Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:0574 CONSTRUCTORS, INC.
Contract ID:1934X
Estimate Number:0023
Pay Period End Date:05.30.2002
Contract Location:
LINCOLN - PLATTE RIVER SCALESEstimate Type:PROG
Contractor:
CONSTRUCTORS, INC.Date Let:06.24.1999
1815 Y STREETDate Awarded:07.13.1999
PO BOX 80268Date Contract Executed:07.20.1999
Date Notice to Proceed:07.26.1999
LINCOLN NE 68501Date Work Began:07.26.1999
Phone:Date Physical Work Completed:
(402)434-1764Date Accepted:
Escrow Agent:
Surety Co:
UNIVERSAL SURETY COMPANY
Counties
CASS
LANCASTER
Project Number PCT Fed State Project Number Description
11934 000B  0.000 EACIM-80-9(704)  GR CP CULV SEED GDRL FENCE BUILDING ELEC SIGN
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$7,473,691.28$7,469,815.69$3,875.59
$7,465,052.84Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$7,473,691.28$7,469,815.69$3,875.59
$7,203,200.00Retainage$-25,000.00$-25,000.00$.00
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
100.12%Net Earnings$7,448,691.28$7,444,815.69$3,875.59
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.01$.01$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$.00$.00$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.94$.94$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments$.95$.95$.00
Payment$7,448,692.23$7,444,816.64$3,875.59
Project ManagerDiv. Head/Dist. Eng.
Sidiqi, Abdul05.30.2002Sklenar, Michael J05.30.2002
Constr. Estimate Eng.Materials Eng.
Bartos, Steve05.31.2002
Controller Div. Processed
Burling, Laurie06.03.2002
Detailed breakdown of stockpiled materials
Est Nbr:0002
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00213075.65 280 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Initial Payment16,809.010801
Dowel bars and Baskets (280mm Pavement)
00223091.21 305 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-HE-25
S.P. Initial Payment1,190.980801
Dowels and Baskets
Total for estimate 0002:17,999.99
Est Nbr:0003
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00213075.65 280 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Adjustment-7,636.080801
Dowel bars and Baskets (280mm Pavement)
Total for estimate 0003:-7,636.08
Est Nbr:0004
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00213075.65 280 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Adjustment1,402.950801
Dowel bars and Baskets (280mm Pavement)
Total for estimate 0004:1,402.95
Est Nbr:0005
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00213075.65 280 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Adjustment-577.170801
Dowel bars and Baskets (280mm Pavement)
00223091.21 305 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-HE-25
S.P. Adjustment-594.380801
Dowels and Baskets
0082A008.73 STREET LIGHTING UNIT, TYPE SL-BT-12.2-0.3-0.20
S.P. Initial Payment31,248.0001661591
Sreet Light Unit, SL-BT-12.2-0.3-0.20
0083A008.74 STREET LIGHTING UNIT, TYPE SL-BT-12.2-0.3-0.40
S.P. Initial Payment31,248.0001661591
Street Light Unit, SL-BT-12.2-0.3-0.40
0084A009.41 STREET LIGHTING UNIT, TYPE SL-BT-13.7-0-0.00
S.P. Initial Payment1,038.0001661591
Street Light Unit, SL-BT-13.7-0.0-0.0
01167320.95 FIBER OPTIC SIGN
S.P. Initial Payment5,649.007532
Fiber Optic Signs
Total for estimate 0005:68,011.45
Est Nbr:0006
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00213075.65 280 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Adjustment-3,470.370801
Dowel bars and Baskets (280mm Pavement)
Total for estimate 0006:-3,470.37
Est Nbr:0007
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00213075.65 280 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Adjustment-2,360.960801
Dowel bars and Baskets (280mm Pavement)
Total for estimate 0007:-2,360.96
Est Nbr:0008
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00213075.65 280 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Adjustment-3,109.950801
Dowel bars and Baskets (280mm Pavement)
Total for estimate 0008:-3,109.95
Est Nbr:0009
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00213075.65 280 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Adjustment-121.950801
Dowel bars and Baskets (280mm Pavement)
00223091.21 305 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-HE-25
S.P. Adjustment-596.600801
Dowels and Baskets
Total for estimate 0009:-718.55
Est Nbr:0010
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00213075.65 280 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Adjustment-274.630801
Dowel bars and Baskets (280mm Pavement)
0082A008.73 STREET LIGHTING UNIT, TYPE SL-BT-12.2-0.3-0.20
S.P. Adjustment-8,928.0001661591
Sreet Light Unit, SL-BT-12.2-0.3-0.20
0083A008.74 STREET LIGHTING UNIT, TYPE SL-BT-12.2-0.3-0.40
S.P. Adjustment-4,464.0001661591
Street Light Unit, SL-BT-12.2-0.3-0.40
Total for estimate 0010:-13,666.63
Est Nbr:0011
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00213075.65 280 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Adjustment-381.140801
Dowel bars and Baskets (280mm Pavement)
0082A008.73 STREET LIGHTING UNIT, TYPE SL-BT-12.2-0.3-0.20
S.P. Adjustment-6,696.0001661591
Sreet Light Unit, SL-BT-12.2-0.3-0.20
0083A008.74 STREET LIGHTING UNIT, TYPE SL-BT-12.2-0.3-0.40
S.P. Adjustment-6,696.0001661591
Street Light Unit, SL-BT-12.2-0.3-0.40
Total for estimate 0011:-13,773.14
Est Nbr:0012
Item NbrItem CdItem DescAdj AmtInvoice Nbr
0083A008.74 STREET LIGHTING UNIT, TYPE SL-BT-12.2-0.3-0.40
S.P. Adjustment-3,348.0001661591
Street Light Unit, SL-BT-12.2-0.3-0.40
Total for estimate 0012:-3,348.00
Est Nbr:0013
Item NbrItem CdItem DescAdj AmtInvoice Nbr
0082A008.73 STREET LIGHTING UNIT, TYPE SL-BT-12.2-0.3-0.20
S.P. Adjustment-11,160.0001661591
Sreet Light Unit, SL-BT-12.2-0.3-0.20
0083A008.74 STREET LIGHTING UNIT, TYPE SL-BT-12.2-0.3-0.40
S.P. Adjustment-16,740.0001661591
Street Light Unit, SL-BT-12.2-0.3-0.40
Total for estimate 0013:-27,900.00
Est Nbr:0014
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01167320.95 FIBER OPTIC SIGN
S.P. Adjustment-5,649.007532
Fiber Optic Signs
Total for estimate 0014:-5,649.00
Est Nbr:0015
Item NbrItem CdItem DescAdj AmtInvoice Nbr
0082A008.73 STREET LIGHTING UNIT, TYPE SL-BT-12.2-0.3-0.20
S.P. Adjustment-4,464.0001661591
Sreet Light Unit, SL-BT-12.2-0.3-0.20
Total for estimate 0015:-4,464.00
Est Nbr:0016
Item NbrItem CdItem DescAdj AmtInvoice Nbr
0084A009.41 STREET LIGHTING UNIT, TYPE SL-BT-13.7-0-0.00
S.P. Adjustment-1,038.0001661591
Street Light Unit, SL-BT-13.7-0.0-0.0
Total for estimate 0016:-1,038.00
Est Nbr:0020
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00213075.65 280 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Closure-279.710801
Dowel bars and Baskets (280mm Pavement)
Total for estimate 0020:-279.71
Total remaining for contract:-0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          L006.00 200.0010.2002,040.00
COVER CROP SEEDING ha 10.2002,040.00
7.3601,472.00
0.0000.00

0002                          L020.10 1.8011,946.00021,502.80
EROSION CONTROL, TYPE HV m2 11,946.00021,502.80
12,897.00023,214.60
0.0000.00

0003                          L021.00 14.30222.0003,174.60
EROSION CHECKS BALE222.0003,174.60
342.0004,890.60
0.0000.00

0004                          L021.06 15.50432.0006,696.00
EROSION CHECKS, TYPE HV BALE432.0006,696.00
679.00010,524.50
0.0000.00

0005                          0030.10 22,000.001.00022,000.00
MOBILIZATION LS 1.00022,000.00
1.00022,000.00
0.0000.00

0006                          1009.00 10,500.001.00010,500.00
GENERAL CLEARING AND GRUBBING LS 1.00010,500.00
1.00010,500.00
0.0000.00

0007                          1011.00 1.151,511.0001,737.65
WATER kL 1,511.0001,737.65
0.0000.00
0.0000.00

0008                          1012.00 80.0019.0001,520.00
RIGHT-OF-WAY MARKERS EACH19.0001,520.00
22.0001,760.00
0.0000.00

0009                          1030.00 3.10151,114.000468,453.40
EARTHWORK MEASURED IN EMBANKMENT m3 151,114.000468,453.40
151,114.000468,453.40
0.0000.00

0010                          1041.00 0.4664,305.00029,580.30
SALVAGING AND PLACING TOPSOIL m2 64,305.00029,580.30
64,305.00029,580.31
0.0000.00

0011                          1101.00 6.401,332.0008,524.80
REMOVE PAVEMENT m2 1,332.0008,524.80
1,515.0339,696.22
0.0000.00

0012                          1102.00 3.904,374.00017,058.60
REMOVE ASPHALT SURFACE m2 4,374.00017,058.60
4,474.82617,451.83
0.0000.00

0013                          1123.00 5.70471.0002,684.70
REMOVE CONCRETE DITCH LINER m2 471.0002,684.70
471.0002,684.70
0.0000.00

0014                          7017.00 3.90130.000507.00
REMOVE GUARDRAIL m 130.000507.00
131.000510.90
0.0000.00

0137                          1900.00 8,709.750.0000.00
FUEL COST ADJUSTMENT LS 1.0008,709.75
Embankment 1.0008,709.75
0.0000.00

0146                          6960.02 1,312.500.0000.00
ADDITIONAL WORK LS 1.0001,312.50
Labor, Material, and Equipment Rental to Remove and Replace Granular Fill Material in area around Eastbound WIM Scale 1.0001,312.50
0.0000.00

0150                          L022.11 10.850.0000.00
FABRIC SILT FENCE-LOW POROSITY m 257.8372,797.53
Not included in original contract. 257.8372,797.53
0.0000.00

2010                          2010.03 9.700.0000.00
CRUSHED ROCK SURFACE COURSE Mg 103.4201,003.17
103.4201,003.17
0.0000.00

GROUP 1 GRADINGContracted595,979.85
Current609,802.81
In place616,562.01
This Estimate0.00

GROUP 3 CONCRETE PAVEMENT
0015                          0030.30 266,290.741.000266,290.74
MOBILIZATION LS 1.000266,290.74
1.000266,290.74
0.0000.00

0016                          1020.06 17.00100.0001,700.00
FLEXIBLE POST DELINEATOR EACH100.0001,700.00
86.0001,462.00
0.0000.00

0017                          3008.05 3.00991.0002,973.00
TIE BARS EACH991.0002,973.00
1,072.0003,216.00
0.0000.00

0018                          3016.21 29.40136.0003,998.40
CONCRETE CLASS 47B-20 SIDEWALKS m2 136.0003,998.40
128.6683,782.84
0.0000.00

0019                          3017.40 22.25112.0002,492.00
CONCRETE CLASS 47B-20 MEDIAN SURFACING m2 112.0002,492.00
171.4363,814.45
0.0000.00

0020                          3075.61 32.6033,297.0001,085,482.20
280 mm CONCRETE PAVEMENT, CLASS 47B-25 m2 33,297.0001,085,482.20
32,222.9821,050,469.22
0.0000.00

0021                          3075.65 38.0029,303.0001,113,514.00
280 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25 m2 29,303.0001,113,514.00
28,989.5691,101,603.63
0.0000.00

0022                          3091.21 51.301,334.00068,434.20
305 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-HE-25 m2 1,334.00068,434.20
1,514.41277,689.33
0.0000.00

0023                          3091.22 48.00720.00034,560.00
305 mm CONCRETE PAVEMENT, CLASS 47B-HE-25 m2 720.00034,560.00
820.13439,366.43
0.0000.00

0024                          8029.84 3.7564,654.000242,452.50
BITUMINOUS FOUNDATION COURSE 100 mm m2 64,654.000242,452.50
63,547.097238,301.63
0.0000.00

0025                          9111.00 0.501,159.000579.50
WATER kL 1,159.000579.50
671.500335.75
0.0000.00

0026                          9170.00 400.0090.84036,336.00
EARTH SHOULDER CONSTRUCTION StaM90.84036,336.00
89.27035,708.00
0.0000.00

0027                          9173.20 1.6064,654.000103,446.40
SUBGRADE PREPARATION m2 64,654.000103,446.40
62,798.167100,477.05
0.0000.00

0028                          9188.50 27.00386.00010,422.00
SURFACING UNDER GUARDRAIL m2 386.00010,422.00
391.40810,568.02
0.0000.00

0131                          3900.20 1,146.000.0000.00
ADDITIONAL COST LS 1.0001,146.00
1.0001,146.00
0.0000.00

0145                          6960.02 2,091.380.0000.00
ADDITIONAL WORK LS 1.0002,091.38
Labor, Material and Equipment Rental for Removal and Replacement of Pavement Panels adjacent to Scales 1.0002,091.38
0.0000.00

0147                          6960.02 2,132.610.0000.00
ADDITIONAL WORK LS 1.0002,132.61
Labor, Material, and Equipment Rental to re-trim Subgrade and Base at Loop 2 and Ramp 1 1.0002,132.61
0.0000.00

GROUP 3 CONCRETE PAVEMENTContracted2,972,680.94
Current2,978,050.93
In place2,938,455.08
This Estimate0.00

GROUP 4 CULVERTS
0029                          P120.30 187.0021.4004,001.80
750 mm CULVERT PIPE, TYPE 2 m 21.4004,001.80
21.4004,001.80
0.0000.00

0030                          P300.18 80.00140.20011,216.00
450 mm CULVERT PIPE, TYPE 3,4 OR 5 m 140.20011,216.00
78.2006,256.00
0.0000.00

0031                          P400.18 95.00332.00031,540.00
450 mm CULVERT PIPE, TYPE 2,5,7 OR 8 m 364.20034,599.00
359.40034,143.00
0.0000.00

0032                          P400.24 127.00160.00020,320.00
600 mm CULVERT PIPE, TYPE 2,5,7 OR 8 m 160.00020,320.00
78.0009,906.00
0.0000.00

0033                          0030.40 6,850.001.0006,850.00
MOBILIZATION LS 1.0006,850.00
1.0006,850.00
0.0000.00

0034                          4004.50 3.906,735.00026,266.50
CAST IRON GRATE AND FRAME kg 6,735.00026,266.50
6,286.00024,515.40
0.0000.00

0035                          4035.25 80.001.00080.00
REMOVE AND SALVAGE FLARED-END SECTION EACH1.00080.00
1.00080.00
0.0000.00

0036                          4040.00 125.004.000500.00
REMOVE HEADWALLS FROM CULVERTS EACH4.000500.00
2.000250.00
0.0000.00

0037                          4044.01 1,400.001.0001,400.00
PREPARATION OF STRUCTURE EACH1.0001,400.00
AT STA. 126+24.4 1.0001,400.00
0.0000.00

0038                          4050.01 9.10442.0004,022.20
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 442.0004,022.20
359.0003,266.90
0.0000.00

0039                          4051.01 13.7098.0001,342.60
EXCAVATION FOR BOX CULVERTS m3 98.0001,342.60
98.0001,342.60
0.0000.00

0040                          4101.06 365.0074.78027,294.70
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 74.78027,294.70
74.78027,294.70
0.0000.00

0041                          4105.59 820.0020.50016,810.00
CLASS 47B-20 CONCRETE FOR INLET AND JUNCTION BOX m3 20.50016,810.00
19.66316,123.66
0.0000.00

0042                          4107.07 870.000.480417.60
CLASS 47B-20 OR AX-20 CONCRETE FOR CONCRETE COLLARS m3 0.480417.60
0.0000.00
0.0000.00

0043                          4151.00 1.603,678.0005,884.80
REINFORCING STEEL FOR BOX CULVERT kg 3,678.0005,884.80
3,678.0005,884.80
0.0000.00

0044                          4155.50 1.80741.0001,333.80
REINFORCING STEEL FOR INLET AND JUNCTION BOX kg 741.0001,333.80
706.8981,272.42
0.0000.00

0045                          4157.00 3.6522.00080.30
REINFORCING STEEL FOR COLLARS kg 22.00080.30
0.0000.00
0.0000.00

0046                          4310.18 200.0014.0002,800.00
450 mm FLARED-END SECTION EACH14.0002,800.00
13.0002,600.00
0.0000.00

0047                          4310.24 240.002.000480.00
600 mm FLARED-END SECTION EACH2.000480.00
2.000480.00
0.0000.00

0048                          4461.30 170.001.000170.00
INSTALL 750 mm CONCRETE FLARED-END SECTION EACH1.000170.00
1.000170.00
0.0000.00

0139                          4035.90 115.500.0000.00
REMOVE AND REINSTALL FLARED-END SECTION EACH4.000462.00
4.000462.00
0.0000.00

GROUP 4 CULVERTSContracted162,810.30
Current166,331.30
In place146,299.28
This Estimate0.00

GROUP 4A CULVERT AT STA. 114+58.97
0049                          0030.40 3,400.001.0003,400.00
MOBILIZATION LS 1.0003,400.00
1.0003,400.00
0.0000.00

0050                          4044.00 2,100.001.0002,100.00
PREPARATION OF STRUCTURE EACH1.0002,100.00
AT STA. 114+58.97 1.0002,100.00
0.0000.00

0051                          4051.01 57.0020.0001,140.00
EXCAVATION FOR BOX CULVERTS m3 20.0001,140.00
60.1003,425.70
0.0000.00

0052                          4101.06 365.0042.56015,534.40
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 42.56015,534.40
46.58017,001.70
0.0000.00

0053                          4151.00 1.602,712.0004,339.20
REINFORCING STEEL FOR BOX CULVERT kg 2,712.0004,339.20
2,712.0004,339.20
0.0000.00

0133                          6104.00 17.890.0000.00
BROKEN CONCRETE RIPRAP Mg 57.6001,030.46
57.6001,030.46
0.0000.00

GROUP 4A CULVERT AT STA. 114+58.97Contracted26,513.60
Current27,544.06
In place31,297.06
This Estimate0.00

GROUP 5 SEEDING
0054                          L001.02 1,175.0011.20013,160.00
SEEDING, TYPE B ha 11.20013,160.00
17.30920,338.08
0.0000.00

0055                          L032.75 80.0056.0004,480.00
MULCH Mg 56.0004,480.00
83.9526,716.16
0.0000.00

0056                          0030.50 114.001.000114.00
MOBILIZATION LS 1.000114.00
1.000114.00
0.0000.00

GROUP 5 SEEDINGContracted17,754.00
Current17,754.00
In place27,168.24
This Estimate0.00

GROUP 7 GUARDRAIL
0057                          0030.70 1.001.0001.00
MOBILIZATION LS 1.0001.00
1.0001.00
0.0000.00

0058                          7011.20 32.00190.5006,096.00
W-BEAM GUARDRAIL m 190.5006,096.00
190.5006,096.00
0.0000.00

0059                          7022.00 600.002.0001,200.00
END ANCHORAGE ASSEMBLY EACH2.0001,200.00
2.0001,200.00
0.0000.00

0060                          7024.25 2,200.002.0004,400.00
GUARDRAIL END TREATMENT, TYPE I EACH2.0004,400.00
2.0004,400.00
0.0000.00

GROUP 7 GUARDRAILContracted11,697.00
Current11,697.00
In place11,697.00
This Estimate0.00

GROUP 7B FENCE
0061                          0030.71 1.001.0001.00
MOBILIZATION LS 1.0001.00
1.0001.00
0.0000.00

0062                          7100.00 6.502,930.00019,045.00
RIGHT-OF-WAY FENCE m 2,930.00019,045.00
3,132.00020,358.00
0.0000.00

0063                          7103.00 111.004.000444.00
END POSTS EACH4.000444.00
12.0001,332.00
0.0000.00

0064                          7104.00 120.0024.0002,880.00
PULL POSTS EACH24.0002,880.00
22.0002,640.00
0.0000.00

0065                          7105.00 120.008.000960.00
CORNER POSTS EACH8.000960.00
15.0001,800.00
0.0000.00

0066                          7108.00 162.004.000648.00
DRAINAGE STRUCTURE TERMINALS EACH4.000648.00
0.0000.00
0.0000.00

0132                          1111.00 3.440.0000.00
REMOVE FENCE m 2,675.0009,202.00
2,675.0009,202.00
0.0000.00

0144                          7105.94 170.890.0000.00
1.2 m GATE EACH2.000341.78
Gate for Right-of-way access at STA 114+59 2.000341.78
0.0000.00

GROUP 7B FENCEContracted23,978.00
Current33,521.78
In place35,674.78
This Estimate0.00

GROUP 8A BUILDING CONSTRUCTION
0067                          0030.80 62,000.001.00062,000.00
MOBILIZATION LS 1.00062,000.00
1.00062,000.00
0.0000.00

0068                          5500.00 695,000.001.000695,000.00
SCALE BUILDING EACH1.000695,000.00
(EB) 1.000695,000.00
0.0000.00

0069                          5500.01 695,000.001.000695,000.00
SCALE BUILDING EACH1.000695,000.00
(WB) 1.000695,000.00
0.0000.00

0070                          5500.05 12,500.001.00012,500.00
LINK BUILDING EACH1.00012,500.00
(EB) 1.00012,500.00
0.0000.00

0071                          5500.06 12,500.001.00012,500.00
LINK BUILDING EACH1.00012,500.00
(WB) 1.00012,500.00
0.0000.00

0072                          5500.10 155,000.001.000155,000.00
INSPECTION BUILDING EACH1.000155,000.00
(EB) 1.000155,000.00
0.0000.00

0073                          5500.11 155,000.001.000155,000.00
INSPECTION BUILDING EACH1.000155,000.00
(WB) 1.000155,000.00
0.0000.00

0074                          5820.55 200,000.002.000400,000.00
STATIC TRUCK SCALE EACH2.000400,000.00
2.000400,000.00
0.0000.00

0075                          5821.10 314,000.001.000314,000.00
WEIGH-IN-MOTION SYSTEM EACH1.000314,000.00
AT STA. 109+46 RT. 1.000314,000.00
0.0000.00

0076                          5821.11 314,000.001.000314,000.00
WEIGH-IN-MOTION SYSTEM EACH1.000314,000.00
AT STA. 141+43 LT. 1.000314,000.00
0.0000.00

0134                          6960.60 -2,400.000.0000.00
MATERIAL COST DIFFERENTIAL LS 1.000-2,400.00
Difference in cost of explosion proof to vapor tight lights 1.000-2,400.00
0.0000.00

0135                          4976.05 511.350.0000.00
ADDITIONAL WORK LS 1.000511.35
1.000511.35
0.0000.00

0138                          4976.05 3,570.000.0000.00
ADDITIONAL WORK LS 1.0003,570.00
Additional Laterals for WB Leach Field 1.0003,570.00
0.0000.00

0140                          6960.02 4,282.480.0000.00
ADDITIONAL WORK LS 1.0004,282.48
Steel Angle for edge protection around Inspection Pits in Inspection Building. 1.0004,282.48
0.0000.00

0141                          A900.10 262.500.0000.00
ADDITIONAL WORK EACH3.000787.50
Abandon Existing and Splice 75mm Telephone Conduit 3.000787.50
0.0000.00

0142                          6960.02 147.000.0000.00
ADDITIONAL WORK LS 1.000147.00
Relocate Telephone outlet for ATM 1.000147.00
0.0000.00

0143                          6960.02 315.000.0000.00
ADDITIONAL WORK LS 1.000315.00
Steel Stand for Water Heater on Northside 1.000315.00
0.0000.00

0148                          A900.10 11,433.000.0000.00
ADDITIONAL WORK EACH1.00011,433.00
LED Programmable Message Board for Eastbound Scale Building including Blockout work for Sidewalk. 1.00011,433.00
0.0000.00

0149                          A900.10 11,458.750.0000.00
ADDITIONAL WORK EACH1.00011,458.75
LED Programmable Message Board for Westbound Scale Building including Blockout work for Sidewalk 1.00011,458.75
0.0000.00

0155                          5879.00 1,315.650.0000.00
DOOR EACH2.0002,631.30
ADDITIONAL DOORS BETWEEN LINK BUILDINGS AND INSPECTION BUILDINGS, EB AND WB. 2.0002,631.30
0.0000.00

0165                          4764.25 5,749.910.0000.00
DRAIN TILE LS 1.0005,749.91
Drain Tile for Scale Buildings 1.0005,749.91
0.0000.00

0166                          6960.01 27,147.1950.0000.00
ADDITIONAL LS 1.00027,147.20
Structure addition to Link building 1.00027,147.20
0.0000.00

0167                          6960.01 27,147.1950.0000.00
ADDITIONAL LS 1.00027,147.20
Structure addition to Link building 1.00027,147.20
0.0000.00

0168                          6960.02 3,875.590.0000.00
ADDITIONAL WORK LS 1.0003,875.59
ADJUSTMENT OF LED MESSAGE SIGNS AND MAST ARMS, EB/WB 1.0003,875.59
1.0003,875.59

GROUP 8A BUILDING CONSTRUCTIONContracted2,815,000.00
Current2,911,656.27
In place2,911,656.28
This Estimate3,875.59

GROUP 8B ELECTRICAL
0077                          A001.01 430.0016.0006,880.00
PULL BOX, TYPE PB-1 EACH16.0006,880.00
20.0008,600.00
0.0000.00

0078                          A001.12 320.0067.00021,440.00
PULL BOX, TYPE PB-5 EACH67.00021,440.00
81.00025,920.00
0.0000.00

0079                          A001.16 365.004.0001,460.00
PULL BOX, TYPE PB-6 EACH2.000730.00
7.0002,555.00
0.0000.00

0080                          A001.17 410.0039.00015,990.00
PULL BOX, TYPE PB-7 EACH0.0000.00
0.0000.00
0.0000.00

0081                          A001.50 600.002.0001,200.00
PULL BOX EACH2.0001,200.00
TYPE 610X914X457 0.0000.00
0.0000.00

0082                          A008.73 1,400.0056.00078,400.00
STREET LIGHTING UNIT, TYPE SL-BT-12.2-0.3-0.20 EACH56.00078,400.00
56.00078,400.00
0.0000.00

0083                          A008.74 1,450.0056.00081,200.00
STREET LIGHTING UNIT, TYPE SL-BT-12.2-0.3-0.40 EACH56.00081,200.00
56.00081,200.00
0.0000.00

0084                          A009.41 1,145.002.0002,290.00
STREET LIGHTING UNIT, TYPE SL-BT-13.7-0-0.00 EACH2.0002,290.00
2.0002,290.00
0.0000.00

0085                          A010.86 815.006.0004,890.00
LOW MOUNT LIGHTING UNIT EACH6.0004,890.00
6.0004,890.00
0.0000.00

0086                          A020.17 2,560.003.0007,680.00
LIGHTING CONTROL CENTER, TYPE P EACH3.0007,680.00
3.0007,680.00
0.0000.00

0087                          A020.75 3,230.002.0006,460.00
LIGHTING CONTROL CENTER EACH2.0006,460.00
TYPE RS 2.0006,460.00
0.0000.00

0088                          A069.09 12.8038.000486.40
25 mm CONDUIT ON STRUCTURE m 38.000486.40
92.0001,177.60
0.0000.00

0089                          A069.10 24.8055.0001,364.00
38 mm CONDUIT ON STRUCTURE m 55.0001,364.00
64.0001,587.20
0.0000.00

0090                          A069.12 40.0038.0001,520.00
75 mm CONDUIT ON STRUCTURE m 38.0001,520.00
92.0003,680.00
0.0000.00

0091                          A069.14 5.355,374.00028,750.90
25 mm CONDUIT IN TRENCH m 962.0005,146.70
905.0004,841.75
0.0000.00

0092                          A070.10 6.006,756.00040,536.00
38 mm CONDUIT IN TRENCH m 11,168.00067,008.00
11,377.00068,262.00
0.0000.00

0093                          A070.14 7.302,486.00018,147.80
50 mm CONDUIT IN TRENCH m 2,486.00018,147.80
3,700.00027,010.00
0.0000.00

0094                          A070.18 10.003,556.00035,560.00
75 mm CONDUIT IN TRENCH m 3,556.00035,560.00
3,404.00034,040.00
0.0000.00

0095                          A070.22 14.26168.0002,395.68
100 mm CONDUIT IN TRENCH m 168.0002,395.68
176.0002,509.76
0.0000.00

0096                          A072.08 7.9096.000758.40
25 mm CONDUIT UNDER ROADWAY m 96.000758.40
86.000679.40
0.0000.00

0097                          A072.10 8.30302.0002,506.60
38 mm CONDUIT UNDER ROADWAY m 302.0002,506.60
282.0002,340.60
0.0000.00

0098                          A072.14 10.1060.000606.00
50 mm CONDUIT UNDER ROADWAY m 60.000606.00
79.000797.90
0.0000.00

0099                          A072.18 15.10151.0002,280.10
75 mm CONDUIT UNDER ROADWAY m 151.0002,280.10
135.0002,038.50
0.0000.00

0100                          A072.20 17.0096.0001,632.00
100 mm CONDUIT UNDER ROADWAY m 96.0001,632.00
67.0001,139.00
0.0000.00

0101                          A074.18 65.0030.0001,950.00
75 mm CONDUIT, JACKED m 30.0001,950.00
210.00013,650.00
0.0000.00

0102                          A074.20 72.0030.0002,160.00
100 mm CONDUIT, JACKED m 30.0002,160.00
216.00015,552.00
0.0000.00

0103                          A080.04 5.90160.000944.00
STREET LIGHTING CABLE, NO. 1/0 USE m 160.000944.00
250.0001,475.00
0.0000.00

0104                          A080.05 5.2580.000420.00
STREET LIGHTING CABLE, NO. 1/0 BARE m 80.000420.00
125.000656.25
0.0000.00

0105                          A080.10 3.303,050.00010,065.00
STREET LIGHTING CABLE, NO. 2 USE m 3,050.00010,065.00
2,798.0009,233.40
0.0000.00

0106                          A080.11 2.601,525.0003,965.00
STREET LIGHTING CABLE, NO. 2 BARE m 2,584.0006,718.40
2,458.0006,390.80
0.0000.00

0107                          A080.22 1.8010,619.00019,114.20
STREET LIGHTING CABLE, NO. 6 BARE m 10,747.00019,344.60
12,049.00021,688.20
0.0000.00

0108                          A080.24 2.0021,238.00042,476.00
STREET LIGHTING CABLE, NO. 6 USE m 28,437.00056,874.00
31,333.00062,666.00
0.0000.00

0109                          A080.35 1.9054.000102.60
STREET LIGHTING CABLE, NO. 10 USE m 54.000102.60
18.00034.20
0.0000.00

0110                          A080.38 1.9027.00051.30
STREET LIGHTING CABLE, NO. 10 BARE m 27.00051.30
9.00017.10
0.0000.00

0111                          A090.01 2,400.001.0002,400.00
STEP DOWN TRANSFORMER AND ENCLOSURE EACH1.0002,400.00
0.0000.00
0.0000.00

0112                          A510.00 200.002.000400.00
INSTALL LUMINAIRE EACH2.000400.00
AND ADJUST 0.0000.00
0.0000.00

0113                          0030.81 6,400.001.0006,400.00
MOBILIZATION LS 1.0006,400.00
1.0006,400.00
0.0000.00

0130                          A001.18 4,074.000.0000.00
PULL BOX, TYPE PB-6 SPECIAL EACH2.0008,148.00
2.0008,148.00
0.0000.00

0136                          A001.12 320.000.0000.00
PULL BOX, TYPE PB-5 EACH78.00024,960.00
Additional PB-5's for PB-7's 78.00024,960.00
0.0000.00

0151                          6960.02 23,090.000.0000.00
ADDITIONAL WORK LS 1.00023,090.00
Additional Work for Changeable Message Sign 1.00023,090.00
0.0000.00

0152                          6960.02 3,150.000.0000.00
ADDITIONAL WORK LS 1.0003,150.00
Additional Work for Flagpoles 1.0003,150.00
0.0000.00

0153                          6960.02 704.000.0000.00
ADDITIONAL WORK LS 1.000704.00
Grounding Rods for Radio Towers 1.000704.00
0.0000.00

0154                          A525.00 655.990.0000.00
INSTALL STREET LIGHT BASE EACH2.0001,311.98
SPOT LIGHTS AT CAMERA LOCATIONS BY I-80, EB/WB 2.0001,311.98
0.0000.00

0159                          A079.60 5.410.0000.00
STREET LIGHTING CABLE m 1,120.0006,059.20
No. 1 USE Wire 1,120.0006,059.20
0.0000.00

0160                          A080.04 6.540.0000.00
STREET LIGHTING CABLE, NO. 1/0 USE m 998.0006,526.92
No. 1/0 USE Wire 998.0006,526.92
0.0000.00

0161                          A080.15 3.050.0000.00
STREET LIGHTING CABLE, NO. 4 USE m 194.000591.70
No. 4 USE Wire 194.000591.70
0.0000.00

0162                          A679.80 2.470.0000.00
REMOVE STREET LIGHTING CABLE m 6,306.00015,575.82
Remove and Reinstall Wires: 6,306.00015,575.82
0.0000.00

0163                          A679.80 2.470.0000.00
REMOVE STREET LIGHTING CABLE m 2,102.0005,191.94
Remove and Reinstall wires 2,102.0005,191.94
0.0000.00

0164                          A910.00 4,567.500.0000.00
ELECTRICAL WORK LS 1.0004,567.50
Relay (qauntity of 2) 1.0004,567.50
0.0000.00

155                           A630.13 826.880.0000.00
REMOVE LIGHT POLE BASE EACH1.000826.88
WB spotlight footing at Camera location. 1.000826.88
0.0000.00

156                           A074.14 50.400.0000.00
50 mm CONDUIT JACKED m 110.0005,544.00
50 mm CONDUITS JACKED EB/WB 110.0005,544.00
0.0000.00

157                           A074.12 40.950.0000.00
38 mm CONDUIT JACKED m 443.00018,140.85
ADDITIONAL 38 mm CONDUIT JACKED EB/WB 443.00018,140.85
0.0000.00

158                           4976.05 1,365.000.0000.00
ADDITIONAL WORK LS 1.0001,365.00
ADDITIONAL CONDUIT RUNS BETWEEN TV-PB AND LIGHT POLES EB/WB 1.0001,365.00
0.0000.00

5820                          5820.45 1,312.500.0000.00
ELECTRICAL WORK FOR SCALE BUILDING EACH2.0002,625.00
2.0002,625.00
0.0000.00

GROUP 8B ELECTRICALContracted454,881.98
Current586,790.37
In place634,240.45
This Estimate0.00

GROUP 8C SIGNING
0114                          A007.15 500.0028.00014,000.00
VEHICLE DETECTOR, TYPE TD-5 EACH28.00014,000.00
28.00014,000.00
0.0000.00

0115                          0030.82 3,000.001.0003,000.00
MOBILIZATION LS 1.0003,000.00
1.0003,000.00
0.0000.00

0116                          7320.95 4,500.002.0009,000.00
FIBER OPTIC SIGN EACH2.0009,000.00
2.0009,000.00
0.0000.00

0117                          7322.01 275.00131.07836,046.45
TYPE B SIGN m2 131.07836,046.45
131.08136,047.28
0.0000.00

0118                          7340.00 5.004,564.60022,823.00
STRUCTURAL STEEL FOR SIGN SUPPORTS kg 4,564.60022,823.00
5,218.97026,094.85
0.0000.00

0119                          7360.24 300.0032.0009,600.00
600 mm SIGN SUPPORT FOOTING EACH32.0009,600.00
32.0009,600.00
0.0000.00

0120                          7360.30 350.006.0002,100.00
750 mm SIGN SUPPORT FOOTING EACH6.0002,100.00
6.0002,100.00
0.0000.00

0121                          7360.36 400.002.000800.00
900 mm SIGN SUPPORT FOOTING EACH2.000800.00
2.000800.00
0.0000.00

0122                          7390.00 370.0010.0003,700.00
REMOVE SIGN AND POST EACH10.0003,700.00
11.0004,070.00
0.0000.00

GROUP 8C SIGNINGContracted101,069.45
Current101,069.45
In place104,712.13
This Estimate0.00

GROUP 10 GENERAL ITEMS
0123                          0001.00 640.0024.00015,360.00
SURVEILLANCE OF TEMPORARY TRAFFIC CONTROL DEVICES CDAY24.00015,360.00
0.0000.00
0.0000.00

0124                          0001.08 0.502,420.0001,210.00
BARRICADE, TYPE II BDAY2,420.0001,210.00
21,789.00010,894.50
0.0000.00

0125                          0001.10 1.19380.000452.20
BARRICADE, TYPE III BDAY380.000452.20
1,469.0001,748.11
0.0000.00

0126                          0001.30 0.89368.000327.52
TYPE B HIGH INTENSITY WARNING LIGHT LDAY368.000327.52
0.0000.00
0.0000.00

0127                          0001.90 0.122,368.000284.16
SIGN DAY EACH2,368.000284.16
710.00085.20
0.0000.00

0128                          0010.04 3,200.001.0003,200.00
FIELD OFFICE EACH1.0003,200.00
1.0003,200.00
0.0000.00

0129                          0030.00 1.001.0001.00
MOBILIZATION LS 1.0001.00
1.0001.00
0.0000.00

GROUP 10 GENERAL ITEMSContracted20,834.88
Current20,834.88
In place15,928.81
This Estimate0.00

Totals for contractContracted7,203,200.00
Current7,465,052.85
In place7,473,691.12
This Estimate3,875.59