Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:0049 HAWKINS CONSTRUCTION COMPANY
Contract ID:2795X
Estimate Number:0009
Pay Period End Date:06.08.2002
Contract Location:
US-275/BIG PAPIO, NEAR JCT. N-85, OMAHAEstimate Type:PROG
Contractor:
HAWKINS CONSTRUCTION COMPANYDate Let:03.29.2001
2512 DEER PARK BLVDDate Awarded:04.06.2001
PO BOX 9008 STA CDate Contract Executed:04.24.2001
Date Notice to Proceed:04.24.2001
OMAHA NE 68109Date Work Began:07.30.2001
Phone:Date Physical Work Completed:
(402)342-1607Date Accepted:
Escrow Agent:
Surety Co:
FIREMAN'S FUND INSURANCE COMPANY
Counties
DOUGLAS
Project Number PCT Fed State Project Number Description
21795 000  0.000 EACNH-275-7(178)  BRIDGE
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$658,067.22$617,123.36$40,943.86
$1,125,266.04Stockpiled Materials$27,095.62$16,163.03$10,932.59
Original Contract AmtGross Earnings$685,162.84$633,286.39$51,876.45
$1,122,913.17Retainage$-6,580.67$-6,171.23$-409.44
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
58.48%Net Earnings$678,582.17$627,115.16$51,467.01
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$.00$.00$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments$.00$.00$.00
Payment$678,582.17$627,115.16$51,467.01
Project ManagerDiv. Head/Dist. Eng.
Gjersvik, John06.11.2002Lech, Marvin (Marv)06.11.2002
Constr. Estimate Eng.Materials Eng.
Bartos, Steve06.11.2002
Controller Div. Processed
Burling, Laurie06.13.2002
Detailed breakdown of stockpiled materials
Est Nbr:0003
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00446131.50 EPOXY COATED REINFORCING STEEL
S.P. Initial Payment12,832.691978
Reinforcing Steel
S.P. Adjustment-898.991978
Reinforcing Steel
S.P. Initial Payment7,067.901972
Reinforcing Steel
S.P. Adjustment-898.991972
Reinforcing Steel
Total for estimate 0003:18,102.61
Est Nbr:0004
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00446131.50 EPOXY COATED REINFORCING STEEL
S.P. Initial Payment6,168.921972
Reinforcing Steel
S.P. Closure-6,168.911972
Reinforcing Steel
00517019.50 IMPACT ATTENUATOR
S.P. Initial Payment17,200.0020139
Impact Attenuator
Total for estimate 0004:17,200.01
Est Nbr:0005
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00356005.35 PRECOMPRESSED POLYURETHANE FOAM JOINT
S.P. Initial Payment4,029.00690713
Precompressed Poly Foam Joint
00446131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-908.481978
Reinforcing Steel
Total for estimate 0005:3,120.52
Est Nbr:0006
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00446131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-10,712.061978
Reinforcing Steel
Total for estimate 0006:-10,712.06
Est Nbr:0007
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00356005.35 PRECOMPRESSED POLYURETHANE FOAM JOINT
S.P. Adjustment-1,659.00690713
Precompressed Poly Foam Joint
00446131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-313.161978
Reinforcing Steel
S.P. Adjustment-975.891972
Reinforcing Steel
00517019.50 IMPACT ATTENUATOR
S.P. Adjustment-8,600.0020139
Impact Attenuator
Total for estimate 0007:-11,548.05
Est Nbr:0009
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00446131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-982.001972
Reinforcing Steel
S.P. Initial Payment11,914.592586
Reinforcing Steel
Total for estimate 0009:10,932.59
Total remaining for contract:27,095.62
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 6 BRIDGE AT STA. 13+99.54
0001                          L020.00 2.41536.0001,291.76
EROSION CONTROL SY 536.0001,291.76
0.0000.00
0.0000.00

0002                          0001.08 0.5011,382.0005,691.00
BARRICADE, TYPE II BDAY11,382.0005,691.00
11,504.0005,752.00
1,148.000574.00

0003                          0001.10 3.581,751.0006,268.58
BARRICADE, TYPE III BDAY1,751.0006,268.58
5,999.00021,476.42
1,092.0003,909.36

0004                          0001.90 0.288,276.0002,317.28
SIGN DAY EACH8,276.0002,317.28
10,522.0002,946.16
1,716.000480.48

0005                          0002.30 0.272,800.000756.00
PAVEMENT MARKING REMOVAL LF 2,800.000756.00
5,287.0001,427.49
0.0000.00

0006                          0002.44 0.0524,000.0001,200.00
TEMPORARY PAVEMENT MARKING, TYPE PAINT LF 24,000.0001,200.00
9,504.000475.20
0.0000.00

0007                          0002.47 0.872,000.0001,740.00
TEMPORARY PAVEMENT MARKING SURFACE PREPARATION LF 2,000.0001,740.00
5,627.0004,895.49
0.0000.00

0008                          0002.48 0.66620.000409.20
TEMPORARY RAISED PAVEMENT MARKER EACH620.000409.20
0.0000.00
0.0000.00

0009                          0002.85 53.0120.0001,060.20
TUBULAR POST EACH20.0001,060.20
16.000848.16
0.0000.00

0010                          0002.97 6.33542.0003,430.86
FLASHING ARROW PANEL DAY 542.0003,430.86
308.0001,949.64
56.000354.48

0011                          0003.10 54.5360.0003,271.80
FLAGGING DAY 60.0003,271.80
1.00054.53
0.0000.00

0012                          0003.51 3.221,040.0003,348.80
INSTALL CONCRETE PROTECTION BARRIER LF 1,040.0003,348.80
700.0002,254.00
0.0000.00

0013                          0003.76 3,132.001.0003,132.00
TEMPORARY TRAFFIC SIGNAL EACH1.0003,132.00
1.0003,132.00
0.0000.00

0014                          0010.04 1,084.001.0001,084.00
FIELD OFFICE EACH1.0001,084.00
1.0001,084.00
0.0000.00

0015                          0020.00 0.801,000.000800.00
TRAINING HOUR1,000.000800.00
704.500563.60
0.0000.00

0016                          0030.60 105,811.001.000105,811.00
MOBILIZATION LS 1.000105,811.00
1.000105,811.00
0.0000.00

0017                          1009.00 685.001.000685.00
GENERAL CLEARING AND GRUBBING LS 1.000685.00
0.500342.50
0.0000.00

0018                          1011.00 1.002.0002.00
WATER MGAL2.0002.00
0.0000.00
0.0000.00

0019                          1030.00 11.48106.0001,216.88
EARTHWORK MEASURED IN EMBANKMENT CY 106.0001,216.88
0.0000.00
0.0000.00

0020                          1043.50 1.21207.000250.47
RIPRAP FILTER FABRIC SY 207.000250.47
0.0000.00
0.0000.00

0021                          1101.00 4.81768.0003,694.08
REMOVE PAVEMENT SY 768.0003,694.08
825.0003,968.25
457.0002,198.17

0022                          1109.00 6.17560.0003,455.20
REMOVE CURB LF 560.0003,455.20
880.0005,429.60
0.0000.00

0023                          1122.01 2.78566.0001,573.48
REMOVE CONCRETE MEDIAN SURFACING SY 566.0001,573.48
957.7202,662.46
0.0000.00

0024                          2020.50 32.01394.00012,611.94
SURFACING SY 394.00012,611.94
8" 785.72025,150.90
0.0000.00

0025                          3008.05 8.1715.000122.55
TIE BARS EACH15.000122.55
164.0001,339.88
30.000245.10

0026                          3011.22 6.35560.0003,556.00
CONCRETE CLASS 47B-3000 CURB TYPE II LF 560.0003,556.00
0.0000.00
0.0000.00

0027                          3014.12 12.2761.000748.47
COMBINATION CONCRETE CLASS 47B-3625 CURB AND GUTTER LF 61.000748.47
0.0000.00
0.0000.00

0028                          3016.21 21.64226.0004,890.64
CONCRETE CLASS 47B-3000 SIDEWALKS SY 226.0004,890.64
0.0000.00
0.0000.00

0029                          3017.40 23.22394.0009,148.68
CONCRETE CLASS 47B-3000 MEDIAN SURFACING SY 394.0009,148.68
0.0000.00
0.0000.00

0030                          3050.15 163.61392.20064,167.84
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-4000 CY 392.20064,167.84
176.51028,878.81
0.0000.00

0031                          3051.10 0.7435,595.00026,340.30
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES LB 35,595.00026,340.30
16,147.77011,949.35
0.0000.00

0032                          4015.00 343.001.000343.00
ADJUST MANHOLE TO GRADE EACH1.000343.00
0.0000.00
0.0000.00

0033                          6000.10 3,210.001.0003,210.00
ABUTMENT NO.1 EXCAVATION LS 1.0003,210.00
1.0003,210.00
0.5001,605.00

0034                          6000.11 3,210.001.0003,210.00
ABUTMENT NO.2 EXCAVATION LS 1.0003,210.00
1.0003,210.00
0.5001,605.00

0035                          6005.35 39.03170.0006,635.10
PRECOMPRESSED POLYURETHANE FOAM JOINT LF 170.0006,635.10
70.0002,732.10
0.0000.00

0036                          6005.78 723.7424.00017,369.76
EXPANSION BEARING, TFE TYPE EACH24.00017,369.76
24.00017,369.76
12.0008,684.88

0037                          6005.83 783.008.0006,264.00
FIXED BEARING EACH8.0006,264.00
8.0006,264.00
4.0003,132.00

0038                          6010.22 260.86185.30048,337.36
CLASS 47B-3000 CONCRETE FOR BRIDGE CY 185.30048,337.36
175.59045,804.41
60.22015,708.99

0039                          6010.26 232.30747.000173,528.10
CLASS 47BD-4000 CONCRETE FOR BRIDGE CY 747.000173,528.10
274.18063,692.02
0.0000.00

0040                          6030.00 53,283.001.00053,283.00
PREPARATION OF BRIDGE EACH1.00053,283.00
AT STA. 13+99.54 0.50026,641.50
0.0000.00

0041                          6071.12 387,368.001.000387,368.00
STEEL SUPERSTRUCTURE LS 1.000387,368.00
AT STA. 13+99.54 0.500193,684.00
0.0000.00

0042                          6100.00 487.008.0003,896.00
FLOOR DRAINS EACH8.0003,896.00
4.0001,948.00
0.0000.00

0043                          6104.00 6.8593.000637.05
BROKEN CONCRETE RIPRAP TON 93.000637.05
0.0000.00
0.0000.00

0044                          6131.50 0.66122,505.00080,853.30
EPOXY COATED REINFORCING STEEL LB 122,505.00080,853.30
52,006.26634,324.14
3,452.8802,278.90

0045                          6139.50 13.5590.0001,219.50
SUBSURFACE DRAINAGE MATTING SY 90.0001,219.50
40.500548.78
0.0000.00

0046                          6401.00 35.10318.30011,172.33
PEDESTRIAN BARRIER RAIL LF 318.30011,172.33
0.0000.00
0.0000.00

0047                          6404.00 39.86316.30012,607.72
PEDESTRIAN RAILING (CHAIN LINK TYPE) LF 316.30012,607.72
0.0000.00
0.0000.00

0048                          6510.55 2,369.001.0002,369.00
TEMPORARY BRIDGE SHORING LS 1.0002,369.00
0.5001,184.50
0.0000.00

0049                          6600.02 9.64366.0003,528.24
2" CONDUIT IN BRIDGE LF 366.0003,528.24
0.0000.00
0.0000.00

0050                          7017.00 2.68125.000335.00
REMOVE GUARDRAIL LF 125.000335.00
125.000335.00
62.500167.50

0051                          7019.50 11,856.002.00023,712.00
IMPACT ATTENUATOR EACH2.00023,712.00
1.00011,856.00
0.0000.00

0052                          7502.14 4.86550.0002,673.00
4" WHITE PREFORMED PAVEMENT MARKING, TYPE 4, GROOVED LF 550.0002,673.00
0.0000.00
0.0000.00

0053                          8091.00 13.04175.0002,282.00
GRANULAR BACKFILL CY 175.0002,282.00
78.7501,026.90
0.0000.00

0054                          9173.20 9.55394.0003,762.70
SUBGRADE PREPARATION SY 394.0003,762.70
785.7207,503.63
0.0000.00

0055                          9185.50 9.6425.000241.00
MILLING CONCRETE CURB LF 25.000241.00
261.0002,516.04
0.0000.00

4001                          1101.25 2.500.0000.00
SAWING PAVEMENT LF 0.0000.00
0.0000.00
0.0000.00

4003                          1101.25 2.500.0000.00
SAWING PAVEMENT LF 730.0001,825.00
730.0001,825.00
0.0000.00

4004                          3041.02 36.380.0000.00
ASPHALT PATCHING OF PORTLAND CEMENT CONCRETE PAVEMENT,TYPE B SY 14.510527.87
0.0000.00
0.0000.00

GROUP 6 BRIDGE AT STA. 13+99.54Contracted1,122,913.17
Current1,125,266.04
In place658,067.22
This Estimate40,943.86

Totals for contractContracted1,122,913.17
Current1,125,266.04
In place658,067.22
This Estimate40,943.86