| | | 1. Contracted
|
---|
| | | 2. Current
|
---|
| | | 3. To date
|
---|
Item Nbr Item Code | Unit Price | | 4. This Est
|
---|
Item Description | Units | Qty | Amount
|
---|
GROUP 6 BRIDGE AT STA. 10+49.50 | | |
|
0001 L001.01 | 1,910.00 | 2.000 | 3,820.00
|
SEEDING, TYPE A | ha | 2.000 | 3,820.00
|
| | 1.250 | 2,387.50
|
| | 1.250 | 2,387.50
|
| | |
|
0002 L006.00 | 150.00 | 2.000 | 300.00
|
COVER CROP SEEDING | ha | 2.000 | 300.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0003 L032.75 | 95.00 | 10.000 | 950.00
|
MULCH | Mg | 10.000 | 950.00
|
| | 5.625 | 534.38
|
| | 5.625 | 534.38
|
| | |
|
0004 0001.10 | 1.25 | 2,628.000 | 3,285.00
|
BARRICADE, TYPE III | BDAY | 2,628.000 | 3,285.00
|
| | 2,232.000 | 2,790.00
|
| | 156.000 | 195.00
|
| | |
|
0005 0001.30 | 4.00 | 438.000 | 1,752.00
|
TYPE B HIGH INTENSITY WARNING LIGHT | LDAY | 438.000 | 1,752.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0006 0001.90 | 0.75 | 2,044.000 | 1,533.00
|
SIGN DAY | EACH | 2,044.000 | 1,533.00
|
| | 2,232.000 | 1,674.00
|
| | 156.000 | 117.00
|
| | |
|
0007 0030.60 | 40,000.00 | 1.000 | 40,000.00
|
MOBILIZATION | LS | 1.000 | 40,000.00
|
| | 1.000 | 40,000.00
|
| | 0.000 | 0.00
|
| | |
|
0008 1009.00 | 2,000.00 | 1.000 | 2,000.00
|
GENERAL CLEARING AND GRUBBING | LS | 1.000 | 2,000.00
|
| | 1.000 | 2,000.00
|
| | 0.000 | 0.00
|
| | |
|
0009 1011.00 | 3.80 | 119.000 | 452.20
|
WATER | kL | 119.000 | 452.20
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0010 1030.00 | 4.91 | 6,775.000 | 33,265.25
|
EARTHWORK MEASURED IN EMBANKMENT | m3 | 6,775.000 | 33,265.25
|
| | 6,775.000 | 33,265.25
|
| | 0.000 | 0.00
|
| | |
|
0011 1043.50 | 1.64 | 973.000 | 1,595.72
|
RIPRAP FILTER FABRIC | m2 | 973.000 | 1,595.72
|
| | 973.000 | 1,595.72
|
| | 0.000 | 0.00
|
| | |
|
0012 1300.24 | 53.48 | 9.000 | 481.32
|
600 mm DRIVEWAY CULVERT PIPE | m | 9.000 | 481.32
|
| | 9.000 | 481.32
|
| | 0.000 | 0.00
|
| | |
|
0013 2009.51 | 400.00 | 4.068 | 1,627.20
|
CRUSHED ROCK EMBEDMENT | StaM | 4.068 | 1,627.20
|
| | 4.068 | 1,627.20
|
| | 0.000 | 0.00
|
| | |
|
0014 2010.03 | 18.50 | 360.000 | 6,660.00
|
CRUSHED ROCK SURFACE COURSE | Mg | 360.000 | 6,660.00
|
| | 361.476 | 6,687.31
|
| | 0.000 | 0.00
|
| | |
|
0015 4045.00 | 4,000.00 | 1.000 | 4,000.00
|
REMOVE STRUCTURE | EACH | 1.000 | 4,000.00
|
AT STA. 9+76 | | 1.000 | 4,000.00
|
| | 0.000 | 0.00
|
| | |
|
0016 4050.01 | 10.00 | 45.000 | 450.00
|
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS | m3 | 45.000 | 450.00
|
| | 45.000 | 450.00
|
| | 0.000 | 0.00
|
| | |
|
0017 4300.48 | 204.00 | 28.300 | 5,773.20
|
1200 mm CULVERT PIPE | m | 28.300 | 5,773.20
|
| | 28.800 | 5,875.20
|
| | 0.000 | 0.00
|
| | |
|
0018 4310.48 | 575.00 | 2.000 | 1,150.00
|
1200 mm FLARED-END SECTION | EACH | 2.000 | 1,150.00
|
| | 2.000 | 1,150.00
|
| | 0.000 | 0.00
|
| | |
|
0019 6000.10 | 4,000.00 | 1.000 | 4,000.00
|
ABUTMENT NO.1 EXCAVATION | LS | 1.000 | 4,000.00
|
| | 1.000 | 4,000.00
|
| | 0.000 | 0.00
|
| | |
|
0020 6000.11 | 4,000.00 | 1.000 | 4,000.00
|
ABUTMENT NO.2 EXCAVATION | LS | 1.000 | 4,000.00
|
| | 1.000 | 4,000.00
|
| | 0.000 | 0.00
|
| | |
|
0021 6010.22 | 500.00 | 108.700 | 54,350.00
|
CLASS 47B-20 CONCRETE FOR BRIDGE | m3 | 108.700 | 54,350.00
|
| | 108.700 | 54,350.00
|
| | 0.000 | 0.00
|
| | |
|
0022 6010.26 | 450.00 | 224.300 | 100,935.00
|
CLASS 47BD-30 CONCRETE FOR BRIDGE | m3 | 224.300 | 100,935.00
|
| | 224.300 | 100,935.00
|
| | 0.000 | 0.00
|
| | |
|
0023 6020.00 | 0.98 | 27,500.000 | 26,950.00
|
REINFORCING STEEL FOR BRIDGE | kg | 27,500.000 | 26,950.00
|
| | 27,500.000 | 26,950.00
|
| | 0.000 | 0.00
|
| | |
|
0024 6040.00 | 12,000.00 | 1.000 | 12,000.00
|
REMOVE STRUCTURE | EACH | 1.000 | 12,000.00
|
AT STA. 10+48.75 | | 1.000 | 12,000.00
|
| | 0.000 | 0.00
|
| | |
|
0025 6080.00 | 4.00 | 635.000 | 2,540.00
|
STRUCTURAL STEEL FOR SUBSTRUCTURE | kg | 635.000 | 2,540.00
|
| | 635.000 | 2,540.00
|
| | 0.000 | 0.00
|
| | |
|
0026 6105.02 | 23.55 | 947.000 | 22,301.85
|
ROCK RIPRAP, TYPE B | Mg | 947.000 | 22,301.85
|
| | 952.420 | 22,429.49
|
| | 0.000 | 0.00
|
| | |
|
0027 6210.12 | 60.00 | 127.400 | 7,644.00
|
HP 250 mm X 62 kg STEEL PILING | m | 127.400 | 7,644.00
|
| | 101.050 | 6,063.00
|
| | 0.000 | 0.00
|
| | |
|
0028 6251.40 | 700.00 | 21.000 | 14,700.00
|
ROCK SOCKET | m | 21.000 | 14,700.00
|
| | 21.551 | 15,085.70
|
| | 0.000 | 0.00
|
| | |
|
0029 6251.50 | 750.00 | 30.100 | 22,575.00
|
DRILLED SHAFT | m | 30.100 | 22,575.00
|
| | 42.695 | 32,021.25
|
| | 0.000 | 0.00
|
| | |
|
0030 7011.20 | 57.26 | 38.100 | 2,181.61
|
W-BEAM GUARDRAIL | m | 38.100 | 2,181.61
|
| | 38.100 | 2,181.61
|
| | 0.000 | 0.00
|
| | |
|
0031 7020.00 | 1,048.50 | 4.000 | 4,194.00
|
BRIDGE APPROACH SECTIONS | EACH | 4.000 | 4,194.00
|
| | 4.000 | 4,194.00
|
| | 0.000 | 0.00
|
| | |
|
0032 7021.45 | 848.00 | 3.000 | 2,544.00
|
BREAKAWAY CABLE TERMINAL | EACH | 3.000 | 2,544.00
|
| | 3.000 | 2,544.00
|
| | 0.000 | 0.00
|
| | |
|
0033 7022.00 | 385.00 | 1.000 | 385.00
|
END ANCHORAGE ASSEMBLY | EACH | 1.000 | 385.00
|
| | 1.000 | 385.00
|
| | 0.000 | 0.00
|
| | |
|
601 6210.59 | 36.00 | 0.000 | 0.00
|
PAY CUT-OFF | m | 14.900 | 536.40
|
Section 703.05 para. 2 pay cut-off for steel piling | | 26.350 | 948.60
|
| | 0.000 | 0.00
|
| | |
|
GROUP 6 BRIDGE AT STA. 10+49.50 | | Contracted | 390,395.35
|
| | Current | 390,931.75
|
| | In place | 395,145.53
|
| | This Estimate | 3,233.88
|
| | |
|
Totals for contract | | Contracted | 390,395.35
|
---|
| | Current | 390,931.75
|
---|
| | In place | 395,145.53
|
---|
| | This Estimate | 3,233.88
|
---|