Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:0462 WEBB CONTRACTOR, INC./L. J.
Contract ID:1607
Estimate Number:0005
Pay Period End Date:03.01.2003
Contract Location:
PLEASANT DALE SOUTHWESTEstimate Type:FINL
Contractor:
WEBB CONTRACTOR, INC./L. J.Date Let:02.17.2000
918 N 13TH STDate Awarded:03.02.2000
PO BOX 386Date Contract Executed:03.22.2000
Date Notice to Proceed:03.22.2000
GENEVA NE 68361-0386Date Work Began:07.05.2000
Phone:Date Physical Work Completed:
(402)759-4160Date Accepted:09.20.2000
Escrow Agent:
Surety Co:
UNIVERSAL SURETY COMPANY
Counties
SEWARD
Project Number PCT Fed State Project Number Description
11607 000B  0.000 STPE-BR-2980(2)  GRAD CULV
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$164,838.90$164,838.90$.00
$164,292.09Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$164,838.90$164,838.90$.00
$160,756.71Retainage$.00$-1,648.39$1,648.39
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
100.33%Net Earnings$164,838.90$163,190.51$1,648.39
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$.00$.00$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments$.00$.00$.00
Payment$164,838.90$163,190.51$1,648.39
Project ManagerDiv. Head/Dist. Eng.
Dodson, Paul03.10.2003Sklenar, Michael J03.11.2003
Constr. Estimate Eng.Materials Eng.
Davis, Carl03.27.2003Hall, David03.27.2003
Controller Div. Processed
Harring, Joyce04.04.2003
Detailed breakdown of stockpiled materials
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          L006.00 120.007.000840.00
COVER CROP SEEDING ACRE7.000840.00
7.000840.00
0.0000.00

0002                          0030.10 1,000.001.0001,000.00
MOBILIZATION LS 1.0001,000.00
1.0001,000.00
0.0000.00

0003                          1009.00 1,200.001.0001,200.00
GENERAL CLEARING AND GRUBBING LS 1.0001,200.00
1.0001,200.00
0.0000.00

0004                          1011.00 9.9929.000289.71
WATER MGAL29.000289.71
0.0000.00
0.0000.00

0005                          1030.00 3.327,945.00026,377.40
EARTHWORK MEASURED IN EMBANKMENT CY 7,945.00026,377.40
7,945.00026,377.40
0.0000.00

4002                          1900.01 0.05210.0000.00
FUEL COST ADJUSTMENT CY 7,945.000413.93
Fuel Cost Adjustment 7,945.000413.93
0.0000.00

GROUP 1 GRADINGContracted29,707.11
Current30,121.04
In place29,831.33
This Estimate0.00

GROUP 4 CULVERTS
0006                          0030.40 100.001.000100.00
MOBILIZATION LS 1.000100.00
1.000100.00
0.0000.00

0007                          4043.00 2.0068.000136.00
REMOVE CULVERT PIPE LF 68.000136.00
68.000136.00
0.0000.00

0008                          4050.01 7.00413.0002,891.00
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS CY 413.0002,891.00
413.0002,891.00
0.0000.00

0009                          4300.30 20.00121.0002,420.00
30" CULVERT PIPE LF 121.0002,420.00
121.0002,420.00
0.0000.00

0010                          4310.30 200.001.000200.00
30" FLARED-END SECTION EACH1.000200.00
1.000200.00
0.0000.00

GROUP 4 CULVERTSContracted5,747.00
Current5,747.00
In place5,747.00
This Estimate0.00

GROUP 4A CULVERT AT STA. 29+80
0011                          0030.40 6,000.001.0006,000.00
MOBILIZATION LS 1.0006,000.00
1.0006,000.00
0.0000.00

0012                          4051.01 30.00124.0003,720.00
EXCAVATION FOR BOX CULVERTS CY 151.1404,534.20
151.1404,534.20
0.0000.00

0013                          4101.06 275.00300.14082,538.50
CLASS 47B-3000 OR AX-3000 CONCRETE FOR BOX CULVERT CY 300.14082,538.50
300.14082,538.50
0.0000.00

0014                          4151.00 0.5033,552.00016,776.00
REINFORCING STEEL FOR BOX CULVERT LB 33,552.00016,776.00
33,552.00016,776.00
0.0000.00

0015                          4765.03 55.00112.0006,160.00
4" PERFORATED CORRUGATED POLYETHYLENE PIPE UNDERDRAIN LF 112.0006,160.00
118.0006,490.00
0.0000.00

0016                          6040.00 7,600.001.0007,600.00
REMOVE STRUCTURE EACH1.0007,600.00
AT STA. 29+97 1.0007,600.00
0.0000.00

4001                          4051.10 27.500.0000.00
GRANULAR BACKFILL FOR BOX CULVERT CY 83.9002,307.25
9" of Granular Backfill for Box Culvert 83.9002,307.25
0.0000.00

GROUP 4A CULVERT AT STA. 29+80Contracted122,794.50
Current125,915.95
In place126,245.95
This Estimate0.00

GROUP 10 GENERAL ITEMS
0017                          0001.10 1.85828.0001,531.80
BARRICADE, TYPE III BDAY828.0001,531.80
760.0001,406.00
0.0000.00

0018                          0001.30 1.40138.000193.20
TYPE B HIGH INTENSITY WARNING LIGHT LDAY138.000193.20
760.0001,064.00
0.0000.00

0019                          0001.90 0.451,518.000683.10
SIGN DAY EACH1,518.000683.10
988.000444.60
0.0000.00

0020                          0030.00 100.001.000100.00
MOBILIZATION LS 1.000100.00
1.000100.00
0.0000.00

GROUP 10 GENERAL ITEMSContracted2,508.10
Current2,508.10
In place3,014.60
This Estimate0.00

Totals for contractContracted160,756.71
Current164,292.09
In place164,838.88
This Estimate0.00