| | Detailed breakdown of stockpiled materials | |
|
---|
Est Nbr: | 0001 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0018 | 0030.90 | MOBILIZATION | |
|
| | S.P. Initial Payment | 14,480.00 | 16351
|
| | Payment for Contract Bond | |
|
0030 | 9005.65 | ASPHALTIC CONCRETE, TYPE SP6(0.5) | |
|
| | S.P. Initial Payment | 40,011.03 | 881140
|
| | Surfacing Gravel 1/4" Dry Chips | |
|
| | S.P. Initial Payment | 7,368.61 | 881140
|
| | Surfacing Gravel 1/4" Dry Chips Freight | |
|
| | S.P. Initial Payment | 66,313.86 | 896705
|
| | Surfacing Gravel 1/4" Dry Chips | |
|
| | S.P. Initial Payment | 12,455.73 | 896705
|
| | Surfacing Gravel 1/4" Dry Chips Freight | |
|
| | S.P. Initial Payment | 29,990.81 | 838833
|
| | Surfacing Gravel 1/4" Dry Chips | |
|
| | S.P. Initial Payment | 2,705.50 | 838833
|
| | Surfacing Gravel, 5/8" Chips | |
|
| | S.P. Initial Payment | 1,102.82 | 824077
|
| | Surfacing Gravel, 5/8" Chips | |
|
| | S.P. Initial Payment | 42,057.21 | 809723
|
| | Surfacing Gravel, 5/8" Chips | |
|
| | S.P. Initial Payment | 20,655.56 | 72306
|
| | Manufactured Sand | |
|
| | S.P. Initial Payment | 27,284.67 | 72362
|
| | Manufactured Sand | |
|
| | S.P. Initial Payment | 27,229.99 | 72410
|
| | Manufactured Sand | |
|
| | Total for estimate 0001: | 291,655.79 |
|
Est Nbr: | 0002 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0018 | 0030.90 | MOBILIZATION | |
|
| | S.P. Adjustment | -1,448.00 | 16351
|
| | Payment for Contract Bond | |
|
0030 | 9005.65 | ASPHALTIC CONCRETE, TYPE SP6(0.5) | |
|
| | S.P. Initial Payment | 68,602.74 | 937056
|
| | Surfacing Gravel 1/4" Dry Chips | |
|
| | S.P. Initial Payment | 3,378.92 | 914785
|
| | Surfacing Gravel 1/4" Dry Chips | |
|
| | S.P. Initial Payment | 853.99 | 914785
|
| | Surfacing Gravel 1/4" Dry Chips Freight | |
|
| | S.P. Initial Payment | 15,205.25 | 937056
|
| | Surfacing Gravel 1/4" Dry Chips Freight | |
|
| | Total for estimate 0002: | 86,592.90 |
|
Est Nbr: | 0004 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0018 | 0030.90 | MOBILIZATION | |
|
| | S.P. Adjustment | -2,172.00 | 16351
|
| | Payment for Contract Bond | |
|
0030 | 9005.65 | ASPHALTIC CONCRETE, TYPE SP6(0.5) | |
|
| | S.P. Adjustment | -40,011.03 | 881140
|
| | Surfacing Gravel 1/4" Dry Chips | |
|
| | S.P. Adjustment | -7,368.61 | 881140
|
| | Surfacing Gravel 1/4" Dry Chips Freight | |
|
| | S.P. Adjustment | -19,873.83 | 896705
|
| | Surfacing Gravel 1/4" Dry Chips | |
|
| | S.P. Adjustment | -2,705.50 | 838833
|
| | Surfacing Gravel, 5/8" Chips | |
|
| | S.P. Adjustment | -1,102.82 | 824077
|
| | Surfacing Gravel, 5/8" Chips | |
|
| | S.P. Adjustment | -25,686.10 | 809723
|
| | Surfacing Gravel, 5/8" Chips | |
|
| | S.P. Adjustment | -20,655.56 | 72306
|
| | Manufactured Sand | |
|
| | S.P. Adjustment | -1,702.91 | 72362
|
| | Manufactured Sand | |
|
| | Total for estimate 0004: | -121,278.36 |
|
Est Nbr: | 0005 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0030 | 9005.65 | ASPHALTIC CONCRETE, TYPE SP6(0.5) | |
|
| | S.P. Adjustment | -46,440.03 | 896705
|
| | Surfacing Gravel 1/4" Dry Chips | |
|
| | S.P. Adjustment | -12,455.73 | 896705
|
| | Surfacing Gravel 1/4" Dry Chips Freight | |
|
| | S.P. Adjustment | -29,990.81 | 838833
|
| | Surfacing Gravel 1/4" Dry Chips | |
|
| | S.P. Adjustment | -4,378.10 | 937056
|
| | Surfacing Gravel 1/4" Dry Chips | |
|
| | S.P. Adjustment | -16,371.11 | 809723
|
| | Surfacing Gravel, 5/8" Chips | |
|
| | S.P. Adjustment | -25,581.76 | 72362
|
| | Manufactured Sand | |
|
| | S.P. Adjustment | -11,639.47 | 72410
|
| | Manufactured Sand | |
|
| | Total for estimate 0005: | -146,857.01 |
|
Est Nbr: | 0006 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0018 | 0030.90 | MOBILIZATION | |
|
| | S.P. Adjustment | -3,620.00 | 16351
|
| | Payment for Contract Bond | |
|
0030 | 9005.65 | ASPHALTIC CONCRETE, TYPE SP6(0.5) | |
|
| | S.P. Adjustment | 42,606.07 | 937056
|
| | Surfacing Gravel 1/4" Dry Chips | |
|
| | S.P. Adjustment | 14,736.69 | 72410
|
| | Manufactured Sand | |
|
| | Total for estimate 0006: | 53,722.76 |
|
Est Nbr: | 0007 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0030 | 9005.65 | ASPHALTIC CONCRETE, TYPE SP6(0.5) | |
|
| | S.P. Adjustment | -33,943.49 | 937056
|
| | Surfacing Gravel 1/4" Dry Chips | |
|
| | S.P. Adjustment | -11,740.45 | 72410
|
| | Manufactured Sand | |
|
| | Total for estimate 0007: | -45,683.94 |
|
Est Nbr: | 0009 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0018 | 0030.90 | MOBILIZATION | |
|
| | S.P. Adjustment | -3,620.00 | 16351
|
| | Payment for Contract Bond | |
|
| | Total for estimate 0009: | -3,620.00 |
|
| | Total remaining for contract: | 114,532.14 |
|
---|
| | | 1. Contracted
|
---|
| | | 2. Current
|
---|
| | | 3. To date
|
---|
Item Nbr Item Code | Unit Price | | 4. This Est
|
---|
Item Description | Units | Qty | Amount
|
---|
GROUP 9 BITUMINOUS | | |
|
0001 A001.12 | 295.00 | 2.000 | 590.00
|
PULL BOX, TYPE PB-5 | EACH | 2.000 | 590.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0002 A001.95 | 1,600.00 | 1.000 | 1,600.00
|
TRAFFIC DETECTOR | EACH | 1.000 | 1,600.00
|
AT STA. 284+79 (LANE 1) | | 1.000 | 1,600.00
|
| | 1.000 | 1,600.00
|
| | |
|
0003 A001.96 | 1,600.00 | 1.000 | 1,600.00
|
TRAFFIC DETECTOR | EACH | 1.000 | 1,600.00
|
AT STA. 284+79 (LANE 2) | | 1.000 | 1,600.00
|
| | 1.000 | 1,600.00
|
| | |
|
0004 A001.97 | 1,600.00 | 1.000 | 1,600.00
|
TRAFFIC DETECTOR | EACH | 1.000 | 1,600.00
|
AT STA. 283+62 (LANE 3) | | 1.000 | 1,600.00
|
| | 1.000 | 1,600.00
|
| | |
|
0005 A001.98 | 1,600.00 | 1.000 | 1,600.00
|
TRAFFIC DETECTOR | EACH | 1.000 | 1,600.00
|
AT STA. 283+62 (LANE 4) | | 1.000 | 1,600.00
|
| | 1.000 | 1,600.00
|
| | |
|
0006 0001.08 | 0.50 | 35,000.000 | 17,500.00
|
BARRICADE, TYPE II | BDAY | 35,000.000 | 17,500.00
|
| | 15,700.000 | 7,850.00
|
| | 1,875.000 | 937.50
|
| | |
|
0007 0001.10 | 3.17 | 1,200.000 | 3,804.00
|
BARRICADE, TYPE III | BDAY | 1,200.000 | 3,804.00
|
| | 1,721.000 | 5,455.57
|
| | 365.000 | 1,157.05
|
| | |
|
0008 0001.75 | 0.26 | 3,400.000 | 884.00
|
TEMPORARY SIGN DAY | EACH | 3,400.000 | 884.00
|
| | 3,374.000 | 877.24
|
| | 159.000 | 41.34
|
| | |
|
0009 0001.90 | 3.17 | 4,000.000 | 12,680.00
|
SIGN DAY | EACH | 4,000.000 | 12,680.00
|
| | 12,401.000 | 39,311.17
|
| | 2,807.000 | 8,898.19
|
| | |
|
0010 0002.55 | 8.00 | 4,220.400 | 33,763.20
|
OVERLAY BROKEN LINES | STA | 4,220.400 | 33,763.20
|
| | 4,327.080 | 34,616.64
|
| | 0.000 | 0.00
|
| | |
|
0011 0002.60 | 8.00 | 8,772.800 | 70,182.40
|
OVERLAY SOLID LINES | STA | 8,772.800 | 70,182.40
|
| | 9,136.890 | 73,095.12
|
| | 0.000 | 0.00
|
| | |
|
0012 0002.61 | 17.00 | 1,925.000 | 32,725.00
|
PLOWABLE PAVEMENT MARKER | EACH | 1,925.000 | 32,725.00
|
| | 1,836.000 | 31,212.00
|
| | 1,836.000 | 31,212.00
|
| | |
|
0013 0002.97 | 58.03 | 140.000 | 8,124.20
|
FLASHING ARROW PANEL | DAY | 140.000 | 8,124.20
|
| | 177.000 | 10,271.31
|
| | 15.000 | 870.45
|
| | |
|
0014 0003.10 | 175.00 | 50.000 | 8,750.00
|
FLAGGING | DAY | 50.000 | 8,750.00
|
| | 51.000 | 8,925.00
|
| | 0.000 | 0.00
|
| | |
|
0015 0003.35 | 527.00 | 6.000 | 3,162.00
|
MOBILE TRAFFIC CONTROL OPERATION | DAY | 6.000 | 3,162.00
|
| | 9.500 | 5,006.50
|
| | 9.500 | 5,006.50
|
| | |
|
0016 0005.10 | 100.00 | 70.000 | 7,000.00
|
TRAFFIC CONTROL MANAGEMENT | DAY | 70.000 | 7,000.00
|
| | 86.000 | 8,600.00
|
| | 9.000 | 900.00
|
| | |
|
0017 0010.04 | 1,000.00 | 1.000 | 1,000.00
|
FIELD OFFICE | EACH | 1.000 | 1,000.00
|
| | 1.000 | 1,000.00
|
| | 0.000 | 0.00
|
| | |
|
0018 0030.90 | 213,775.00 | 1.000 | 213,775.00
|
MOBILIZATION | LS | 1.000 | 213,775.00
|
| | 0.750 | 160,331.25
|
| | 0.250 | 53,443.75
|
| | |
|
0019 3040.11 | 111.74 | 43.200 | 4,827.17
|
CONCRETE PAVEMENT REPAIR, TYPE A, FULL DEPTH | SY | 43.200 | 4,827.17
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0020 3040.12 | 101.59 | 21.400 | 2,174.03
|
CONCRETE PAVEMENT REPAIR, TYPE B, FULL DEPTH | SY | 21.400 | 2,174.03
|
| | 85.198 | 8,655.26
|
| | 0.000 | 0.00
|
| | |
|
0021 3040.13 | 95.56 | 41.300 | 3,946.63
|
CONCRETE PAVEMENT REPAIR, TYPE C, FULL DEPTH | SY | 41.300 | 3,946.63
|
| | 211.043 | 20,167.27
|
| | 0.000 | 0.00
|
| | |
|
0022 3221.15 | 101.59 | 638.400 | 64,855.06
|
CONCRETE PAVEMENT, CLASS PR-3500 | SY | 638.400 | 64,855.06
|
JOINT REPAIR | | 960.960 | 97,623.93
|
| | -100.000 | -10,159.00
|
| | |
|
0023 7490.03 | 0.31 | 151,000.000 | 46,810.00
|
4" YELLOW THERMOPLASTIC | LF | 151,000.000 | 46,810.00
|
| | 154,417.000 | 47,869.27
|
| | 154,417.000 | 47,869.27
|
| | |
|
0024 7490.04 | 0.31 | 191,050.000 | 59,225.50
|
4" WHITE THERMOPLASTIC | LF | 191,050.000 | 59,225.50
|
| | 193,043.500 | 59,843.49
|
| | 193,043.500 | 59,843.49
|
| | |
|
0025 7490.12 | 1.00 | 3,400.000 | 3,400.00
|
12" WHITE THERMOPLASTIC | LF | 3,400.000 | 3,400.00
|
| | 2,821.000 | 2,821.00
|
| | 2,821.000 | 2,821.00
|
| | |
|
0026 9000.75 | 11.79 | 100.000 | 1,179.00
|
ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE | TON | 100.000 | 1,179.00
|
SPS | | 111.990 | 1,320.36
|
| | 0.000 | 0.00
|
| | |
|
0027 9005.01 | 29.43 | 250.000 | 7,357.50
|
ASPHALTIC CONCRETE FOR PATCHING, TYPE | TON | 250.000 | 7,357.50
|
SP6 | | 33.500 | 985.91
|
| | 0.000 | 0.00
|
| | |
|
0028 9005.23 | 11.79 | 15,330.000 | 180,740.70
|
ASPHALTIC CONCRETE, TYPE SPS | TON | 15,330.000 | 180,740.70
|
| | 14,579.160 | 171,888.29
|
| | 0.000 | 0.00
|
| | |
|
0029 9005.64 | 18.88 | 35,180.000 | 664,198.40
|
ASPHALTIC CONCRETE, TYPE SP6(0.375) | TON | 35,180.000 | 664,198.40
|
| | 36,197.400 | 683,406.91
|
| | 0.000 | 0.00
|
| | |
|
0030 9005.65 | 18.70 | 55,000.000 | 1,028,500.00
|
ASPHALTIC CONCRETE, TYPE SP6(0.5) | TON | 55,000.000 | 1,028,500.00
|
| | 64,153.580 | 1,199,671.95
|
| | 0.000 | 0.00
|
| | |
|
0031 9020.92 | 170.00 | 5.400 | 918.00
|
PERFORMANCE GRADED BINDER (58-28) FOR STATE MAINTENANCEPATCHING | TON | 5.400 | 918.00
|
| | 3.680 | 625.60
|
| | 0.000 | 0.00
|
| | |
|
0032 9021.03 | 170.00 | 827.820 | 140,729.40
|
PERFORMANCE GRADED BINDER (58-28) | TON | 827.820 | 140,729.40
|
| | 462.540 | 78,631.80
|
| | 0.000 | 0.00
|
| | |
|
0033 9021.04 | 200.00 | 5,235.020 | 1,047,004.00
|
PERFORMANCE GRADED BINDER (70-28) | TON | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0034 9053.00 | 0.60 | 110,240.000 | 66,144.00
|
TACK COAT | GAL | 110,240.000 | 66,144.00
|
| | 109,400.000 | 65,640.00
|
| | 0.000 | 0.00
|
| | |
|
0035 9110.01 | 60.00 | 130.000 | 7,800.00
|
RENTAL OF LOADER, FULLY OPERATED | HOUR | 130.000 | 7,800.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0036 9110.02 | 65.00 | 130.000 | 8,450.00
|
RENTAL OF MOTOR GRADER, FULLY OPERATED | HOUR | 130.000 | 8,450.00
|
| | 3.000 | 195.00
|
| | 0.000 | 0.00
|
| | |
|
0037 9110.03 | 45.00 | 130.000 | 5,850.00
|
RENTAL OF DUMP TRUCK, FULLY OPERATED | HOUR | 130.000 | 5,850.00
|
| | 3.000 | 135.00
|
| | 0.000 | 0.00
|
| | |
|
0038 9110.07 | 45.00 | 130.000 | 5,850.00
|
RENTAL OF SKID LOADER, FULLY OPERATED | HOUR | 130.000 | 5,850.00
|
| | 3.000 | 135.00
|
| | 0.000 | 0.00
|
| | |
|
0039 9179.24 | 345.00 | 1,407.307 | 485,520.92
|
COLD MILLING, CLASS 4 | STA | 1,407.307 | 485,520.92
|
| | 1,411.339 | 486,911.97
|
| | 0.000 | 0.00
|
| | |
|
0040 9179.33 | 0.51 | 204,537.000 | 104,313.87
|
COLD MILLING, CLASS 3 | SY | 204,537.000 | 104,313.87
|
| | 169,646.687 | 86,519.81
|
| | 0.000 | 0.00
|
| | |
|
0041 9179.63 | 150.00 | 117.304 | 17,595.60
|
COLD MILLING, CLASS 3 | STA | 117.304 | 17,595.60
|
TYPE A | | 152.070 | 22,810.50
|
| | 0.000 | 0.00
|
| | |
|
0042 9185.76 | 6.80 | 2,814.000 | 19,135.20
|
RUMBLE STRIPS, ASPHALT | STA | 2,814.000 | 19,135.20
|
| | 2,754.500 | 18,730.60
|
| | 2,754.500 | 18,730.60
|
| | |
|
0043 9300.52 | 13,000.00 | 1.000 | 13,000.00
|
ASPHALT PAVEMENT SMOOTHNESS TESTING I/D | LS | 1.000 | 13,000.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
4001 9021.04 | 227.13 | 0.000 | 0.00
|
PERFORMANCE GRADED BINDER (70-28) | TON | 2,251.520 | 511,387.74
|
Perf Graded Binder (70-28) (Revised Price and Qty.) | | 1,775.650 | 403,303.38
|
| | 0.000 | 0.00
|
| | |
|
4002 9021.01 | 212.00 | 0.000 | 0.00
|
PERFORMANCE GRADED BINDER (64-22) | TON | 2,983.500 | 632,502.00
|
Perf Graded Binder (64-22) | | 2,667.120 | 565,429.44
|
| | 0.000 | 0.00
|
| | |
|
4003 7050.00 | 1,500.00 | 0.000 | 0.00
|
ADDITIONAL COMPENSATION | EACH | 1.000 | 1,500.00
|
PG Binder Verification | | 1.000 | 1,500.00
|
| | 0.000 | 0.00
|
| | |
|
4004 0005.50 | -500.00 | 0.000 | 0.00
|
TRAFFIC CONTROL MANAGEMENT ASSESSMENT | EACH | 1.000 | -500.00
|
Assessment letter dated July 30, 2003. | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
GROUP 9 BITUMINOUS | | Contracted | 4,409,864.76
|
| | Current | 4,507,750.50
|
| | In place | 4,417,773.54
|
| | This Estimate | 227,972.14
|
| | |
|
Totals for contract | | Contracted | 4,409,864.76
|
---|
| | Current | 4,507,750.50
|
---|
| | In place | 4,417,773.54
|
---|
| | This Estimate | 227,972.14
|
---|