Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:3366 D-K CONTRACTING CORPORATION
Contract ID:1634X
Estimate Number:0002
Pay Period End Date:08.30.2003
Contract Location:
JUNCTION US-136/N-4, IN BEATRICEEstimate Type:PROG
Contractor:
D-K CONTRACTING CORPORATIONDate Let:06.26.2003
800 S 10THDate Awarded:07.03.2003
PO BOX 147Date Contract Executed:07.18.2003
Date Notice to Proceed:07.18.2003
BEATRICE NE 68310Date Work Began:08.11.2003
Phone:Date Physical Work Completed:
(402)228-2381Date Accepted:
Escrow Agent:
Surety Co:
UNIVERSAL SURETY COMPANY
Counties
GAGE
Project Number PCT Fed State Project Number Description
12634 000  0.000 STPP-136-6(115)  CONCRETE PAVEMENT
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$117,224.51$53,417.94$63,806.57
$112,417.39Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$117,224.51$53,417.94$63,806.57
$112,417.39Retainage$-1,172.25$-534.18$-638.07
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
104.28%Net Earnings$116,052.26$52,883.76$63,168.50
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$.00$.00$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments$.00$.00$.00
Payment$116,052.26$52,883.76$63,168.50
Project ManagerDiv. Head/Dist. Eng.
Preble, Rodger09.02.2003Sklenar, Michael J09.02.2003
Constr. Estimate Eng.Materials Eng.
Bartos, Steve09.02.2003
Controller Div. Processed
Burling, Laurie09.03.2003
Detailed breakdown of stockpiled materials
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 3 CONCRETE PAVEMENT
0001                          0001.08 0.50560.000280.00
BARRICADE, TYPE II BDAY560.000280.00
330.000165.00
195.00097.50

0002                          0001.75 11.008.00088.00
TEMPORARY SIGN DAY EACH8.00088.00
36.000396.00
20.000220.00

0003                          0001.90 0.55368.000202.40
SIGN DAY EACH368.000202.40
88.00048.40
64.00035.20

0004                          0002.97 44.0024.0001,056.00
FLASHING ARROW PANEL DAY 24.0001,056.00
18.000792.00
10.000440.00

0005                          0003.10 184.0010.0001,840.00
FLAGGING DAY 10.0001,840.00
15.0002,760.00
3.000552.00

0006                          0030.30 12,547.481.00012,547.48
MOBILIZATION LS 1.00012,547.48
1.00012,547.48
1.00012,547.48

0007                          1009.00 896.001.000896.00
GENERAL CLEARING AND GRUBBING LS 1.000896.00
1.000896.00
1.000896.00

0008                          1010.01 6.17109.000672.53
EXCAVATION (ESTABLISHED QUANTITY) CY 109.000672.53
109.000672.53
109.000672.53

0009                          1101.00 11.2010.000112.00
REMOVE PAVEMENT SY 10.000112.00
21.240237.89
21.240237.89

0010                          1106.00 4.5037.000166.50
REMOVE DRIVEWAY SY 37.000166.50
36.330163.49
36.330163.49

0011                          1107.00 4.5063.000283.50
REMOVE WALK SY 63.000283.50
71.540321.93
71.540321.93

0012                          1108.00 2.87125.000358.75
REMOVE COMBINATION CURB AND GUTTER LF 125.000358.75
49.150141.06
49.150141.06

0013                          3008.05 8.4049.000411.60
TIE BARS EACH49.000411.60
102.000856.80
46.000386.40

0014                          3016.21 48.8969.0003,373.41
CONCRETE CLASS 47B-3000 SIDEWALKS SY 69.0003,373.41
76.9003,759.64
76.9003,759.64

0015                          3020.24 49.3039.0001,922.70
CONCRETE CLASS 47B-3500 DRIVEWAY SY 39.0001,922.70
38.9401,919.74
38.9401,919.74

0016                          3040.13 89.30396.30035,389.59
CONCRETE PAVEMENT REPAIR, TYPE C, FULL DEPTH SY 396.30035,389.59
830.70074,181.51
271.90024,280.67

0017                          3075.52 42.30163.0006,894.90
10" CONCRETE PAVEMENT, CLASS 47B-3500 SY 163.0006,894.90
158.1906,691.44
158.1906,691.44

0018                          8029.04 2.10202.000424.20
AGGREGATE FOUNDATION COURSE 4" SY 202.000424.20
0.0000.00
0.0000.00

0019                          9170.00 216.002.217478.87
EARTH SHOULDER CONSTRUCTION STA 2.217478.87
0.0000.00
0.0000.00

0020                          9173.20 2.38202.000480.76
SUBGRADE PREPARATION SY 202.000480.76
173.790413.62
173.790413.62

0021                          A001.01 530.003.0001,590.00
PULL BOX, TYPE PB-1 EACH3.0001,590.00
3.0001,590.00
3.0001,590.00

0022                          A003.10 670.008.0005,360.00
TRAFFIC SIGNAL, TYPE TS-1 EACH8.0005,360.00
0.0000.00
0.0000.00

0023                          A003.20 605.001.000605.00
TRAFFIC SIGNAL, TYPE TS-1A EACH1.000605.00
0.0000.00
0.0000.00

0024                          A006.15 515.008.0004,120.00
PEDESTRIAN SIGNAL, TYPE PS-1 EACH8.0004,120.00
0.0000.00
0.0000.00

0025                          A006.70 105.004.000420.00
PEDESTRIAN PUSHBUTTON, TYPE PPB EACH4.000420.00
0.0000.00
0.0000.00

0026                          A007.00 115.004.000460.00
VEHICLE DETECTOR, TYPE B PREFORMED EACH4.000460.00
4.000460.00
2.000230.00

0027                          A009.29 1,525.003.0004,575.00
STREET LIGHTING UNIT, TYPE SL-BT-40-6-0.25 EACH3.0004,575.00
0.7501,143.75
0.7501,143.75

0028                          A011.24 5,015.001.0005,015.00
COMBINATION MAST ARM SIGNAL AND LIGHTING POLE,TYPE CMP 30-12 EACH1.0005,015.00
0.2001,003.00
0.2001,003.00

0029                          A016.50 4,045.001.0004,045.00
MAST ARM SIGNAL POLE, TYPE MP-30 EACH1.0004,045.00
0.200809.00
0.200809.00

0030                          A016.55 4,340.001.0004,340.00
MAST ARM SIGNAL POLE, TYPE MP-35 EACH1.0004,340.00
0.200868.00
0.200868.00

0031                          A016.75 5,530.001.0005,530.00
MAST ARM SIGNAL POLE, TYPE MP-55 EACH1.0005,530.00
0.2001,106.00
0.2001,106.00

0032                          A020.10 835.001.000835.00
LIGHTING CONTROL CENTER, TYPE D EACH1.000835.00
0.0000.00
0.0000.00

0033                          A070.08 10.0096.000960.00
1 1/2-INCH CONDUIT, JACKED LF 96.000960.00
68.000680.00
68.000680.00

0034                          A070.10 2.45137.000335.65
1 1/2-INCH CONDUIT IN TRENCH LF 137.000335.65
143.500351.58
143.500351.58

0035                          A070.13 3.00162.000486.00
2" CONDUIT IN TRENCH LF 162.000486.00
107.800323.40
107.800323.40

0036                          A072.10 4.0045.000180.00
1 1/2-INCH CONDUIT UNDER ROADWAY LF 45.000180.00
73.000292.00
73.000292.00

0037                          A072.14 4.25119.000505.75
2-INCH CONDUIT UNDER ROADWAY LF 119.000505.75
119.000505.75
119.000505.75

0038                          A074.18 13.0080.0001,040.00
3-INCH CONDUIT, JACKED LF 80.0001,040.00
80.0001,040.00
80.0001,040.00

0039                          A077.12 0.80341.000272.80
2/C #14 AWG TRAFFIC SIGNAL CABLE LF 341.000272.80
0.0000.00
0.0000.00

0040                          A077.22 1.70341.000579.70
12/C #14 AWG TRAFFIC SIGNAL CABLE LF 341.000579.70
0.0000.00
0.0000.00

0041                          A079.01 0.85166.000141.10
2/C #14 AWG DETECTOR LEAD-IN CABLE LF 166.000141.10
0.0000.00
0.0000.00

0042                          A079.50 0.90361.000324.90
GROUNDING CONDUCTOR LF 361.000324.90
0.0000.00
0.0000.00

0043                          A079.55 1.15200.000230.00
SERVICE CABLE LF 200.000230.00
0.0000.00
0.0000.00

0044                          A080.22 0.85278.000236.30
STREET LIGHTING CABLE, NO. 6 BARE LF 278.000236.30
0.0000.00
0.0000.00

0045                          A080.24 1.00556.000556.00
STREET LIGHTING CABLE, NO. 6 USE LF 556.000556.00
0.0000.00
0.0000.00

0046                          A500.20 875.001.000875.00
INSTALL TRAFFIC SIGNAL CONTROLLER, TYPE TC-170 EACH1.000875.00
0.10087.50
0.10087.50

0047                          L010.00 8.00115.000920.00
SODDING SY 115.000920.00
0.0000.00
0.0000.00

GROUP 3 CONCRETE PAVEMENTContracted112,417.39
Current112,417.39
In place117,224.51
This Estimate63,806.57

Totals for contractContracted112,417.39
Current112,417.39
In place117,224.51
This Estimate63,806.57