Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:0810 ELK HORN CONSTRUCTION CO.
Contract ID:1774
Estimate Number:0008
Pay Period End Date:08.31.2002
Contract Location:
BARNESTON SOUTHEASTEstimate Type:PROG
Contractor:
ELK HORN CONSTRUCTION CO.Date Let:12.06.2001
2243 ANDREW AVEDate Awarded:01.04.2002
PO BOX 580Date Contract Executed:01.22.2002
Date Notice to Proceed:01.22.2002
SERGEANT BLUFF IA 51054Date Work Began:
Phone:Date Physical Work Completed:
(712)943-4430Date Accepted:
Escrow Agent:
Surety Co:
MERCHANTS BONDING COMPANY (MUTUAL)
Counties
GAGE
Project Number PCT Fed State Project Number Description
11774 000  0.000 BRO-7034(16)  BRIDGE
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$395,145.60$391,911.71$3,233.89
$390,931.75Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$395,145.60$391,911.71$3,233.89
$390,395.35Retainage$-3,951.46$-3,919.12$-32.34
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
101.08%Net Earnings$391,194.14$387,992.59$3,201.55
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$36.24$36.24$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments$36.24$36.24$.00
Payment$391,230.38$388,028.83$3,201.55
Project ManagerDiv. Head/Dist. Eng.
Mueller, Gerald09.03.2002Sklenar, Michael J09.04.2002
Constr. Estimate Eng.Materials Eng.
Bartos, Steve09.05.2002
Controller Div. Processed
Burling, Laurie09.05.2002
Detailed breakdown of stockpiled materials
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 6 BRIDGE AT STA. 10+49.50
0001                          L001.01 1,910.002.0003,820.00
SEEDING, TYPE A ha 2.0003,820.00
1.2502,387.50
1.2502,387.50

0002                          L006.00 150.002.000300.00
COVER CROP SEEDING ha 2.000300.00
0.0000.00
0.0000.00

0003                          L032.75 95.0010.000950.00
MULCH Mg 10.000950.00
5.625534.38
5.625534.38

0004                          0001.10 1.252,628.0003,285.00
BARRICADE, TYPE III BDAY2,628.0003,285.00
2,232.0002,790.00
156.000195.00

0005                          0001.30 4.00438.0001,752.00
TYPE B HIGH INTENSITY WARNING LIGHT LDAY438.0001,752.00
0.0000.00
0.0000.00

0006                          0001.90 0.752,044.0001,533.00
SIGN DAY EACH2,044.0001,533.00
2,232.0001,674.00
156.000117.00

0007                          0030.60 40,000.001.00040,000.00
MOBILIZATION LS 1.00040,000.00
1.00040,000.00
0.0000.00

0008                          1009.00 2,000.001.0002,000.00
GENERAL CLEARING AND GRUBBING LS 1.0002,000.00
1.0002,000.00
0.0000.00

0009                          1011.00 3.80119.000452.20
WATER kL 119.000452.20
0.0000.00
0.0000.00

0010                          1030.00 4.916,775.00033,265.25
EARTHWORK MEASURED IN EMBANKMENT m3 6,775.00033,265.25
6,775.00033,265.25
0.0000.00

0011                          1043.50 1.64973.0001,595.72
RIPRAP FILTER FABRIC m2 973.0001,595.72
973.0001,595.72
0.0000.00

0012                          1300.24 53.489.000481.32
600 mm DRIVEWAY CULVERT PIPE m 9.000481.32
9.000481.32
0.0000.00

0013                          2009.51 400.004.0681,627.20
CRUSHED ROCK EMBEDMENT StaM4.0681,627.20
4.0681,627.20
0.0000.00

0014                          2010.03 18.50360.0006,660.00
CRUSHED ROCK SURFACE COURSE Mg 360.0006,660.00
361.4766,687.31
0.0000.00

0015                          4045.00 4,000.001.0004,000.00
REMOVE STRUCTURE EACH1.0004,000.00
AT STA. 9+76 1.0004,000.00
0.0000.00

0016                          4050.01 10.0045.000450.00
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 45.000450.00
45.000450.00
0.0000.00

0017                          4300.48 204.0028.3005,773.20
1200 mm CULVERT PIPE m 28.3005,773.20
28.8005,875.20
0.0000.00

0018                          4310.48 575.002.0001,150.00
1200 mm FLARED-END SECTION EACH2.0001,150.00
2.0001,150.00
0.0000.00

0019                          6000.10 4,000.001.0004,000.00
ABUTMENT NO.1 EXCAVATION LS 1.0004,000.00
1.0004,000.00
0.0000.00

0020                          6000.11 4,000.001.0004,000.00
ABUTMENT NO.2 EXCAVATION LS 1.0004,000.00
1.0004,000.00
0.0000.00

0021                          6010.22 500.00108.70054,350.00
CLASS 47B-20 CONCRETE FOR BRIDGE m3 108.70054,350.00
108.70054,350.00
0.0000.00

0022                          6010.26 450.00224.300100,935.00
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 224.300100,935.00
224.300100,935.00
0.0000.00

0023                          6020.00 0.9827,500.00026,950.00
REINFORCING STEEL FOR BRIDGE kg 27,500.00026,950.00
27,500.00026,950.00
0.0000.00

0024                          6040.00 12,000.001.00012,000.00
REMOVE STRUCTURE EACH1.00012,000.00
AT STA. 10+48.75 1.00012,000.00
0.0000.00

0025                          6080.00 4.00635.0002,540.00
STRUCTURAL STEEL FOR SUBSTRUCTURE kg 635.0002,540.00
635.0002,540.00
0.0000.00

0026                          6105.02 23.55947.00022,301.85
ROCK RIPRAP, TYPE B Mg 947.00022,301.85
952.42022,429.49
0.0000.00

0027                          6210.12 60.00127.4007,644.00
HP 250 mm X 62 kg STEEL PILING m 127.4007,644.00
101.0506,063.00
0.0000.00

0028                          6251.40 700.0021.00014,700.00
ROCK SOCKET m 21.00014,700.00
21.55115,085.70
0.0000.00

0029                          6251.50 750.0030.10022,575.00
DRILLED SHAFT m 30.10022,575.00
42.69532,021.25
0.0000.00

0030                          7011.20 57.2638.1002,181.61
W-BEAM GUARDRAIL m 38.1002,181.61
38.1002,181.61
0.0000.00

0031                          7020.00 1,048.504.0004,194.00
BRIDGE APPROACH SECTIONS EACH4.0004,194.00
4.0004,194.00
0.0000.00

0032                          7021.45 848.003.0002,544.00
BREAKAWAY CABLE TERMINAL EACH3.0002,544.00
3.0002,544.00
0.0000.00

0033                          7022.00 385.001.000385.00
END ANCHORAGE ASSEMBLY EACH1.000385.00
1.000385.00
0.0000.00

601                           6210.59 36.000.0000.00
PAY CUT-OFF m 14.900536.40
Section 703.05 para. 2 pay cut-off for steel piling 26.350948.60
0.0000.00

GROUP 6 BRIDGE AT STA. 10+49.50Contracted390,395.35
Current390,931.75
In place395,145.53
This Estimate3,233.88

Totals for contractContracted390,395.35
Current390,931.75
In place395,145.53
This Estimate3,233.88