Nebraska Department of Roads | |
---|---|
Estimate Summary to Contractor | |
Vendor ID: | 2831 MUSSELMAN AND HALL CONTRACTORS, LLC |
Contract ID: | 1504X |
Estimate Number: | 0001 |
Pay Period End Date: | 12.07.2002 |
Contract Location: | ||
IN LINCOLN | Estimate Type: | PROG |
Contractor: | ||
MUSSELMAN AND HALL CONTRACTORS, LLC | Date Let: | 12.06.2001 |
4922 E BLUE BANKS | Date Awarded: | 12.18.2001 |
Date Contract Executed: | 01.11.2002 | |
Date Notice to Proceed: | 01.11.2002 | |
KANSAS CITY MO 64130 | Date Work Began: | 11.04.2002 |
Phone: | Date Physical Work Completed: | |
(816)861-1234 | Date Accepted: | |
Escrow Agent: | ||
Surety Co: | ||
UNITED STATES FIDELITY AND GUARANTY COMPANY |
Counties |
---|
LANCASTER |
Project Number |   | PCT |   | Fed State Project Number |   | Description | |
---|---|---|---|---|---|---|---|
12504 000 |   | 0.000 |   | RD-80-9(1114) |   | BITUMINOUS |
Total to Date | Prev to Date | This Estimate | ||
Current Contract Amt | Total Earnings | $63,441.10 | $.00 | $63,441.10 |
$58,238.90 | Stockpiled Materials | $.00 | $.00 | $.00 |
Original Contract Amt | Gross Earnings | $63,441.10 | $.00 | $63,441.10 |
$58,238.90 | Retainage | $-634.41 | $.00 | $-634.41 |
Escrow Amount | $.00 | $.00 | $.00 | |
Percent Complete | Securities Encumbered | $.00 | $.00 | $.00 |
108.93% | Net Earnings | $62,806.69 | $.00 | $62,806.69 |
Liquidated Damages | $.00 | $.00 | $.00 | |
Incentives | $.00 | $.00 | $.00 | |
Disincentives | $.00 | $.00 | $.00 | |
Other Contract Adj | $.00 | $.00 | $.00 | |
Appl of Training Adj | $.00 | $.00 | $.00 | |
Training Rates Adj | $.00 | $.00 | $.00 | |
Fuel Adj | $.00 | $.00 | $.00 | |
Bituminous Adj | $.00 | $.00 | $.00 | |
Autopay Adj | $.00 | $.00 | $.00 | |
Gasoline Adj | $.00 | $.00 | $.00 | |
Other Adj | $.00 | $.00 | $.00 | |
Price Adj | $.00 | $.00 | $.00 | |
Substandard Item Adj | $.00 | $.00 | $.00 | |
Asphalt Adj | $.00 | $.00 | $.00 | |
Diesel Fuel Adj | $.00 | $.00 | $.00 | |
Petrol Adj | $.00 | $.00 | $.00 | |
Total for Adjustments | $.00 | $.00 | $.00 | |
Payment | $62,806.69 | $.00 | $62,806.69 | |
Project Manager | Div. Head/Dist. Eng. | |||
Dodson, Paul | 12.15.2002 | Sklenar, Michael J | 12.16.2002 | |
Constr. Estimate Eng. | Materials Eng. | |||
Bartos, Steve | 12.16.2002 | |||
Controller Div. Processed | ||||
Burling, Laurie | 12.16.2002 |
Detailed breakdown of stockpiled materials | ||||
---|---|---|---|---|
Total remaining for contract: | 0.00 |
1. Contracted | |||
---|---|---|---|
2. Current | |||
3. To date | |||
Item Nbr Item Code | Unit Price | 4. This Est | |
Item Description | Units | Qty | Amount |
GROUP 3 CONCRETE PAVEMENT | |||
0001 0001.08 | 0.50 | 350.000 | 175.00 |
BARRICADE, TYPE II | BDAY | 350.000 | 175.00 |
585.000 | 292.50 | ||
585.000 | 292.50 | ||
0002 0001.10 | 2.50 | 30.000 | 75.00 |
BARRICADE, TYPE III | BDAY | 30.000 | 75.00 |
0.000 | 0.00 | ||
0.000 | 0.00 | ||
0003 0001.30 | 2.50 | 20.000 | 50.00 |
TYPE B HIGH INTENSITY WARNING LIGHT | LDAY | 20.000 | 50.00 |
0.000 | 0.00 | ||
0.000 | 0.00 | ||
0004 0001.75 | 3.50 | 240.000 | 840.00 |
TEMPORARY SIGN DAY | EACH | 240.000 | 840.00 |
267.000 | 934.50 | ||
267.000 | 934.50 | ||
0005 0002.97 | 30.00 | 10.000 | 300.00 |
FLASHING ARROW PANEL | DAY | 10.000 | 300.00 |
13.000 | 390.00 | ||
13.000 | 390.00 | ||
0006 0003.10 | 125.00 | 10.000 | 1,250.00 |
FLAGGING | DAY | 10.000 | 1,250.00 |
0.000 | 0.00 | ||
0.000 | 0.00 | ||
0007 0030.30 | 4,500.00 | 1.000 | 4,500.00 |
MOBILIZATION | LS | 1.000 | 4,500.00 |
1.000 | 4,500.00 | ||
1.000 | 4,500.00 | ||
0008 3211.25 | 1.48 | 160.000 | 236.80 |
SEALING CRACKS | LF | 160.000 | 236.80 |
736.000 | 1,089.28 | ||
736.000 | 1,089.28 | ||
0009 3211.30 | 0.74 | 68,665.000 | 50,812.10 |
SEALING JOINTS | LF | 68,665.000 | 50,812.10 |
75,993.000 | 56,234.82 | ||
75,993.000 | 56,234.82 | ||
GROUP 3 CONCRETE PAVEMENT | Contracted | 58,238.90 | |
Current | 58,238.90 | ||
In place | 63,441.10 | ||
This Estimate | 63,441.10 | ||
Totals for contract | Contracted | 58,238.90 | |
Current | 58,238.90 | ||
In place | 63,441.10 | ||
This Estimate | 63,441.10 |