Nebraska Department of Roads | |
---|---|
Estimate Summary to Contractor | |
Vendor ID: | 3626 REALM CONSTRUCTION, INC. |
Contract ID: | 1682Y |
Estimate Number: | 0007 |
Pay Period End Date: | 07.29.2003 |
Contract Location: | ||
LINCOLN - PLATTE RIVER BRIDGE | Estimate Type: | PROG |
Contractor: | ||
REALM CONSTRUCTION, INC. | Date Let: | 03.13.2003 |
604 SE INDUSTRIAL DR | Date Awarded: | 03.20.2003 |
PO BOX 1236 | Date Contract Executed: | 03.25.2003 |
Date Notice to Proceed: | 03.25.2003 | |
BLUE SPRINGS MO 64014 | Date Work Began: | 04.17.2003 |
Phone: | Date Physical Work Completed: | |
(816)229-6620 | Date Accepted: | |
Escrow Agent: | ||
Surety Co: | ||
FIRST NATIONAL INSURANCE COMPANY OF AMERICA |
Counties |
---|
CASS |
LANCASTER |
Project Number |   | PCT |   | Fed State Project Number |   | Description | |
---|---|---|---|---|---|---|---|
12682 000 |   | 0.000 |   | RD-80-9(1139) |   | BITUMINOUS |
Total to Date | Prev to Date | This Estimate | ||
Current Contract Amt | Total Earnings | $371,608.22 | $371,608.22 | $.00 |
$375,436.22 | Stockpiled Materials | $.00 | $.00 | $.00 |
Original Contract Amt | Gross Earnings | $371,608.22 | $371,608.22 | $.00 |
$203,500.60 | Retainage | $-3,716.08 | $-3,716.08 | $.00 |
Escrow Amount | $.00 | $.00 | $.00 | |
Percent Complete | Securities Encumbered | $.00 | $.00 | $.00 |
98.98% | Net Earnings | $367,892.14 | $367,892.14 | $.00 |
Liquidated Damages | $.00 | $.00 | $.00 | |
Incentives | $.00 | $.00 | $.00 | |
Disincentives | $.00 | $.00 | $.00 | |
Other Contract Adj | $.00 | $.00 | $.00 | |
Appl of Training Adj | $.00 | $.00 | $.00 | |
Training Rates Adj | $.00 | $.00 | $.00 | |
Fuel Adj | $.00 | $.00 | $.00 | |
Bituminous Adj | $.00 | $.00 | $.00 | |
Autopay Adj | $.00 | $.00 | $.00 | |
Gasoline Adj | $.00 | $.00 | $.00 | |
Other Adj | $.00 | $.00 | $.00 | |
Price Adj | $.00 | $.00 | $.00 | |
Substandard Item Adj | $.00 | $.00 | $.00 | |
Asphalt Adj | $.00 | $.00 | $.00 | |
Diesel Fuel Adj | $.00 | $.00 | $.00 | |
Petrol Adj | $.00 | $.00 | $.00 | |
Total for Adjustments | $.00 | $.00 | $.00 | |
Payment | $367,892.14 | $367,892.14 | $.00 | |
Project Manager | Div. Head/Dist. Eng. | |||
Murillo, Ernest | 07.29.2003 | Sklenar, Michael J | 07.30.2003 | |
Constr. Estimate Eng. | Materials Eng. | |||
Hitzeman, Bill | 07.30.2003 | |||
Controller Div. Processed | ||||
Burling, Laurie | 07.30.2003 |
Detailed breakdown of stockpiled materials | ||||
---|---|---|---|---|
Total remaining for contract: | 0.00 |
1. Contracted | |||
---|---|---|---|
2. Current | |||
3. To date | |||
Item Nbr Item Code | Unit Price | 4. This Est | |
Item Description | Units | Qty | Amount |
GROUP 9 BITUMINOUS | |||
0001 0001.08 | 0.50 | 1,000.000 | 500.00 |
BARRICADE, TYPE II | BDAY | 1,000.000 | 500.00 |
3,240.000 | 1,620.00 | ||
0.000 | 0.00 | ||
0002 0001.10 | 4.00 | 267.000 | 1,068.00 |
BARRICADE, TYPE III | BDAY | 267.000 | 1,068.00 |
17.000 | 68.00 | ||
0.000 | 0.00 | ||
0003 0001.75 | 8.00 | 550.000 | 4,400.00 |
TEMPORARY SIGN DAY | EACH | 550.000 | 4,400.00 |
212.000 | 1,696.00 | ||
0.000 | 0.00 | ||
0004 0001.90 | 6.00 | 288.000 | 1,728.00 |
SIGN DAY | EACH | 288.000 | 1,728.00 |
64.000 | 384.00 | ||
0.000 | 0.00 | ||
0005 0002.97 | 600.00 | 25.000 | 15,000.00 |
FLASHING ARROW PANEL | DAY | 25.000 | 15,000.00 |
26.000 | 15,600.00 | ||
0.000 | 0.00 | ||
0006 0003.35 | 1,000.00 | 25.000 | 25,000.00 |
MOBILE TRAFFIC CONTROL OPERATION | DAY | 25.000 | 25,000.00 |
24.500 | 24,500.00 | ||
0.000 | 0.00 | ||
0007 0030.90 | 7,500.00 | 1.000 | 7,500.00 |
MOBILIZATION | LS | 1.000 | 7,500.00 |
1.000 | 7,500.00 | ||
0.000 | 0.00 | ||
0008 9140.40 | 0.34 | 436,190.000 | 148,304.60 |
CRACK SEALING BITUMINOUS SURFACING | LF | 941,883.000 | 320,240.22 |
941,883.000 | 320,240.22 | ||
0.000 | 0.00 | ||
GROUP 9 BITUMINOUS | Contracted | 203,500.60 | |
Current | 375,436.22 | ||
In place | 371,608.22 | ||
This Estimate | 0.00 | ||
Totals for contract | Contracted | 203,500.60 | |
Current | 375,436.22 | ||
In place | 371,608.22 | ||
This Estimate | 0.00 |