Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:0462 WEBB CONTRACTOR, INC./L. J.
Contract ID:1669
Estimate Number:0011
Pay Period End Date:01.14.2003
Contract Location:
STAPLEHURST SOUTHEstimate Type:PROG
Contractor:
WEBB CONTRACTOR, INC./L. J.Date Let:12.06.2001
918 N 13TH STDate Awarded:12.27.2001
PO BOX 386Date Contract Executed:01.18.2002
Date Notice to Proceed:01.18.2002
GENEVA NE 68361-0386Date Work Began:
Phone:Date Physical Work Completed:
(402)759-4160Date Accepted:
Escrow Agent:
Surety Co:
UNIVERSAL SURETY COMPANY
Counties
SEWARD
Project Number PCT Fed State Project Number Description
11669 000  0.000 BRO-7080(22)  GR CULV BR GDRL
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$406,233.83$390,979.22$15,254.61
$408,810.98Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$406,233.83$390,979.22$15,254.61
$406,932.53Retainage$-4,062.34$-3,909.79$-152.55
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
99.37%Net Earnings$402,171.49$387,069.43$15,102.06
Liquidated Damages-$2,256.00-$1,880.00-$376.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$620.21$620.21$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments-$1,635.79-$1,259.79-$376.00
Payment$400,535.70$385,809.64$14,726.06
Project ManagerDiv. Head/Dist. Eng.
England, Jim01.16.2003Sklenar, Michael J01.16.2003
Constr. Estimate Eng.Materials Eng.
Bartos, Steve01.17.2003
Controller Div. Processed
Burling, Laurie01.17.2003
Detailed breakdown of stockpiled materials
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          L006.00 200.009.0001,800.00
COVER CROP SEEDING ACRE9.0001,800.00
9.0001,800.00
0.0000.00

0002                          0030.10 4,750.001.0004,750.00
MOBILIZATION LS 1.0004,750.00
1.0004,750.00
0.0000.00

0003                          1000.00 60.0015.000900.00
LARGE TREE REMOVAL EACH15.000900.00
19.0001,140.00
0.0000.00

0004                          1009.00 2,300.001.0002,300.00
GENERAL CLEARING AND GRUBBING LS 1.0002,300.00
1.0002,300.00
0.0000.00

0005                          1010.01 1.3428,342.00037,978.28
EXCAVATION (ESTABLISHED QUANTITY) CY 28,342.00037,978.28
28,342.00037,978.28
0.0000.00

0006                          1011.00 10.00105.0001,050.00
WATER MGAL105.0001,050.00
0.0000.00
0.0000.00

0007                          1102.00 3.2072.000230.40
REMOVE ASPHALT SURFACE SY 72.000230.40
0.0000.00
0.0000.00

0008                          1300.48 30.65294.0009,011.10
48" DRIVEWAY CULVERT PIPE LF 294.0009,011.10
294.0009,011.10
168.0005,149.20

0009                          1305.30 15.6536.000563.40
30" ROUND EQUIVALENT DRIVEWAY CULVERT PIPE LF 36.000563.40
36.000563.40
0.0000.00

0010                          1305.48 31.65204.0006,456.60
48" ROUND EQUIVALENT DRIVEWAY CULVERT PIPE LF 204.0006,456.60
204.0006,456.60
0.0000.00

GROUP 1 GRADINGContracted65,039.78
Current65,039.78
In place63,999.38
This Estimate5,149.20

GROUP 4 CULVERTS
0011                          0030.40 1,200.001.0001,200.00
MOBILIZATION LS 1.0001,200.00
1.0001,200.00
0.0000.00

0012                          4040.00 125.002.000250.00
REMOVE HEADWALLS FROM CULVERTS EACH2.000250.00
2.000250.00
0.0000.00

0013                          4043.00 3.50222.000777.00
REMOVE CULVERT PIPE LF 222.000777.00
223.000780.50
0.0000.00

0014                          4050.01 10.001,143.00011,430.00
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS CY 1,143.00011,430.00
1,159.00011,590.00
0.0000.00

0015                          4100.06 660.0010.6006,996.00
CLASS 47B-3000 OR AX-3000 CONCRETE FOR HEADWALL CY 10.6006,996.00
10.6006,996.00
0.0000.00

0016                          4150.00 1.001,100.0001,100.00
REINFORCING STEEL FOR HEADWALL LB 1,100.0001,100.00
1,100.0001,100.00
0.0000.00

0017                          4200.36 1,300.003.0003,900.00
36" AUTOMATIC FLOOD CONTROL GATE EACH3.0003,900.00
3.0003,900.00
0.0000.00

0018                          4200.48 2,800.003.0008,400.00
48" AUTOMATIC FLOOD CONTROL GATE EACH3.0008,400.00
3.0008,400.00
0.0000.00

0019                          4300.30 22.50104.0002,340.00
30" CULVERT PIPE LF 104.0002,340.00
104.0002,340.00
0.0000.00

0020                          4300.36 28.00208.0005,824.00
36" CULVERT PIPE LF 208.0005,824.00
208.0005,824.00
0.0000.00

0021                          4300.42 38.0042.0001,596.00
42" CULVERT PIPE LF 42.0001,596.00
42.0001,596.00
0.0000.00

0022                          4300.48 42.00274.00011,508.00
48" CULVERT PIPE LF 274.00011,508.00
274.00011,508.00
0.0000.00

0023                          4305.36 29.5076.0002,242.00
36" ROUND EQUIVALENT CULVERT PIPE LF 76.0002,242.00
76.0002,242.00
0.0000.00

0024                          4310.30 260.004.0001,040.00
30" FLARED-END SECTION EACH4.0001,040.00
4.0001,040.00
0.0000.00

0025                          4310.36 370.002.000740.00
36" FLARED-END SECTION EACH2.000740.00
2.000740.00
0.0000.00

0026                          4310.42 700.002.0001,400.00
42" FLARED-END SECTION EACH2.0001,400.00
2.0001,400.00
0.0000.00

0027                          4310.48 780.004.0003,120.00
48" FLARED-END SECTION EACH4.0003,120.00
4.0003,120.00
0.0000.00

0028                          4320.36 350.004.0001,400.00
36" ROUND EQUIVALENT FLARED-END SECTION EACH4.0001,400.00
4.0001,400.00
0.0000.00

601                           4051.12 27.320.0000.00
GRANULAR MATERIAL FOR FOUNDATIONS OF BOX CULVERTS CY 7.000191.24
STA 38+55, 38'RT-38+91'RT. 7.000191.24
0.0000.00

602                           4051.12 27.320.0000.00
GRANULAR MATERIAL FOR FOUNDATIONS OF BOX CULVERTS CY 9.000245.88
22+85 TWIN CULVERT PIPE 9.000245.88
0.0000.00

GROUP 4 CULVERTSContracted65,263.00
Current65,700.12
In place65,863.62
This Estimate0.00

GROUP 6 BRIDGE AT STA. 41+60
0029                          0030.60 20,000.001.00020,000.00
MOBILIZATION LS 1.00020,000.00
1.00020,000.00
0.0000.00

0030                          1043.50 2.001,746.0003,492.00
RIPRAP FILTER FABRIC SY 1,746.0003,492.00
1,746.0003,492.00
93.000186.00

0031                          6000.10 2,000.001.0002,000.00
ABUTMENT NO.1 EXCAVATION LS 1.0002,000.00
1.0002,000.00
0.0000.00

0032                          6000.11 2,000.001.0002,000.00
ABUTMENT NO.2 EXCAVATION LS 1.0002,000.00
1.0002,000.00
0.0000.00

0033                          6001.50 8,000.001.0008,000.00
BENT NO.1 EXCAVATION LS 1.0008,000.00
1.0008,000.00
0.0000.00

0034                          6001.51 8,000.001.0008,000.00
BENT NO.2 EXCAVATION LS 1.0008,000.00
1.0008,000.00
0.0000.00

0035                          6010.22 280.00222.10062,188.00
CLASS 47B-3000 CONCRETE FOR BRIDGE CY 222.10062,188.00
222.10062,188.00
0.0000.00

0036                          6010.26 300.00142.80042,840.00
CLASS 47BD-4000 CONCRETE FOR BRIDGE CY 142.80042,840.00
142.80042,840.00
0.0000.00

0037                          6020.00 0.5540,385.00022,211.75
REINFORCING STEEL FOR BRIDGE LB 40,385.00022,211.75
40,385.00022,211.76
0.0000.00

0038                          6040.00 7,000.001.0007,000.00
REMOVE STRUCTURE EACH1.0007,000.00
AT STA. 41+59 1.0007,000.00
0.0000.00

0039                          6080.00 3.002,190.0006,570.00
STRUCTURAL STEEL FOR SUBSTRUCTURE LB 2,190.0006,570.00
2,190.0006,570.00
0.0000.00

0040                          6105.02 32.001,319.00042,208.00
ROCK RIPRAP, TYPE B TON 1,319.00042,208.00
1,319.15042,212.80
83.0002,656.00

0041                          6210.12 24.001,280.00030,720.00
HP 10"X42# STEEL PILING LF 1,280.00030,720.00
1,280.00030,720.00
295.0007,080.00

603                           4051.12 27.320.0000.00
GRANULAR MATERIAL FOR FOUNDATIONS OF BOX CULVERTS CY 42.6001,163.83
BRIDGE BENTS AT STA 41+42 & 41+78 42.6001,163.83
0.0000.00

GROUP 6 BRIDGE AT STA. 41+60Contracted257,229.75
Current258,393.58
In place258,398.39
This Estimate9,922.00

GROUP 7 GUARDRAIL
0042                          0030.70 750.001.000750.00
MOBILIZATION LS 1.000750.00
1.000750.00
0.0000.00

0043                          7020.00 1,600.004.0006,400.00
BRIDGE APPROACH SECTIONS EACH4.0006,400.00
4.0006,400.00
0.0000.00

0044                          7021.45 1,600.004.0006,400.00
BREAKAWAY CABLE TERMINAL EACH4.0006,400.00
4.0006,400.00
0.0000.00

GROUP 7 GUARDRAILContracted13,550.00
Current13,550.00
In place13,550.00
This Estimate0.00

GROUP 10 GENERAL ITEMS
0045                          0001.10 1.301,750.0002,275.00
BARRICADE, TYPE III BDAY1,750.0002,275.00
1,952.0002,537.60
112.000145.60

0046                          0001.30 0.90250.000225.00
TYPE B HIGH INTENSITY WARNING LIGHT LDAY250.000225.00
0.0000.00
0.0000.00

0047                          0001.90 0.401,500.000600.00
SIGN DAY EACH1,500.000600.00
732.000292.80
42.00016.80

0048                          0010.04 1,500.001.0001,500.00
FIELD OFFICE EACH1.0001,500.00
0.0000.00
0.0000.00

0049                          0030.00 1,250.001.0001,250.00
MOBILIZATION LS 1.0001,250.00
1.0001,250.00
0.0000.00

0401                          0001.99 0.750.0000.00
CONTRACTOR FURNISHED SIGN DAY EACH370.000277.50
456.000342.00
28.00021.00

GROUP 10 GENERAL ITEMSContracted5,850.00
Current6,127.50
In place4,422.40
This Estimate183.40

Totals for contractContracted406,932.53
Current408,810.98
In place406,233.79
This Estimate15,254.60