Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:0049 HAWKINS CONSTRUCTION COMPANY
Contract ID:2597A
Estimate Number:0005
Pay Period End Date:05.25.2002
Contract Location:
PLATTE RIVER TO N-31 - BRIDGEEstimate Type:PROG
Contractor:
HAWKINS CONSTRUCTION COMPANYDate Let:12.06.2001
2512 DEER PARK BLVDDate Awarded:12.18.2001
PO BOX 9008 STA CDate Contract Executed:01.22.2002
Date Notice to Proceed:01.22.2002
OMAHA NE 68109Date Work Began:02.26.2002
Phone:Date Physical Work Completed:
(402)342-1607Date Accepted:
Escrow Agent:
Surety Co:
FIREMAN'S FUND INSURANCE COMPANY
Counties
SARPY
Project Number PCT Fed State Project Number Description
21597A 000  0.000 EACBR-6-7(173)  GR CP BR GDRL
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$454,767.70$347,232.77$107,534.93
$1,061,623.55Stockpiled Materials$34,004.27$10,145.77$23,858.50
Original Contract AmtGross Earnings$488,771.97$357,378.54$131,393.43
$1,070,464.27Retainage$-4,547.68$-3,472.33$-1,075.35
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
42.84%Net Earnings$484,224.29$353,906.21$130,318.08
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$142.50$142.50$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments$142.50$142.50$.00
Payment$484,366.79$354,048.71$130,318.08
Project ManagerDiv. Head/Dist. Eng.
Weander, Marty05.28.2002Lech, Marvin (Marv)05.28.2002
Constr. Estimate Eng.Materials Eng.
Bartos, Steve05.28.2002
Controller Div. Processed
Burling, Laurie05.28.2002
Detailed breakdown of stockpiled materials
Est Nbr:0004
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00383051.10 EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES
S.P. Initial Payment2,790.972449
Epoxy Coated Re-Steel for PVMT Approach
40106080.00 STRUCTURAL STEEL FOR SUBSTRUCTURE
S.P. Initial Payment1,648.00588036
Struc Steel For Substructure
40116131.50 EPOXY COATED REINFORCING STEEL
S.P. Initial Payment5,706.802450
Epoxy Coated Reinforcing Steel
Total for estimate 0004:10,145.77
Est Nbr:0005
Item NbrItem CdItem DescAdj AmtInvoice Nbr
40136210.12 HP 10"X42# STEEL PILING
S.P. Initial Payment27,325.90033422
HP 10"X42# STEEL PILING
S.P. Adjustment-3,467.40033422
HP 10"X42# STEEL PILING
Total for estimate 0005:23,858.50
Total remaining for contract:34,004.27
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          L006.50 345.004.2001,449.00
TEMPORARY SEEDING ACRE4.2001,449.00
2.000690.00
2.000690.00

0002                          L020.00 1.552,745.0004,254.75
EROSION CONTROL SY 2,745.0004,254.75
0.0000.00
0.0000.00

0003                          L020.12 7.771,550.00012,043.50
EROSION CONTROL, TYPE B-2 SY 1,550.00012,043.50
0.0000.00
0.0000.00

0004                          L021.06 17.2724.000414.48
EROSION CHECKS, TYPE HV BALE24.000414.48
0.0000.00
0.0000.00

0005                          L022.11 2.88800.0002,304.00
FABRIC SILT FENCE-LOW POROSITY LF 800.0002,304.00
0.0000.00
0.0000.00

0006                          0030.10 10,360.001.00010,360.00
MOBILIZATION LS 1.00010,360.00
0.0000.00
0.0000.00

0007                          1009.00 13,589.001.00013,589.00
GENERAL CLEARING AND GRUBBING LS 1.00013,589.00
1.00013,589.00
0.0000.00

0008                          1010.01 3.559,342.00033,164.10
EXCAVATION (ESTABLISHED QUANTITY) CY 9,342.00033,164.10
5,000.00017,750.00
0.0000.00

0009                          1011.00 4.61240.0001,106.40
WATER MGAL240.0001,106.40
0.0000.00
0.0000.00

0010                          1012.00 92.004.000368.00
RIGHT-OF-WAY MARKERS EACH4.000368.00
0.0000.00
0.0000.00

0011                          1030.00 4.5517,310.00078,760.50
EARTHWORK MEASURED IN EMBANKMENT CY 17,310.00078,760.50
15,000.00068,250.00
0.0000.00

0012                          1101.00 4.382,658.00011,642.04
REMOVE PAVEMENT SY 2,658.00011,642.04
0.0000.00
0.0000.00

0013                          4050.01 5.2967.000354.43
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS CY 67.000354.43
67.000354.43
0.0000.00

0014                          4200.36 1,531.001.0001,531.00
36" AUTOMATIC FLOOD CONTROL GATE EACH1.0001,531.00
1.0001,531.00
0.0000.00

0015                          4350.36 28.0056.0001,568.00
36" CORRUGATED METAL PIPE LF 56.0001,568.00
56.0001,568.00
0.0000.00

0016                          4350.60 63.32410.00025,961.20
60" CORRUGATED METAL PIPE LF 410.00025,961.20
458.00029,000.56
0.0000.00

0017                          4360.36 339.001.000339.00
36" METAL FLARED-END SECTION EACH1.000339.00
1.000339.00
0.0000.00

0018                          7017.00 1.15550.000632.50
REMOVE GUARDRAIL LF 550.000632.50
550.000632.50
550.000632.50

0019                          9110.01 86.0010.000860.00
RENTAL OF LOADER, FULLY OPERATED HOUR10.000860.00
8.500731.00
0.0000.00

0020                          9110.03 86.0010.000860.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR10.000860.00
13.0001,118.00
0.0000.00

0021                          9110.07 86.0010.000860.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR10.000860.00
3.500301.00
0.0000.00

4003                          6990.02 450.000.0000.00
SHIPPING COST LS 1.000450.00
Shipping cost for delivery of additional 60" CMP 1.000450.00
0.0000.00

GROUP 1 GRADINGContracted202,421.90
Current202,871.90
In place136,304.49
This Estimate1,322.50

GROUP 3 CONCRETE PAVEMENT
0022                          L001.02 754.290.580437.49
SEEDING, TYPE B ACRE0.580437.49
0.0000.00
0.0000.00

0023                          L001.03 461.001.200553.20
SEEDING, TYPE C ACRE1.200553.20
0.0000.00
0.0000.00

0024                          L032.75 86.004.000344.00
MULCH TON 4.000344.00
0.0000.00
0.0000.00

0025                          0030.30 26,526.001.00026,526.00
MOBILIZATION LS 1.00026,526.00
0.50013,263.00
0.0000.00

0026                          3075.42 25.101,563.00039,231.30
9" CONCRETE PAVEMENT, CLASS 47B-3500 SY 1,563.00039,231.30
0.0000.00
0.0000.00

0027                          3075.46 27.252,343.00063,846.75
9" DOWELED CONCRETE PAVEMENT, CLASS 47B-3500 SY 2,343.00063,846.75
0.0000.00
0.0000.00

0028                          3089.25 28.057,976.000223,726.80
TEMPORARY SURFACING SY 0.0000.00
10" 0.0000.00
0.0000.00

0029                          8029.04 5.373,906.00020,975.22
AGGREGATE FOUNDATION COURSE 4" SY 0.0000.00
0.0000.00
0.0000.00

0030                          9111.00 2.64212.000559.68
WATER MGAL212.000559.68
0.0000.00
0.0000.00

0031                          9170.00 86.3717.6401,523.57
EARTH SHOULDER CONSTRUCTION STA 17.6401,523.57
0.0000.00
0.0000.00

0032                          9173.20 1.233,906.0004,804.38
SUBGRADE PREPARATION SY 3,906.0004,804.38
0.0000.00
0.0000.00

0033                          9188.50 36.3887.0003,165.06
SURFACING UNDER GUARDRAIL SY 87.0003,165.06
0.0000.00
0.0000.00

4001                          3089.25 27.530.0000.00
TEMPORARY SURFACING SY 7,976.000219,579.28
TEMPORARY SURFACING 10" 7,102.430195,529.90
0.0000.00

4002                          8029.04 4.450.0000.00
AGGREGATE FOUNDATION COURSE 4" SY 3,906.00017,381.70
AGGREGATE FOUNDATION COURSE 4" 0.0000.00
0.0000.00

GROUP 3 CONCRETE PAVEMENTContracted385,693.45
Current377,952.41
In place208,792.90
This Estimate0.00

GROUP 6 BRIDGE AT STA. 18+21.67
0034                          0030.60 44,830.001.00044,830.00
MOBILIZATION LS 0.0000.00
0.0000.00
0.0000.00

0035                          1010.01 3.96120.000475.20
EXCAVATION (ESTABLISHED QUANTITY) CY 120.000475.20
0.0000.00
0.0000.00

0036                          1043.50 2.9464.000188.16
RIPRAP FILTER FABRIC SY 64.000188.16
0.0000.00
0.0000.00

0037                          3050.15 149.86203.70030,526.48
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-4000 CY 0.0000.00
0.0000.00
0.0000.00

0038                          3051.10 0.6320,480.00012,902.40
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES LB 20,480.00012,902.40
0.0000.00
0.0000.00

0039                          6000.10 627.001.000627.00
ABUTMENT NO.1 EXCAVATION LS 1.000627.00
0.0000.00
0.0000.00

0040                          6000.11 627.001.000627.00
ABUTMENT NO.2 EXCAVATION LS 1.000627.00
0.0000.00
0.0000.00

0041                          6001.50 4,287.001.0004,287.00
BENT NO.1 EXCAVATION LS 0.0000.00
0.0000.00
0.0000.00

0042                          6001.51 4,486.001.0004,486.00
BENT NO.2 EXCAVATION LS 0.0000.00
0.0000.00
0.0000.00

0043                          6010.22 219.08236.30051,768.60
CLASS 47B-3000 CONCRETE FOR BRIDGE CY 0.0000.00
0.0000.00
0.0000.00

0044                          6010.26 355.85289.800103,125.33
CLASS 47BD-4000 CONCRETE FOR BRIDGE CY 0.0000.00
0.0000.00
0.0000.00

0045                          6040.00 53,308.001.00053,308.00
REMOVE STRUCTURE EACH1.00053,308.00
AT STA. 18+26.48 1.00053,308.00
1.00053,308.00

0046                          6080.00 2.92800.0002,336.00
STRUCTURAL STEEL FOR SUBSTRUCTURE LB 0.0000.00
0.0000.00
0.0000.00

0047                          6104.00 5.83270.0001,574.10
BROKEN CONCRETE RIPRAP TON 270.0001,574.10
0.0000.00
0.0000.00

0048                          6105.02 22.86100.8002,304.29
ROCK RIPRAP, TYPE B TON 100.8002,304.29
0.0000.00
0.0000.00

0049                          6131.50 0.6484,915.00054,345.60
EPOXY COATED REINFORCING STEEL LB 0.0000.00
0.0000.00
0.0000.00

0050                          6139.50 27.9049.8001,389.42
SUBSURFACE DRAINAGE MATTING SY 0.0000.00
0.0000.00
0.0000.00

0051                          6210.12 13.02980.00012,759.60
HP 10"X42# STEEL PILING LF 0.0000.00
0.0000.00
0.0000.00

0052                          6210.14 15.652,620.00041,003.00
HP 12"X53# STEEL PILING LF 0.0000.00
0.0000.00
0.0000.00

0053                          6310.00 9.552,561.90024,466.15
STEEL SHEET PILING SF 2,561.90024,466.15
0.0000.00
0.0000.00

0054                          8091.00 11.1788.500988.55
GRANULAR BACKFILL CY 88.500988.55
0.0000.00
0.0000.00

4004                          0030.60 1.000
MOBILIZATION LS 2.0000.00
Mobilization 0.5009,678.00
0.5009,678.00

4005                          3050.15 150.680.0000.00
CLASS 47BD-4000 CONCRETE FOR PAVEMENT APPROACHES CY 201.50030,362.02
0.0000.00
0.0000.00

4006                          6001.50 3,883.000.0000.00
BENT EXCAVATION LS 1.0003,883.00
1.0003,883.00
1.0003,883.00

4007                          6001.51 4,082.000.0000.00
BENT EXCAVATION LS 1.0004,082.00
0.0000.00
0.0000.00

4008                          6010.22 207.750.0000.00
CLASS 47B-3000 CONCRETE FOR BRIDGE CY 250.90052,124.48
0.0000.00
0.0000.00

4009                          6010.26 407.970.0000.00
CLASS 47BD-4000 CONCRETE FOR BRIDGE CY 124.80050,914.66
0.0000.00
0.0000.00

4010                          6080.00 3.030.0000.00
STRUCTURAL STEEL FOR SUBSTRUCTURE LB 800.0002,424.00
0.0000.00
0.0000.00

4011                          6131.50 0.62150.0000.00
EPOXY COATED REINFORCING STEEL LB 43,720.00027,171.98
0.0000.00
0.0000.00

4012                          6139.50 19.950.0000.00
SUBSURFACE DRAINAGE MATTING SY 49.800993.51
0.0000.00
0.0000.00

4013                          6210.12 14.050.0000.00
HP 10"X42# STEEL PILING LF 3,600.00050,580.00
457.4406,427.03
457.4406,427.03

4014                          6011.11 75,866.000.0000.00
PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE AT STATION LS 1.00075,866.00
Sta. 18+21.67 0.0000.00
0.0000.00

4015                          4048.00 31,549.700.0000.00
MODIFICATION OF STRUCTURE EACH1.00031,549.70
Design Fees From Slab Bridge to Inverted "T" and V.E.P. 1.00031,549.70
1.00031,549.70

GROUP 6 BRIDGE AT STA. 18+21.67Contracted448,317.87
Current446,768.18
In place104,845.73
This Estimate104,845.73

GROUP 7 GUARDRAIL
0055                          0030.70 288.001.000288.00
MOBILIZATION LS 1.000288.00
0.0000.00
0.0000.00

0056                          7011.20 16.12225.0003,627.00
W-BEAM GUARDRAIL LF 225.0003,627.00
0.0000.00
0.0000.00

0057                          7020.00 1,382.004.0005,528.00
BRIDGE APPROACH SECTIONS EACH4.0005,528.00
0.0000.00
0.0000.00

0058                          7024.25 2,303.001.0002,303.00
GUARDRAIL END TREATMENT, TYPE I EACH1.0002,303.00
0.0000.00
0.0000.00

0059                          7024.27 1,843.003.0005,529.00
GUARDRAIL END TREATMENT, TYPE II EACH3.0005,529.00
0.0000.00
0.0000.00

GROUP 7 GUARDRAILContracted17,275.00
Current17,275.00
In place0.00
This Estimate0.00

GROUP 10 GENERAL ITEMS
0060                          0001.08 0.501,960.000980.00
BARRICADE, TYPE II BDAY1,960.000980.00
1,200.000600.00
720.000360.00

0061                          0001.10 2.251,244.0002,799.00
BARRICADE, TYPE III BDAY1,244.0002,799.00
272.000612.00
140.000315.00

0062                          0001.30 2.25404.000909.00
TYPE B HIGH INTENSITY WARNING LIGHT LDAY404.000909.00
144.000324.00
28.00063.00

0063                          0001.90 0.355,068.0001,773.80
SIGN DAY EACH5,068.0001,773.80
1,170.000409.50
420.000147.00

0064                          0002.30 0.461,000.000460.00
PAVEMENT MARKING REMOVAL LF 1,000.000460.00
990.000455.40
0.0000.00

0065                          0002.44 0.0912,500.0001,125.00
TEMPORARY PAVEMENT MARKING, TYPE PAINT LF 12,500.0001,125.00
9,535.000858.15
0.0000.00

0066                          0002.47 0.58800.000464.00
TEMPORARY PAVEMENT MARKING SURFACE PREPARATION LF 800.000464.00
0.0000.00
0.0000.00

0067                          0003.10 240.8525.0006,021.25
FLAGGING DAY 25.0006,021.25
6.5001,565.53
2.000481.70

0068                          0010.04 1,423.001.0001,423.00
FIELD OFFICE EACH1.0001,423.00
0.0000.00
0.0000.00

0069                          0020.00 0.801,000.000800.00
TRAINING HOUR1,000.000800.00
0.0000.00
0.0000.00

0070                          0030.00 1.001.0001.00
MOBILIZATION LS 1.0001.00
0.0000.00
0.0000.00

GROUP 10 GENERAL ITEMSContracted16,756.05
Current16,756.05
In place4,824.58
This Estimate1,366.70

Totals for contractContracted1,070,464.27
Current1,042,267.53
In place454,767.70
This Estimate107,534.93