0067                          1117.00 225.001.000225.00
REMOVE MANHOLE EACH1.000225.00
1.000225.00
0.0000.00

0068                          1119.00 150.007.0001,050.00
REMOVE INLET EACH7.0001,050.00
8.0001,200.00
3.000450.00

0069                          1119.50 125.001.000125.00
REMOVE JUNCTION BOX EACH1.000125.00
2.000250.00
0.0000.00

0070                          4002.00 2.951,138.0003,357.10
CAST IRON COVER AND FRAME kg 1,138.0003,357.10
957.0002,823.15
0.0000.00

0071                          4004.50 2.952,034.0006,000.30
CAST IRON GRATE AND FRAME kg 2,034.0006,000.30
2,821.0008,321.95
0.0000.00

0072                          4005.00 2.45468.0001,146.60
CAST IRON RING AND COVER kg 468.0001,146.60
695.0001,702.75
0.0000.00

0073                          4016.00 2,500.001.0002,500.00
MANHOLE EACH1.0002,500.00
AT STA. 33+01, 12.0 m LT. 1.0002,500.00
0.0000.00

0074                          4016.01 2,325.001.0002,325.00
MANHOLE EACH1.0002,325.00
AT STA. 34+72, 19.0 m LT. 1.0002,325.00
0.0000.00

0075                          4016.02 1,950.001.0001,950.00
MANHOLE EACH1.0001,950.00
AT STA. 35+60, 9.0 m RT. 1.0001,950.00
0.0000.00

0076                          4016.03 1,950.001.0001,950.00
MANHOLE EACH1.0001,950.00
AT STA. 37+61, 19.0 m LT. 1.0001,950.00
0.0000.00

0077                          4016.04 2,000.001.0002,000.00
MANHOLE EACH1.0002,000.00
AT STA. 38+11, 9.0 m LT. 1.0002,000.00
0.0000.00

0078                          4035.00 75.002.000150.00
REMOVE FLARED-END SECTION EACH2.000150.00
2.000150.00
0.0000.00

0079                          4040.00 150.0010.0001,500.00
REMOVE HEADWALLS FROM CULVERTS EACH10.0001,500.00
10.0001,500.00
0.0000.00

0080                          4043.50 35.00122.0004,270.00
REMOVE SEWER PIPE m 122.0004,270.00
155.9005,456.50
0.0000.00

0081                          4044.00 2,500.001.0002,500.00
PREPARATION OF STRUCTURE EACH1.0002,500.00
AT STA. 31+94.28 1.0002,500.00
0.0000.00

0082                          4050.01 12.00115.0001,380.00
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 115.0001,380.00
126.0001,512.00
0.0000.00

0083                          4051.01 12.00174.0002,088.00
EXCAVATION FOR BOX CULVERTS m3 174.0002,088.00
221.0602,652.72
0.0000.00

0084                          4101.06 455.0061.58028,018.90
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 61.58028,018.90
63.68528,976.68
0.0000.00

0085                          4102.11 610.0015.7009,577.00
CLASS 47B-20 OR AX-20 CONCRETE FOR RETAINING WALL m3 15.7009,577.00
13.3888,166.68
0.0000.00

0086                          4105.58 595.0048.66028,952.70
CLASS 47B-20 CONCRETE FOR INLET AND JUNCTION BOX m3 48.66028,952.70
66.37039,490.15
0.0000.00

0087                          4151.00 1.454,274.0006,197.30
REINFORCING STEEL FOR BOX CULVERT kg 4,274.0006,197.30
4,446.5606,447.51
0.0000.00

0088                          4152.00 2.201,103.0002,426.60
REINFORCING STEEL FOR RETAINING WALL kg 1,103.0002,426.60
1,003.0612,206.73
0.0000.00

0089                          4155.50 2.201,513.0003,328.60
REINFORCING STEEL FOR INLET AND JUNCTION BOX kg 1,513.0003,328.60
2,182.4004,801.28
0.0000.00

0090                          4310.24 415.002.000830.00
600 mm FLARED-END SECTION EACH2.000830.00
4.0001,660.00
0.0000.00

0091                          4310.48 985.001.000985.00
1200 mm FLARED-END SECTION EACH1.000985.00
1.000985.00
0.0000.00

0092                          4320.24 550.002.0001,100.00
600 mm ROUND EQUIVALENT FLARED-END SECTION EACH2.0001,100.00
2.0001,100.00
0.0000.00

0093                          4852.24 398.0017.0006,766.00
JACKING 600 mm STORM SEWER PIPE, TYPE m 17.0006,766.00
1 CLASS IV 0.0000.00
0.0000.00

0094                          6105.01 37.8097.0003,666.60
ROCK RIPRAP, TYPE A Mg 97.0003,666.60
99.7303,769.79
0.0000.00

0095                          6105.03 37.2550.0001,862.50
ROCK RIPRAP, TYPE C Mg 50.0001,862.50
0.0000.00
0.0000.00

0406                          4900.58 5,229.000.0000.00
RECONNECT EACH1.0005,229.00
Repair Sanitary Sewer Line 1.0005,229.00
0.0000.00

0409                          4043.00 5,712.000.0000.00
REMOVE CULVERT PIPE m 1.0005,712.00
Remove and Salvage 1200mm R.C. Pipe 1.0005,712.00
0.0000.00

0414                          4350.26 68.250.0000.00
600 mm CORRUGATED METAL PIPE m 12.200832.65
Added pipe at Mulberry Avenue. 12.200832.65
0.0000.00

0415                          4310.24 236.250.0000.00
600 mm FLARED-END SECTION EACH2.000472.50
For added pipe. 2.000472.50
0.0000.00

0416                          4035.00 52.500.0000.00
REMOVE FLARED-END SECTION EACH1.00052.50
Remove and dispose of RCFE at Station 29+75 Left. 1.00052.50
0.0000.00

0417                          0095.00 162.750.0000.00
ADDITIONAL FREIGHT LS 1.000162.75
For additional pipe at Station 29+75 Left. 1.000162.75
0.0000.00

0418                          4350.12 57.750.0000.00
300 mm CORRUGATED METAL PIPE m 9.500548.63
For added pipe at Station 33+95.24, Right. 9.500548.63
0.0000.00

0419                          4360.12 204.750.0000.00
300 mm METAL FLARED-END SECTION EACH1.000204.75
For added pipe at 33+95.24 1.000204.75
0.0000.00

0420                          4200.12 708.750.0000.00
300 mm AUTOMATIC FLOOD CONTROL GATE EACH1.000708.75
For added pipe at Station 33+95.24, Right 1.000708.75
0.0000.00

0421                          1043.50 2.520.0000.00
RIPRAP FILTER FABRIC m2 206.000519.12
For locations, 29+75 Rt., 32+35 Lt., and 34+60 Lt. 206.000519.12
0.0000.00

0422                          4018.00 813.750.0000.00
TAPPING EXISTING STRUCTURE EACH1.000813.75
Tap and install 450 mm RCP at Sta. 34+35 left. 1.000813.75
0.0000.00

0423                          4460.30 577.500.0000.00
750 mm CONCRETE FLARED END SECTION EACH1.000577.50
750 mm RCP Flared End for new pipe run No. 15. 1.000577.50
0.0000.00

0424                          4025.51 3,045.000.0000.00
FLUMES, TYPE I EACH1.0003,045.00
Concrete Flume, Type 1 added at Station 33+95.24 1.0003,045.00
0.0000.00

0425                          6403.75 309.750.0000.00
SPLASH BARRIER m 10.0003,097.50
Flume Spillway-added 10.0003,097.50
0.0000.00

0426                          4039.05 2,982.000.0000.00
REMOVE AND RELAY REINFORCED CONCRETE SEWER PIPE LS 1.0002,982.00
Remove, Salvage, Extend, Relay 600 mm RCP, Station 31+94.28 1.0002,982.00
0.0000.00

0427                          W719.90 2,404.500.0000.00
LOWER WATER SERVICE PIPE LS 1.0002,404.50
Lower 5 private lines at Station 29+75 Left. 1.0002,404.50
0.0000.00

0428                          3900.27 15,225.000.0000.00
ADDITIONAL COST EACH1.00015,225.00
Extra work to build Retention Pond. 1.00015,225.00
0.0000.00

0429                          4450.36 226.800.0000.00
900 mm REINFORCED CONCRETE PIPE m 31.4007,121.52
31.4007,121.52
0.0000.00

0430                          4460.36 782.250.0000.00
900 mm CONCRETE FLARED END SECTION EACH1.000782.25
1.000782.25
0.0000.00

0431                          4015.66 3,328.500.0000.00
INSTALL MANHOLE EACH1.0003,328.50
1.0003,328.50
0.0000.00

6001                          4051.12 45.500.0000.00
GRANULAR MATERIAL FOR FOUNDATION OF BOX CULVERT m3 37.8901,724.00
47B Fine Agg. for Box Culvert Foundation. 37.8901,724.00
0.0000.00

6002                          4051.12 45.500.0000.00
GRANULAR MATERIAL FOR FOUNDATION OF BOX CULVERT m3 9.170417.24
47B Course Material for unsuitable material, Left side of bo 9.170417.24
0.0000.00

GROUP 4 CULVERTSContracted197,855.20
Current253,816.60
In place279,610.60
This Estimate450.00

GROUP 6 BRIDGE AT STA. 36+50.33
0096                          0020.00 0.801,000.000800.00
TRAINING HOUR1,000.000800.00
716.000572.80
0.0000.00

0097                          0030.60 76,250.001.00076,250.00
MOBILIZATION LS 0.0000.00
1.00076,250.00
0.0000.00

0098                          3050.15 225.00188.30042,367.50
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 m3 188.30042,367.50
188.30042,367.50
0.0000.00

0099                          3051.10 1.1012,484.00013,732.40
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES kg 12,484.00013,732.40
12,483.50013,731.85
0.0000.00

0100                          6000.10 5,000.001.0005,000.00
ABUTMENT NO.1 EXCAVATION LS 1.0005,000.00
1.0005,000.00
0.0000.00

0101                          6000.11 5,000.001.0005,000.00
ABUTMENT NO.2 EXCAVATION LS 1.0005,000.00
1.0005,000.00
0.0000.00

0102                          6000.20 35,000.001.00035,000.00
PIER NO.1 EXCAVATION LS 0.0000.00
0.0000.00
0.0000.00

0103                          6005.85 8,000.002.00016,000.00
GUIDED BEARING DEVICE, TYPE II EACH2.00016,000.00
0.0000.00
0.0000.00

0104                          6010.22 400.00250.700100,280.00
CLASS 47B-20 CONCRETE FOR BRIDGE m3 205.60082,240.00
205.60082,240.00
0.0000.00

0105                          6010.26 450.00372.200167,490.00
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 372.200167,490.00
372.200167,490.00
0.0000.00

0106                          6040.00 133,000.001.000133,000.00
REMOVE STRUCTURE EACH1.000133,000.00
AT STA. 36+80 1.000133,000.00
0.0000.00

0107                          6071.11 600,000.001.000600,000.00
STEEL SUPERSTRUCTURE LS 1.000600,000.00
AT STA. 36+50.33 1.000600,000.00
0.0000.00

0108                          6080.00 4.0033,895.000135,580.00
STRUCTURAL STEEL FOR SUBSTRUCTURE kg 33,895.000135,580.00
33,895.000135,580.00
0.0000.00

0109                          6100.00 800.001.000800.00
FLOOR DRAINS EACH1.000800.00
1.000800.00
0.0000.00

0110                          6107.00 40.00907.00036,280.00
CONCRETE SLOPE PROTECTION m2 907.00036,280.00
890.72335,628.92
0.0000.00

0111                          6131.50 1.1064,617.00071,078.70
EPOXY COATED REINFORCING STEEL kg 68,100.00074,910.00
68,100.00074,910.00
0.0000.00

0112                          6139.50 30.00108.0003,240.00
SUBSURFACE DRAINAGE MATTING m2 108.0003,240.00
108.0003,240.00
0.0000.00

0113                          6210.12 59.00637.30037,600.70
HP 250 mm X 62 kg STEEL PILING m 637.30037,600.70
660.35038,960.65
0.0000.00

0114                          6401.00 106.5095.80010,202.70
PEDESTRIAN BARRIER RAIL m 95.80010,202.70
95.80010,202.70
0.0000.00

0115                          6404.00 165.0095.60015,774.00
PEDESTRIAN RAILING (CHAIN LINK TYPE) m 95.60015,774.00
95.60015,774.00
0.0000.00

0116                          6601.03 24.0020.200484.80
20 mm CONDUIT IN BRIDGE m 20.200484.80
20.200484.80
0.0000.00

0117                          6601.15 26.00107.7002,800.20
38 mm CONDUIT IN BRIDGE m 107.7002,800.20
107.7002,800.20
0.0000.00

0118                          6610.45 350.0039.80013,930.00
STRIP SEALS m 39.80013,930.00
39.80013,930.00
0.0000.00

0119                          8091.00 30.00295.0008,850.00
GRANULAR BACKFILL m3 295.0008,850.00
295.0008,850.00
0.0000.00

0401                          6000.20 14,865.000.0000.00
PIER NO.1 EXCAVATION LS 1.00014,865.00
Pier No. 1 Excavation (Revised) 1.00014,865.00
0.0000.00

0402                          6010.21 276.860.0000.00
CONCRETE CLASS 47B-20 FOR BRIDGES m3 39.00010,797.54
For Drilled Shafts (EQ) 39.00010,797.54
0.0000.00

0403                          6251.52 833.33330.0000.00
DRILLED SHAFT EACH24.00020,000.00
Drilled Shaft 24.00020,000.00
0.0000.00

0404                          0030.60 1.000
MOBILIZATION LS 2.0000.00
Mobilization (Revised) 1.00047,375.00
0.0000.00

0405                          0025.10 16,210.580.0000.00
VALUE ENGINEERING ADJUSTMENT LS 1.00016,210.58
VEP Incentive 1.00016,210.58
0.0000.00

0407                          6210.61 118.000.0000.00
PILE SPLICE EACH30.0003,540.00
Pile Splices 30.0003,540.00
0.0000.00

0408                          6210.55 35.400.0000.00
STEEL PILING m 26.970954.74
Pile Cut Off 26.970954.74
0.0000.00

0432                          6610.60 2,549.240.0000.00
METAL BOND BREAKER EACH1.0002,549.24
Pay for installation and materials of Bond Breaker. 0.0000.00
0.0000.00

GROUP 6 BRIDGE AT STA. 36+50.33Contracted1,531,541.00
Current1,522,374.40
In place1,580,556.28
This Estimate0.00

GROUP 7 GUARDRAIL
0120                          0030.70 1,050.001.0001,050.00
MOBILIZATION LS 1.0001,050.00
1.0001,050.00
0.0000.00

0121                          7011.20 48.00144.8006,950.40
W-BEAM GUARDRAIL m 144.8006,950.40
144.8006,950.40
0.0000.00

0122                          7020.00 1,250.004.0005,000.00
BRIDGE APPROACH SECTIONS EACH4.0005,000.00
4.0005,000.00
0.0000.00

0123                          7024.25 2,000.004.0008,000.00
GUARDRAIL END TREATMENT, TYPE I EACH4.0008,000.00
4.0008,000.00
0.0000.00

GROUP 7 GUARDRAILContracted21,000.40
Current21,000.40
In place21,000.40
This Estimate0.00

GROUP 8B LIGHTING
0124                          A001.12 350.003.0001,050.00
PULL BOX, TYPE PB-5 EACH3.0001,050.00
3.0001,050.00
0.0000.00

0125                          A001.16 370.001.000370.00
PULL BOX, TYPE PB-6 EACH1.000370.00
1.000370.00
0.0000.00

0126                          A009.07 990.001.000990.00
STREET LIGHTING UNIT, TYPE SL-S-12.2-1.2-0.25 EACH1.000990.00
1.000990.00
0.0000.00

0127                          A009.29 1,365.0012.00016,380.00
STREET LIGHTING UNIT, TYPE SL-BT-12.2-1.8-0.25 EACH12.00016,380.00
12.00016,380.00
0.0000.00

0128                          A020.17 1,370.001.0001,370.00
LIGHTING CONTROL CENTER, TYPE P EACH1.0001,370.00
1.0001,370.00
0.0000.00

0129                          A070.10 5.20513.0002,667.60
38 mm CONDUIT IN TRENCH m 513.0002,667.60
532.0002,766.40
0.0000.00

0130                          A072.10 11.00148.0001,628.00
38 mm CONDUIT UNDER ROADWAY m 148.0001,628.00
148.0001,628.00
0.0000.00

0131                          A080.22 1.60769.0001,230.40
STREET LIGHTING CABLE, NO. 6 BARE m 769.0001,230.40
810.0001,296.00
0.0000.00

0132                          A080.24 1.801,538.0002,768.40
STREET LIGHTING CABLE, NO. 6 USE m 1,538.0002,768.40
1,620.0002,916.00
0.0000.00

0133                          0030.80 400.001.000400.00
MOBILIZATION LS 1.000400.00
1.000400.00
0.0000.00

GROUP 8B LIGHTINGContracted28,854.40
Current28,854.40
In place29,166.40
This Estimate0.00

GROUP 10 GENERAL ITEMS
0134                          0001.10 1.255,344.0006,680.00
BARRICADE, TYPE III BDAY5,344.0006,680.00
11,298.00014,122.50
0.0000.00

0135                          0001.30 3.00928.0002,784.00
TYPE B HIGH INTENSITY WARNING LIGHT LDAY928.0002,784.00
761.0002,283.00
0.0000.00

0136                          0001.90 0.2513,536.0003,384.00
SIGN DAY EACH13,536.0003,384.00
8,383.0002,095.75
0.0000.00

0137                          0002.39 2.10315.000661.50
TEMPORARY PAVEMENT MARKING, TYPE II m 315.000661.50
0.0000.00
0.0000.00

0138                          0003.10 175.0030.0005,250.00
FLAGGING DAY 30.0005,250.00
0.0000.00
0.0000.00

0139                          0010.04 1,000.001.0001,000.00
FIELD OFFICE EACH1.0001,000.00
0.750750.00
0.0000.00

0140                          0030.10 2,500.001.0002,500.00
MOBILIZATION LS 1.0002,500.00
1.0002,500.00
0.0000.00

0410                          0001.08 0.500.0000.00
BARRICADE, TYPE II BDAY500.000250.00
Type "II" Barricades 1,592.000796.00
0.0000.00

0411                          0001.46 0.250.0000.00
REFLECTORIZED CONE BDAY500.000125.00
42" Reflective Cones 164.00041.00
0.0000.00

GROUP 10 GENERAL ITEMSContracted22,259.50
Current22,634.50
In place22,588.25
This Estimate0.00

Totals for contractContracted3,279,284.06
Current3,279,078.85
In place3,377,287.24
This Estimate8,178.94