| | Detailed breakdown of stockpiled materials | |
|
---|
Est Nbr: | 0002 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0021 | 9005.30 | ASPHALTIC CONCRETE, TYPE SP2(0.5) | |
|
| | S.P. Initial Payment | 6,043.53 | 2075093
|
| | 5/8" CRUSHED ROCK | |
|
| | Total for estimate 0002: | 6,043.53 |
|
Est Nbr: | 0003 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0021 | 9005.30 | ASPHALTIC CONCRETE, TYPE SP2(0.5) | |
|
| | S.P. Initial Payment | 6,454.78 | 2084748
|
| | 5/8" CRUSHED ROCK | |
|
| | S.P. Initial Payment | 3,550.60 | 2095758
|
| | 5/8" CRUSHED ROCK | |
|
| | S.P. Initial Payment | 4,402.56 | 2095758
|
| | SCREENINGS | |
|
| | S.P. Initial Payment | 1,726.47 | 2095758
|
| | 1/4" CRUSHED ROCK | |
|
| | S.P. Initial Payment | 2,529.44 | 2106964
|
| | SCREENINGS | |
|
| | S.P. Initial Payment | 7,617.83 | 2106964
|
| | 1/4" CRUSHED ROCK | |
|
| | Total for estimate 0003: | 26,281.68 |
|
Est Nbr: | 0006 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0021 | 9005.30 | ASPHALTIC CONCRETE, TYPE SP2(0.5) | |
|
| | S.P. Adjustment | -6,043.53 | 2075093
|
| | 5/8" CRUSHED ROCK | |
|
| | S.P. Adjustment | -6,454.78 | 2084748
|
| | 5/8" CRUSHED ROCK | |
|
| | S.P. Adjustment | -3,550.60 | 2095758
|
| | 5/8" CRUSHED ROCK | |
|
| | S.P. Adjustment | -4,402.56 | 2095758
|
| | SCREENINGS | |
|
| | S.P. Adjustment | -1,726.47 | 2095758
|
| | 1/4" CRUSHED ROCK | |
|
| | S.P. Adjustment | -2,529.44 | 2106964
|
| | SCREENINGS | |
|
| | S.P. Adjustment | -7,617.83 | 2106964
|
| | 1/4" CRUSHED ROCK | |
|
| | Total for estimate 0006: | -32,325.21 |
|
Est Nbr: | 0002 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0021 | 9005.30 | ASPHALTIC CONCRETE, TYPE SP2(0.5) | |
|
| | S.P. Initial Payment | 6,619.11 | 2075093
|
| | 5/8" CRUSHED ROCK | |
|
| | Total for estimate 0002: | 6,619.11 |
|
Est Nbr: | 0003 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0021 | 9005.30 | ASPHALTIC CONCRETE, TYPE SP2(0.5) | |
|
| | S.P. Initial Payment | 7,069.57 | 2084748
|
| | 5/8" CRUSHED ROCK | |
|
| | S.P. Initial Payment | 3,888.86 | 2095758
|
| | 5/8" CRUSHED ROCK | |
|
| | S.P. Initial Payment | 4,821.92 | 2095758
|
| | SCREENINGS | |
|
| | S.P. Initial Payment | 1,890.92 | 2095758
|
| | 1/4" CRUSHED ROCK | |
|
| | S.P. Initial Payment | 2,770.32 | 2106964
|
| | SCREENINGS | |
|
| | S.P. Initial Payment | 8,343.30 | 2106964
|
| | 1/4" CRUSHED ROCK | |
|
| | Total for estimate 0003: | 28,784.89 |
|
Est Nbr: | 0002 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0021 | 9005.30 | ASPHALTIC CONCRETE, TYPE SP2(0.5) | |
|
| | S.P. Initial Payment | 10,935.79 | 2075093
|
| | 5/8 " CRUSHED ROCK | |
|
| | Total for estimate 0002: | 10,935.79 |
|
Est Nbr: | 0003 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0021 | 9005.30 | ASPHALTIC CONCRETE, TYPE SP2(0.5) | |
|
| | S.P. Initial Payment | 11,680.12 | 2084748
|
| | 5/8" CRUSHED ROCK | |
|
| | S.P. Initial Payment | 6,424.93 | 2095758
|
| | 5?8 " CRUSHED ROCK | |
|
| | S.P. Initial Payment | 7,966.56 | 2095758
|
| | SCREENINGS | |
|
| | S.P. Initial Payment | 3,124.17 | 2095758
|
| | 1/4 " CRUSHED ROCK | |
|
| | S.P. Initial Payment | 4,577.12 | 2106964
|
| | SCREENINGS | |
|
| | S.P. Initial Payment | 13,784.57 | 2106964
|
| | 1/4" CRUSHED ROCK | |
|
| | Total for estimate 0003: | 47,557.47 |
|
Est Nbr: | 0005 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0021 | 9005.30 | ASPHALTIC CONCRETE, TYPE SP2(0.5) | |
|
| | S.P. Adjustment | -7,417.73 | 2075093
|
| | 5/8 " CRUSHED ROCK | |
|
| | S.P. Adjustment | -7,922.98 | 2084748
|
| | 5/8" CRUSHED ROCK | |
|
| | S.P. Adjustment | -4,357.39 | 2095758
|
| | 5?8 " CRUSHED ROCK | |
|
| | S.P. Adjustment | -5,404.10 | 2095758
|
| | SCREENINGS | |
|
| | S.P. Adjustment | -2,119.35 | 2095758
|
| | 1/4 " CRUSHED ROCK | |
|
| | S.P. Adjustment | -3,104.14 | 2106964
|
| | SCREENINGS | |
|
| | S.P. Adjustment | -9,350.58 | 2106964
|
| | 1/4" CRUSHED ROCK | |
|
| | Total for estimate 0005: | -39,676.27 |
|
Est Nbr: | 0006 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0021 | 9005.30 | ASPHALTIC CONCRETE, TYPE SP2(0.5) | |
|
| | S.P. Adjustment | -454.17 | 2075093
|
| | 5/8 " CRUSHED ROCK | |
|
| | S.P. Adjustment | -485.11 | 2084748
|
| | 5/8" CRUSHED ROCK | |
|
| | S.P. Adjustment | -266.79 | 2095758
|
| | 5?8 " CRUSHED ROCK | |
|
| | S.P. Adjustment | -330.88 | 2095758
|
| | SCREENINGS | |
|
| | S.P. Adjustment | -129.76 | 2095758
|
| | 1/4 " CRUSHED ROCK | |
|
| | S.P. Adjustment | -190.06 | 2106964
|
| | SCREENINGS | |
|
| | S.P. Adjustment | -572.52 | 2106964
|
| | 1/4" CRUSHED ROCK | |
|
| | Total for estimate 0006: | -2,429.29 |
|
Est Nbr: | 0002 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0021 | 9005.30 | ASPHALTIC CONCRETE, TYPE SP2(0.5) | |
|
| | S.P. Initial Payment | 5,180.17 | 2075093
|
| | 5/8 " CRUSHED ROCK | |
|
| | Total for estimate 0002: | 5,180.17 |
|
Est Nbr: | 0003 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0021 | 9005.30 | ASPHALTIC CONCRETE, TYPE SP2(0.5) | |
|
| | S.P. Initial Payment | 5,532.73 | 2084748
|
| | 5/8" CRUSHED ROCK | |
|
| | S.P. Initial Payment | 3,043.46 | 2095758
|
| | 5/8 " CRUSHED ROCK | |
|
| | S.P. Initial Payment | 3,773.68 | 2095758
|
| | SCREENINGS | |
|
| | S.P. Initial Payment | 1,479.79 | 2095758
|
| | 1/4" CRUSHED ROCK | |
|
| | S.P. Initial Payment | 2,168.16 | 2106964
|
| | SCREENINGS | |
|
| | S.P. Initial Payment | 6,529.55 | 2106964
|
| | 1/4" CRUSHED ROCK | |
|
| | Total for estimate 0003: | 22,527.37 |
|
| | Total remaining for contract: | 79,499.24 |
|
---|
| | | 1. Contracted
|
---|
| | | 2. Current
|
---|
| | | 3. To date
|
---|
Item Nbr Item Code | Unit Price | | 4. This Est
|
---|
Item Description | Units | Qty | Amount
|
---|
GROUP 6 BRIDGE AT STA. 41+09.11 | | |
|
0001 0030.60 | 920.00 | 1.000 | 920.00
|
MOBILIZATION | LS | 1.000 | 920.00
|
| | 1.000 | 920.00
|
| | 0.000 | 0.00
|
| | |
|
0002 6010.26 | 1,500.00 | 13.000 | 19,500.00
|
CLASS 47BD-4000 CONCRETE FOR BRIDGE | CY | 13.000 | 19,500.00
|
| | 13.000 | 19,500.00
|
| | 0.000 | 0.00
|
| | |
|
0003 6020.00 | 1.10 | 995.000 | 1,094.50
|
REINFORCING STEEL FOR BRIDGE | LB | 995.000 | 1,094.50
|
| | 995.000 | 1,094.50
|
| | 0.000 | 0.00
|
| | |
|
0004 6030.00 | 1,150.00 | 1.000 | 1,150.00
|
PREPARATION OF BRIDGE | EACH | 1.000 | 1,150.00
|
AT STA. 41+09.11 | | 1.000 | 1,150.00
|
| | 0.000 | 0.00
|
| | |
|
GROUP 6 BRIDGE AT STA. 41+09.11 | | Contracted | 22,664.50
|
| | Current | 22,664.50
|
| | In place | 22,664.50
|
| | This Estimate | 0.00
|
| | |
|
GROUP 7 GUARDRAIL | | |
|
0005 0030.70 | 920.00 | 1.000 | 920.00
|
MOBILIZATION | LS | 1.000 | 920.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0006 7011.20 | 13.27 | 87.500 | 1,161.13
|
W-BEAM GUARDRAIL | LF | 87.500 | 1,161.13
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0007 7017.00 | 2.16 | 425.000 | 918.00
|
REMOVE GUARDRAIL | LF | 425.000 | 918.00
|
| | 216.000 | 466.56
|
| | 0.000 | 0.00
|
| | |
|
0008 7020.00 | 1,096.00 | 4.000 | 4,384.00
|
BRIDGE APPROACH SECTIONS | EACH | 4.000 | 4,384.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0009 7024.27 | 1,666.00 | 4.000 | 6,664.00
|
GUARDRAIL END TREATMENT, TYPE II | EACH | 4.000 | 6,664.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
GROUP 7 GUARDRAIL | | Contracted | 14,047.13
|
| | Current | 14,047.13
|
| | In place | 466.56
|
| | This Estimate | 0.00
|
| | |
|
GROUP 9 BITUMINOUS | | |
|
0011 L020.00 | 2.00 | 574.200 | 1,148.40
|
EROSION CONTROL | SY | 574.200 | 1,148.40
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0015 0030.90 | 578.35 | 1.000 | 578.35
|
MOBILIZATION | LS | 1.000 | 578.35
|
| | 0.080 | 46.27
|
| | 0.000 | 0.00
|
| | |
|
0016 1009.00 | 300.00 | 1.000 | 300.00
|
GENERAL CLEARING AND GRUBBING | LS | 1.000 | 300.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0017 1030.00 | 22.00 | 45.000 | 990.00
|
EARTHWORK MEASURED IN EMBANKMENT | CY | 45.000 | 990.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0021 9005.30 | 21.09 | 90.000 | 1,898.10
|
ASPHALTIC CONCRETE, TYPE SP2(0.5) | TON | 90.000 | 1,898.10
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0024 9021.01 | 170.00 | 4.860 | 826.20
|
PERFORMANCE GRADED BINDER (64-22) | TON | 4.860 | 826.20
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0025 9053.00 | 1.00 | 150.000 | 150.00
|
TACK COAT | GAL | 150.000 | 150.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0033 9188.50 | 20.00 | 204.000 | 4,080.00
|
SURFACING UNDER GUARDRAIL | SY | 204.000 | 4,080.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
GROUP 9 BITUMINOUS | | Contracted | 9,971.05
|
| | Current | 9,971.05
|
| | In place | 46.27
|
| | This Estimate | 0.00
|
| | |
|
GROUP 10 GENERAL ITEMS | | |
|
0034 0001.08 | 0.50 | 840.000 | 420.00
|
BARRICADE, TYPE II | BDAY | 840.000 | 420.00
|
| | 638.000 | 319.00
|
| | 120.000 | 60.00
|
| | |
|
0035 0001.10 | 2.50 | 252.000 | 630.00
|
BARRICADE, TYPE III | BDAY | 252.000 | 630.00
|
| | 200.000 | 500.00
|
| | 96.000 | 240.00
|
| | |
|
0036 0001.30 | 2.50 | 42.000 | 105.00
|
TYPE B HIGH INTENSITY WARNING LIGHT | LDAY | 42.000 | 105.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0038 0001.90 | 0.50 | 378.000 | 189.00
|
SIGN DAY | EACH | 378.000 | 189.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0039 0003.10 | 175.00 | 30.000 | 5,250.00
|
FLAGGING | DAY | 30.000 | 5,250.00
|
| | 7.000 | 1,225.00
|
| | 0.000 | 0.00
|
| | |
|
0041 0010.04 | 1,500.00 | 0.200 | 300.00
|
FIELD OFFICE | EACH | 0.200 | 300.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0042 0030.00 | 833.33 | 1.000 | 833.33
|
MOBILIZATION | LS | 1.000 | 833.33
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
GROUP 10 GENERAL ITEMS | | Contracted | 7,727.33
|
| | Current | 7,727.33
|
| | In place | 2,044.00
|
| | This Estimate | 300.00
|
| | |
|
GROUP 9 BITUMINOUS | | |
|
0010 L001.02 | 352.00 | 20.000 | 7,040.00
|
SEEDING, TYPE B | ACRE | 20.000 | 7,040.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0012 L032.75 | 65.00 | 45.000 | 2,925.00
|
MULCH | TON | 45.000 | 2,925.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0013 0002.55 | 7.00 | 733.000 | 5,131.00
|
OVERLAY BROKEN LINES | STA | 733.000 | 5,131.00
|
| | 1,406.540 | 9,845.78
|
| | 775.930 | 5,431.51
|
| | |
|
0014 0002.60 | 8.00 | 1,466.000 | 11,728.00
|
OVERLAY SOLID LINES | STA | 1,466.000 | 11,728.00
|
| | 1,516.150 | 12,129.20
|
| | 775.930 | 6,207.44
|
| | |
|
0015 0030.90 | 23,706.07 | 1.000 | 23,706.07
|
MOBILIZATION | LS | 1.000 | 23,706.07
|
| | 1.000 | 23,706.07
|
| | 0.000 | 0.00
|
| | |
|
0016 1009.00 | 300.00 | 1.000 | 300.00
|
GENERAL CLEARING AND GRUBBING | LS | 1.000 | 300.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0018 9000.75 | 21.09 | 100.000 | 2,109.00
|
ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE | TON | 100.000 | 2,109.00
|
SP2(0.5) | | 25.140 | 530.20
|
| | 25.140 | 530.20
|
| | |
|
0019 9004.91 | 275.00 | 363.766 | 100,035.65
|
HOT IN-PLACE RECYCLING | STA | 363.766 | 100,035.65
|
| | 352.380 | 96,904.50
|
| | 25.000 | 6,875.00
|
| | |
|
0020 9005.00 | 31.09 | 100.000 | 3,109.00
|
ASPHALTIC CONCRETE FOR PATCHING, TYPE | TON | 100.000 | 3,109.00
|
SP2(0.5) | | 64.710 | 2,011.83
|
| | 64.710 | 2,011.83
|
| | |
|
0021 9005.30 | 21.09 | 11,090.000 | 233,888.10
|
ASPHALTIC CONCRETE, TYPE SP2(0.5) | TON | 11,090.000 | 233,888.10
|
| | 10,999.720 | 231,984.09
|
| | 10,999.720 | 231,984.09
|
| | |
|
0022 9020.75 | 427.00 | 34.072 | 14,548.74
|
REJUVENATING AGENT | TON | 34.072 | 14,548.74
|
| | 14.173 | 6,051.87
|
| | 0.939 | 400.95
|
| | |
|
0023 9020.91 | 170.00 | 5.400 | 918.00
|
PERFORMANCE GRADED BINDER (64-22) FOR STATE MAINTENANCEPATCHING | TON | 5.400 | 918.00
|
| | 1.270 | 215.90
|
| | 1.270 | 215.90
|
| | |
|
0024 9021.01 | 170.00 | 604.260 | 102,724.20
|
PERFORMANCE GRADED BINDER (64-22) | TON | 604.260 | 102,724.20
|
| | 554.360 | 94,241.20
|
| | 554.360 | 94,241.20
|
| | |
|
0025 9053.00 | 1.00 | 5,340.000 | 5,340.00
|
TACK COAT | GAL | 5,340.000 | 5,340.00
|
| | 3,077.000 | 3,077.00
|
| | 3,077.000 | 3,077.00
|
| | |
|
0026 9110.01 | 65.00 | 35.000 | 2,275.00
|
RENTAL OF LOADER, FULLY OPERATED | HOUR | 35.000 | 2,275.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0027 9110.02 | 65.00 | 35.000 | 2,275.00
|
RENTAL OF MOTOR GRADER, FULLY OPERATED | HOUR | 35.000 | 2,275.00
|
| | 3.500 | 227.50
|
| | 3.500 | 227.50
|
| | |
|
0028 9110.03 | 50.00 | 35.000 | 1,750.00
|
RENTAL OF DUMP TRUCK, FULLY OPERATED | HOUR | 35.000 | 1,750.00
|
| | 1.000 | 50.00
|
| | 1.000 | 50.00
|
| | |
|
0029 9110.07 | 45.00 | 35.000 | 1,575.00
|
RENTAL OF SKID LOADER, FULLY OPERATED | HOUR | 35.000 | 1,575.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0030 9111.00 | 9.00 | 161.000 | 1,449.00
|
WATER | MGAL | 161.000 | 1,449.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0031 9170.00 | 40.00 | 644.308 | 25,772.32
|
EARTH SHOULDER CONSTRUCTION | STA | 644.308 | 25,772.32
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0032 9179.23 | 415.00 | 43.875 | 18,208.13
|
COLD MILLING, CLASS 3 | STA | 43.875 | 18,208.13
|
| | 42.730 | 17,732.95
|
| | 0.000 | 0.00
|
| | |
|
GROUP 9 BITUMINOUS | | Contracted | 566,807.21
|
| | Current | 566,807.21
|
| | In place | 498,708.09
|
| | This Estimate | 351,252.62
|
| | |
|
GROUP 10 GENERAL ITEMS | | |
|
0035 0001.10 | 2.50 | 160.000 | 400.00
|
BARRICADE, TYPE III | BDAY | 160.000 | 400.00
|
| | 128.000 | 320.00
|
| | 56.000 | 140.00
|
| | |
|
0036 0001.30 | 2.50 | 80.000 | 200.00
|
TYPE B HIGH INTENSITY WARNING LIGHT | LDAY | 80.000 | 200.00
|
| | 64.000 | 160.00
|
| | 28.000 | 70.00
|
| | |
|
0037 0001.75 | 8.50 | 160.000 | 1,360.00
|
TEMPORARY SIGN DAY | EACH | 160.000 | 1,360.00
|
| | 423.000 | 3,595.50
|
| | 174.000 | 1,479.00
|
| | |
|
0038 0001.90 | 0.50 | 2,800.000 | 1,400.00
|
SIGN DAY | EACH | 2,800.000 | 1,400.00
|
| | 1,982.000 | 991.00
|
| | 938.000 | 469.00
|
| | |
|
0039 0003.10 | 175.00 | 54.000 | 9,450.00
|
FLAGGING | DAY | 54.000 | 9,450.00
|
| | 37.000 | 6,475.00
|
| | 18.000 | 3,150.00
|
| | |
|
0040 0003.20 | 275.00 | 7.000 | 1,925.00
|
FURNISHING AND OPERATING PILOT VEHICLE | DAY | 7.000 | 1,925.00
|
| | 17.000 | 4,675.00
|
| | 8.500 | 2,337.50
|
| | |
|
0041 0010.04 | 1,500.00 | 0.200 | 300.00
|
FIELD OFFICE | EACH | 0.200 | 300.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0042 0030.00 | 916.67 | 1.000 | 916.67
|
MOBILIZATION | LS | 1.000 | 916.67
|
| | 1.000 | 916.67
|
| | 0.000 | 0.00
|
| | |
|
GROUP 10 GENERAL ITEMS | | Contracted | 15,951.67
|
| | Current | 15,951.67
|
| | In place | 17,133.17
|
| | This Estimate | 7,645.50
|
| | |
|
GROUP 9 BITUMINOUS | | |
|
0010 L001.02 | 352.00 | 13.000 | 4,576.00
|
SEEDING, TYPE B | ACRE | 13.000 | 4,576.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0012 L032.75 | 65.00 | 29.000 | 1,885.00
|
MULCH | TON | 29.000 | 1,885.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0013 0002.55 | 7.00 | 750.000 | 5,250.00
|
OVERLAY BROKEN LINES | STA | 750.000 | 5,250.00
|
| | 756.860 | 5,298.02
|
| | 647.260 | 4,530.82
|
| | |
|
0014 0002.60 | 8.00 | 1,500.000 | 12,000.00
|
OVERLAY SOLID LINES | STA | 1,500.000 | 12,000.00
|
| | 787.160 | 6,297.28
|
| | 647.260 | 5,178.08
|
| | |
|
0015 0030.90 | 23,995.15 | 1.000 | 23,995.15
|
MOBILIZATION | LS | 1.000 | 23,995.15
|
| | 1.000 | 23,995.15
|
| | 0.905 | 21,715.61
|
| | |
|
0016 1009.00 | 300.00 | 1.000 | 300.00
|
GENERAL CLEARING AND GRUBBING | LS | 1.000 | 300.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0018 9000.75 | 21.09 | 100.000 | 2,109.00
|
ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE | TON | 100.000 | 2,109.00
|
SP2(0.5) | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0019 9004.91 | 275.00 | 368.246 | 101,267.65
|
HOT IN-PLACE RECYCLING | STA | 368.246 | 101,267.65
|
| | 362.650 | 99,728.75
|
| | 323.000 | 88,825.00
|
| | |
|
0020 9005.00 | 31.09 | 100.000 | 3,109.00
|
ASPHALTIC CONCRETE FOR PATCHING, TYPE | TON | 100.000 | 3,109.00
|
SP2(0.5) | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0021 9005.30 | 21.09 | 11,784.000 | 248,524.56
|
ASPHALTIC CONCRETE, TYPE SP2(0.5) | TON | 11,784.000 | 248,524.56
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0022 9020.75 | 427.00 | 37.666 | 16,083.38
|
REJUVENATING AGENT | TON | 37.666 | 16,083.38
|
| | 15.219 | 6,498.51
|
| | 13.050 | 5,572.35
|
| | |
|
0023 9020.91 | 170.00 | 5.400 | 918.00
|
PERFORMANCE GRADED BINDER (64-22) FOR STATE MAINTENANCEPATCHING | TON | 5.400 | 918.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0024 9021.01 | 170.00 | 637.520 | 108,378.40
|
PERFORMANCE GRADED BINDER (64-22) | TON | 637.520 | 108,378.40
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0025 9053.00 | 1.00 | 6,370.000 | 6,370.00
|
TACK COAT | GAL | 6,370.000 | 6,370.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0026 9110.01 | 65.00 | 35.000 | 2,275.00
|
RENTAL OF LOADER, FULLY OPERATED | HOUR | 35.000 | 2,275.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0027 9110.02 | 65.00 | 35.000 | 2,275.00
|
RENTAL OF MOTOR GRADER, FULLY OPERATED | HOUR | 35.000 | 2,275.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0028 9110.03 | 50.00 | 35.000 | 1,750.00
|
RENTAL OF DUMP TRUCK, FULLY OPERATED | HOUR | 35.000 | 1,750.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0029 9110.07 | 45.00 | 35.000 | 1,575.00
|
RENTAL OF SKID LOADER, FULLY OPERATED | HOUR | 35.000 | 1,575.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0030 9111.00 | 9.00 | 172.000 | 1,548.00
|
WATER | MGAL | 172.000 | 1,548.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0031 9170.00 | 40.00 | 688.778 | 27,551.12
|
EARTH SHOULDER CONSTRUCTION | STA | 688.778 | 27,551.12
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0032 9179.23 | 415.00 | 23.854 | 9,899.41
|
COLD MILLING, CLASS 3 | STA | 23.854 | 9,899.41
|
| | 30.620 | 12,707.30
|
| | 0.000 | 0.00
|
| | |
|
GROUP 9 BITUMINOUS | | Contracted | 581,639.67
|
| | Current | 581,639.67
|
| | In place | 154,525.01
|
| | This Estimate | 125,821.86
|
| | |
|
GROUP 10 GENERAL ITEMS | | |
|
0035 0001.10 | 2.50 | 160.000 | 400.00
|
BARRICADE, TYPE III | BDAY | 160.000 | 400.00
|
| | 128.000 | 320.00
|
| | 52.000 | 130.00
|
| | |
|
0036 0001.30 | 2.50 | 80.000 | 200.00
|
TYPE B HIGH INTENSITY WARNING LIGHT | LDAY | 80.000 | 200.00
|
| | 64.000 | 160.00
|
| | 26.000 | 65.00
|
| | |
|
0037 0001.75 | 8.50 | 160.000 | 1,360.00
|
TEMPORARY SIGN DAY | EACH | 160.000 | 1,360.00
|
| | 252.000 | 2,142.00
|
| | 104.000 | 884.00
|
| | |
|
0038 0001.90 | 0.50 | 2,800.000 | 1,400.00
|
SIGN DAY | EACH | 2,800.000 | 1,400.00
|
| | 1,824.000 | 912.00
|
| | 741.000 | 370.50
|
| | |
|
0039 0003.10 | 175.00 | 54.000 | 9,450.00
|
FLAGGING | DAY | 54.000 | 9,450.00
|
| | 17.500 | 3,062.50
|
| | 11.000 | 1,925.00
|
| | |
|
0040 0003.20 | 275.00 | 7.000 | 1,925.00
|
FURNISHING AND OPERATING PILOT VEHICLE | DAY | 7.000 | 1,925.00
|
| | 7.500 | 2,062.50
|
| | 5.500 | 1,512.50
|
| | |
|
0041 0010.04 | 1,500.00 | 0.200 | 300.00
|
FIELD OFFICE | EACH | 0.200 | 300.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0042 0030.00 | 916.67 | 1.000 | 916.67
|
MOBILIZATION | LS | 1.000 | 916.67
|
| | 1.000 | 916.67
|
| | 0.000 | 0.00
|
| | |
|
GROUP 10 GENERAL ITEMS | | Contracted | 15,951.67
|
| | Current | 15,951.67
|
| | In place | 9,575.67
|
| | This Estimate | 4,887.00
|
| | |
|
GROUP 9 BITUMINOUS | | |
|
0010 L001.02 | 352.00 | 30.000 | 10,560.00
|
SEEDING, TYPE B | ACRE | 30.000 | 10,560.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0012 L032.75 | 65.00 | 67.000 | 4,355.00
|
MULCH | TON | 67.000 | 4,355.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0013 0002.55 | 7.00 | 1,290.000 | 9,030.00
|
OVERLAY BROKEN LINES | STA | 1,290.000 | 9,030.00
|
| | 1,918.978 | 13,432.85
|
| | 192.090 | 1,344.63
|
| | |
|
0014 0002.60 | 8.00 | 2,580.000 | 20,640.00
|
OVERLAY SOLID LINES | STA | 2,580.000 | 20,640.00
|
| | 2,074.676 | 16,597.41
|
| | 217.440 | 1,739.52
|
| | |
|
0015 0030.90 | 30,875.65 | 1.000 | 30,875.65
|
MOBILIZATION | LS | 1.000 | 30,875.65
|
| | 1.000 | 30,875.65
|
| | 0.000 | 0.00
|
| | |
|
0016 1009.00 | 300.00 | 1.000 | 300.00
|
GENERAL CLEARING AND GRUBBING | LS | 1.000 | 300.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0018 9000.75 | 21.09 | 100.000 | 2,109.00
|
ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE | TON | 100.000 | 2,109.00
|
SP2(0.5) | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0019 9004.91 | 275.00 | 645.524 | 177,519.10
|
HOT IN-PLACE RECYCLING | STA | 645.524 | 177,519.10
|
| | 484.100 | 133,127.50
|
| | 14.000 | 3,850.00
|
| | |
|
0020 9005.00 | 31.09 | 100.000 | 3,109.00
|
ASPHALTIC CONCRETE FOR PATCHING, TYPE | TON | 100.000 | 3,109.00
|
SP2(0.5) | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0021 9005.30 | 21.09 | 19,890.000 | 419,480.10
|
ASPHALTIC CONCRETE, TYPE SP2(0.5) | TON | 19,890.000 | 419,480.10
|
| | 14,223.660 | 299,976.99
|
| | 820.640 | 17,307.30
|
| | |
|
0022 9020.75 | 427.00 | 62.504 | 26,689.21
|
REJUVENATING AGENT | TON | 62.504 | 26,689.21
|
| | 22.340 | 9,539.19
|
| | 0.528 | 225.46
|
| | |
|
0023 9020.91 | 170.00 | 5.400 | 918.00
|
PERFORMANCE GRADED BINDER (64-22) FOR STATE MAINTENANCEPATCHING | TON | 5.400 | 918.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0024 9021.01 | 170.00 | 1,079.460 | 183,508.20
|
PERFORMANCE GRADED BINDER (64-22) | TON | 1,079.460 | 183,508.20
|
| | 733.820 | 124,749.40
|
| | 39.980 | 6,796.60
|
| | |
|
0025 9053.00 | 1.00 | 14,440.000 | 14,440.00
|
TACK COAT | GAL | 14,440.000 | 14,440.00
|
| | 4,461.000 | 4,461.00
|
| | 88.000 | 88.00
|
| | |
|
0026 9110.01 | 65.00 | 60.000 | 3,900.00
|
RENTAL OF LOADER, FULLY OPERATED | HOUR | 60.000 | 3,900.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0027 9110.02 | 65.00 | 60.000 | 3,900.00
|
RENTAL OF MOTOR GRADER, FULLY OPERATED | HOUR | 60.000 | 3,900.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0028 9110.03 | 50.00 | 60.000 | 3,000.00
|
RENTAL OF DUMP TRUCK, FULLY OPERATED | HOUR | 60.000 | 3,000.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0029 9110.07 | 45.00 | 60.000 | 2,700.00
|
RENTAL OF SKID LOADER, FULLY OPERATED | HOUR | 60.000 | 2,700.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0030 9111.00 | 9.00 | 294.000 | 2,646.00
|
WATER | MGAL | 294.000 | 2,646.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0031 9170.00 | 40.00 | 1,177.325 | 47,093.00
|
EARTH SHOULDER CONSTRUCTION | STA | 1,177.325 | 47,093.00
|
| | 297.990 | 11,919.60
|
| | 297.990 | 11,919.60
|
| | |
|
0032 9179.23 | 415.00 | 56.860 | 23,596.90
|
COLD MILLING, CLASS 3 | STA | 56.860 | 23,596.90
|
| | 89.968 | 37,336.72
|
| | 23.510 | 9,756.65
|
| | |
|
GROUP 9 BITUMINOUS | | Contracted | 990,369.16
|
| | Current | 990,369.16
|
| | In place | 682,016.31
|
| | This Estimate | 53,027.76
|
| | |
|
GROUP 10 GENERAL ITEMS | | |
|
0035 0001.10 | 2.50 | 378.000 | 945.00
|
BARRICADE, TYPE III | BDAY | 378.000 | 945.00
|
| | 388.000 | 970.00
|
| | 154.000 | 385.00
|
| | |
|
0036 0001.30 | 2.50 | 236.000 | 590.00
|
TYPE B HIGH INTENSITY WARNING LIGHT | LDAY | 236.000 | 590.00
|
| | 242.000 | 605.00
|
| | 92.000 | 230.00
|
| | |
|
0037 0001.75 | 8.50 | 252.000 | 2,142.00
|
TEMPORARY SIGN DAY | EACH | 252.000 | 2,142.00
|
| | 965.000 | 8,202.50
|
| | 402.000 | 3,417.00
|
| | |
|
0038 0001.90 | 0.50 | 5,936.000 | 2,968.00
|
SIGN DAY | EACH | 5,936.000 | 2,968.00
|
| | 4,065.000 | 2,032.50
|
| | 1,355.000 | 677.50
|
| | |
|
0039 0003.10 | 175.00 | 90.000 | 15,750.00
|
FLAGGING | DAY | 90.000 | 15,750.00
|
| | 72.500 | 12,687.50
|
| | 18.000 | 3,150.00
|
| | |
|
0040 0003.20 | 275.00 | 11.000 | 3,025.00
|
FURNISHING AND OPERATING PILOT VEHICLE | DAY | 11.000 | 3,025.00
|
| | 23.500 | 6,462.50
|
| | 3.500 | 962.50
|
| | |
|
0041 0010.04 | 1,500.00 | 0.200 | 300.00
|
FIELD OFFICE | EACH | 0.200 | 300.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0042 0030.00 | 1,500.00 | 1.000 | 1,500.00
|
MOBILIZATION | LS | 1.000 | 1,500.00
|
| | 1.000 | 1,500.00
|
| | 0.000 | 0.00
|
| | |
|
GROUP 10 GENERAL ITEMS | | Contracted | 27,220.00
|
| | Current | 27,220.00
|
| | In place | 32,460.00
|
| | This Estimate | 8,822.00
|
| | |
|
GROUP 9 BITUMINOUS | | |
|
0010 L001.02 | 352.00 | 9.000 | 3,168.00
|
SEEDING, TYPE B | ACRE | 9.000 | 3,168.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0012 L032.75 | 65.00 | 20.000 | 1,300.00
|
MULCH | TON | 20.000 | 1,300.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0013 0002.55 | 7.00 | 629.000 | 4,403.00
|
OVERLAY BROKEN LINES | STA | 629.000 | 4,403.00
|
| | 641.900 | 4,493.30
|
| | 636.200 | 4,453.40
|
| | |
|
0014 0002.60 | 8.00 | 1,258.000 | 10,064.00
|
OVERLAY SOLID LINES | STA | 1,258.000 | 10,064.00
|
| | 646.600 | 5,172.80
|
| | 636.200 | 5,089.60
|
| | |
|
0015 0030.90 | 21,219.78 | 1.000 | 21,219.78
|
MOBILIZATION | LS | 1.000 | 21,219.78
|
| | 1.000 | 21,219.78
|
| | 0.905 | 19,203.90
|
| | |
|
0016 1009.00 | 300.00 | 1.000 | 300.00
|
GENERAL CLEARING AND GRUBBING | LS | 1.000 | 300.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0019 9004.91 | 275.00 | 314.482 | 86,482.55
|
HOT IN-PLACE RECYCLING | STA | 314.482 | 86,482.55
|
| | 318.100 | 87,477.50
|
| | 318.100 | 87,477.50
|
| | |
|
0020 9005.00 | 31.09 | 500.000 | 15,545.00
|
ASPHALTIC CONCRETE FOR PATCHING, TYPE | TON | 500.000 | 15,545.00
|
SP2(0.5) | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0021 9005.30 | 21.09 | 9,420.000 | 198,667.80
|
ASPHALTIC CONCRETE, TYPE SP2(0.5) | TON | 9,420.000 | 198,667.80
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0022 9020.75 | 427.00 | 29.456 | 12,577.71
|
REJUVENATING AGENT | TON | 29.456 | 12,577.71
|
| | 9.350 | 3,992.45
|
| | 9.350 | 3,992.45
|
| | |
|
0024 9021.01 | 170.00 | 535.680 | 91,065.60
|
PERFORMANCE GRADED BINDER (64-22) | TON | 535.680 | 91,065.60
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0025 9053.00 | 1.00 | 4,080.000 | 4,080.00
|
TACK COAT | GAL | 4,080.000 | 4,080.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0026 9110.01 | 65.00 | 30.000 | 1,950.00
|
RENTAL OF LOADER, FULLY OPERATED | HOUR | 30.000 | 1,950.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0027 9110.02 | 65.00 | 30.000 | 1,950.00
|
RENTAL OF MOTOR GRADER, FULLY OPERATED | HOUR | 30.000 | 1,950.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0028 9110.03 | 50.00 | 30.000 | 1,500.00
|
RENTAL OF DUMP TRUCK, FULLY OPERATED | HOUR | 30.000 | 1,500.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0029 9110.07 | 45.00 | 30.000 | 1,350.00
|
RENTAL OF SKID LOADER, FULLY OPERATED | HOUR | 30.000 | 1,350.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0030 9111.00 | 9.00 | 156.000 | 1,404.00
|
WATER | MGAL | 156.000 | 1,404.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0031 9170.00 | 40.00 | 624.964 | 24,998.56
|
EARTH SHOULDER CONSTRUCTION | STA | 624.964 | 24,998.56
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0032 9179.23 | 415.00 | 6.000 | 2,490.00
|
COLD MILLING, CLASS 3 | STA | 6.000 | 2,490.00
|
| | 6.261 | 2,598.32
|
| | 0.000 | 0.00
|
| | |
|
GROUP 9 BITUMINOUS | | Contracted | 484,516.00
|
| | Current | 484,516.00
|
| | In place | 124,954.15
|
| | This Estimate | 120,216.85
|
| | |
|
GROUP 10 GENERAL ITEMS | | |
|
0035 0001.10 | 2.50 | 140.000 | 350.00
|
BARRICADE, TYPE III | BDAY | 140.000 | 350.00
|
| | 136.000 | 340.00
|
| | 56.000 | 140.00
|
| | |
|
0036 0001.30 | 2.50 | 84.000 | 210.00
|
TYPE B HIGH INTENSITY WARNING LIGHT | LDAY | 84.000 | 210.00
|
| | 68.000 | 170.00
|
| | 28.000 | 70.00
|
| | |
|
0037 0001.75 | 8.50 | 112.000 | 952.00
|
TEMPORARY SIGN DAY | EACH | 112.000 | 952.00
|
| | 136.000 | 1,156.00
|
| | 56.000 | 476.00
|
| | |
|
0038 0001.90 | 0.50 | 1,764.000 | 882.00
|
SIGN DAY | EACH | 1,764.000 | 882.00
|
| | 1,360.000 | 680.00
|
| | 560.000 | 280.00
|
| | |
|
0039 0003.10 | 175.00 | 40.000 | 7,000.00
|
FLAGGING | DAY | 40.000 | 7,000.00
|
| | 15.500 | 2,712.50
|
| | 13.000 | 2,275.00
|
| | |
|
0040 0003.20 | 275.00 | 5.000 | 1,375.00
|
FURNISHING AND OPERATING PILOT VEHICLE | DAY | 5.000 | 1,375.00
|
| | 6.500 | 1,787.50
|
| | 6.500 | 1,787.50
|
| | |
|
0041 0010.04 | 1,500.00 | 0.200 | 300.00
|
FIELD OFFICE | EACH | 0.200 | 300.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0042 0030.00 | 833.33 | 1.000 | 833.33
|
MOBILIZATION | LS | 1.000 | 833.33
|
| | 1.000 | 833.33
|
| | 0.000 | 0.00
|
| | |
|
GROUP 10 GENERAL ITEMS | | Contracted | 11,902.33
|
| | Current | 11,902.33
|
| | In place | 7,679.33
|
| | This Estimate | 5,028.50
|
| | |
|
Totals for contract | | Contracted | 2,748,767.72
|
---|
| | Current | 2,748,767.72
|
---|
| | In place | 1,552,273.06
|
---|
| | This Estimate | 677,002.09
|
---|