| | | 1. Contracted
|
---|
| | | 2. Current
|
---|
| | | 3. To date
|
---|
Item Nbr Item Code | Unit Price | | 4. This Est
|
---|
Item Description | Units | Qty | Amount
|
---|
GROUP 1 GRADING | | |
|
0001 L006.00 | 83.13 | 15.600 | 1,296.83
|
COVER CROP SEEDING | ha | 15.600 | 1,296.83
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0002 L020.00 | 1.45 | 49,000.000 | 71,050.00
|
EROSION CONTROL | m2 | 49,000.000 | 71,050.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0003 L021.00 | 22.17 | 18.000 | 399.06
|
EROSION CHECKS | BALE | 18.000 | 399.06
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0004 L021.06 | 22.17 | 12.000 | 266.04
|
EROSION CHECKS, TYPE HV | BALE | 12.000 | 266.04
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0005 L022.11 | 6.93 | 731.000 | 5,065.83
|
FABRIC SILT FENCE-LOW POROSITY | m | 731.000 | 5,065.83
|
| | 369.280 | 2,559.11
|
| | 0.000 | 0.00
|
| | |
|
0006 L022.12 | 7.70 | 730.000 | 5,621.00
|
FABRIC SILT FENCE-HIGH POROSITY | m | 730.000 | 5,621.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0007 L022.75 | 27.71 | 80.000 | 2,216.80
|
TEMPORARY SILT CHECK | m | 80.000 | 2,216.80
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0008 P310.60 | 229.83 | 26.000 | 5,975.58
|
1500 mm CULVERT PIPE, TYPE 2,4 OR 5 | m | 26.000 | 5,975.58
|
| | 26.000 | 5,975.58
|
| | 0.000 | 0.00
|
| | |
|
0009 P400.24 | 76.04 | 36.500 | 2,775.46
|
600 mm CULVERT PIPE, TYPE 2,5,7 OR 8 | m | 36.500 | 2,775.46
|
| | 36.500 | 2,775.46
|
| | 0.000 | 0.00
|
| | |
|
0010 0030.10 | 8,030.00 | 1.000 | 8,030.00
|
MOBILIZATION | LS | 1.000 | 8,030.00
|
| | 1.000 | 8,030.00
|
| | 0.000 | 0.00
|
| | |
|
0011 1009.00 | 15,695.00 | 1.000 | 15,695.00
|
GENERAL CLEARING AND GRUBBING | LS | 1.000 | 15,695.00
|
| | 1.000 | 15,695.00
|
| | 0.000 | 0.00
|
| | |
|
0012 1010.01 | 4.43 | 6,503.000 | 28,808.29
|
EXCAVATION (ESTABLISHED QUANTITY) | m3 | 6,503.000 | 28,808.29
|
| | 1,300.000 | 5,759.00
|
| | 0.000 | 0.00
|
| | |
|
0013 1011.00 | 1.41 | 6,287.000 | 8,864.67
|
WATER | kL | 6,287.000 | 8,864.67
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0014 1030.00 | 7.34 | 224,543.000 | 1,648,145.62
|
EARTHWORK MEASURED IN EMBANKMENT | m3 | 224,543.000 | 1,648,145.62
|
| | 216,174.340 | 1,586,719.66
|
| | 0.000 | 0.00
|
| | |
|
0015 1101.00 | 3.48 | 13,817.000 | 48,083.16
|
REMOVE PAVEMENT | m2 | 13,817.000 | 48,083.16
|
| | 8,351.227 | 29,062.28
|
| | 4,200.000 | 14,616.00
|
| | |
|
0016 1102.00 | 3.33 | 2,150.000 | 7,159.50
|
REMOVE ASPHALT SURFACE | m2 | 2,150.000 | 7,159.50
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0017 1106.00 | 3.33 | 640.000 | 2,131.20
|
REMOVE DRIVEWAY | m2 | 640.000 | 2,131.20
|
| | 377.156 | 1,255.93
|
| | 0.000 | 0.00
|
| | |
|
0018 1600.00 | 18,898.00 | 1.000 | 18,898.00
|
MONITORING INSTRUMENTATION | LS | 1.000 | 18,898.00
|
| | 0.741 | 14,003.42
|
| | 0.000 | 0.00
|
| | |
|
0019 1701.24 | 65.60 | 28.500 | 1,869.60
|
600 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 | m | 28.500 | 1,869.60
|
| | 28.500 | 1,869.60
|
| | 0.000 | 0.00
|
| | |
|
0020 4050.01 | 17.00 | 6.000 | 102.00
|
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS | m3 | 6.000 | 102.00
|
| | 6.000 | 102.00
|
| | 0.000 | 0.00
|
| | |
|
0021 9110.01 | 121.93 | 20.000 | 2,438.60
|
RENTAL OF LOADER, FULLY OPERATED | HOUR | 20.000 | 2,438.60
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0022 9110.03 | 77.59 | 20.000 | 1,551.80
|
RENTAL OF DUMP TRUCK, FULLY OPERATED | HOUR | 20.000 | 1,551.80
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0023 9110.07 | 99.76 | 20.000 | 1,995.20
|
RENTAL OF SKID LOADER, FULLY OPERATED | HOUR | 20.000 | 1,995.20
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
4010 W206.50 | 1,466.33 | 0.000 | 0.00
|
GAS LINE CONNECTION | EACH | 1.000 | 1,466.33
|
Tract #58-Meyers | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
GROUP 1 GRADING | | Contracted | 1,888,439.24
|
| | Current | 1,889,905.57
|
| | In place | 1,673,807.04
|
| | This Estimate | 14,616.00
|
| | |
|
GROUP 1A MSE WALL | | |
|
0024 0030.10 | 12,292.00 | 1.000 | 12,292.00
|
MOBILIZATION | LS | 1.000 | 12,292.00
|
| | 1.000 | 12,292.00
|
| | 0.000 | 0.00
|
| | |
|
0025 4095.00 | 155.87 | 383.000 | 59,698.21
|
CONCRETE FACE PANELS | m2 | 383.000 | 59,698.21
|
| | 383.000 | 59,698.21
|
| | 19.000 | 2,961.53
|
| | |
|
0026 4095.10 | 24.26 | 67.000 | 1,625.42
|
CONCRETE LEVELING PADS | m | 67.000 | 1,625.42
|
| | 67.000 | 1,625.42
|
| | 0.000 | 0.00
|
| | |
|
0027 4095.20 | 164.47 | 69.000 | 11,348.43
|
COPING | m | 69.000 | 11,348.43
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0028 4350.18 | 37.37 | 76.500 | 2,858.81
|
450 mm CORRUGATED METAL PIPE | m | 76.500 | 2,858.81
|
| | 76.500 | 2,858.81
|
| | 0.000 | 0.00
|
| | |
|
0029 4350.21 | 41.26 | 59.500 | 2,454.97
|
525 mm CORRUGATED METAL PIPE | m | 59.500 | 2,454.97
|
| | 59.500 | 2,454.97
|
| | 0.000 | 0.00
|
| | |
|
0030 8024.75 | 19.47 | 3,409.000 | 66,373.23
|
SELECT GRANULAR BACKFILL FOR MSE WALL | m3 | 3,409.000 | 66,373.23
|
| | 3,409.000 | 66,373.23
|
| | 171.000 | 3,329.37
|
| | |
|
GROUP 1A MSE WALL | | Contracted | 156,651.07
|
| | Current | 156,651.07
|
| | In place | 145,302.64
|
| | This Estimate | 6,290.90
|
| | |
|
GROUP 3 CONCRETE PAVEMENT | | |
|
0031 P402.15 | 68.45 | 165.900 | 11,355.86
|
375 mm CULVERT PIPE, TYPE 3,4,5 OR 6 | m | 165.900 | 11,355.86
|
| | 18.000 | 1,232.10
|
| | 0.000 | 0.00
|
| | |
|
0032 0030.30 | 94,363.00 | 1.000 | 94,363.00
|
MOBILIZATION | LS | 1.000 | 94,363.00
|
| | 1.000 | 94,363.00
|
| | 0.000 | 0.00
|
| | |
|
0033 1020.03 | 20.78 | 93.000 | 1,932.54
|
DELINEATOR, TYPE III | EACH | 93.000 | 1,932.54
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0034 1020.20 | 22.17 | 54.000 | 1,197.18
|
INSTALL CHEVRONS | EACH | 54.000 | 1,197.18
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0035 2001.03 | 14.93 | 16.000 | 238.88
|
GRAVEL SURFACE COURSE | Mg | 16.000 | 238.88
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0036 3075.31 | 28.92 | 341.000 | 9,861.72
|
205 mm CONCRETE PAVEMENT, CLASS 47B-25 | m2 | 341.000 | 9,861.72
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0037 3075.41 | 29.98 | 858.000 | 25,722.84
|
230 mm CONCRETE PAVEMENT, CLASS 47B-25 | m2 | 858.000 | 25,722.84
|
| | 270.720 | 8,116.19
|
| | 0.000 | 0.00
|
| | |
|
0038 3075.45 | 30.61 | 6,952.000 | 212,800.72
|
230 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25 | m2 | 6,952.000 | 212,800.72
|
| | 1,250.000 | 38,262.50
|
| | 0.000 | 0.00
|
| | |
|
0039 4024.55 | 134.00 | 9.300 | 1,246.20
|
FLUME SPILLWAY | m | 9.300 | 1,246.20
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0040 4024.70 | 886.00 | 1.000 | 886.00
|
CONCRETE FLUME, TYPE I | EACH | 1.000 | 886.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0041 4024.73 | 603.00 | 6.000 | 3,618.00
|
CONCRETE FLUME, TYPE IV | EACH | 6.000 | 3,618.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0042 4105.59 | 745.00 | 5.700 | 4,246.50
|
CLASS 47B-20 CONCRETE FOR INLET AND JUNCTION BOX | m3 | 5.700 | 4,246.50
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0043 4155.50 | 0.62 | 142.000 | 88.04
|
REINFORCING STEEL FOR INLET AND JUNCTION BOX | kg | 142.000 | 88.04
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0044 7503.14 | 9.53 | 2,400.000 | 22,872.00
|
100 mm YELLOW PREFORMED PAVEMENT MARKING, TYPE 4, GROOVED | m | 2,400.000 | 22,872.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0045 7509.14 | 25.22 | 560.000 | 14,123.20
|
300 mm YELLOW PREFORMED PAVEMENT MARKING, TYPE 4, GROOVED | m | 560.000 | 14,123.20
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0046 8051.00 | 29.61 | 230.000 | 6,810.30
|
SOIL BINDER | m3 | 230.000 | 6,810.30
|
| | 558.200 | 16,528.31
|
| | 0.000 | 0.00
|
| | |
|
0047 8101.40 | 2.69 | 23,978.000 | 64,500.82
|
SUBGRADE STABILIZATION | m2 | 23,978.000 | 64,500.82
|
| | 17,298.940 | 46,534.15
|
| | 0.000 | 0.00
|
| | |
|
0048 8111.00 | 703.50 | 16.042 | 11,285.55
|
SHOULDER SUBGRADE PREPARATION | StaM | 16.042 | 11,285.55
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0049 9005.35 | 34.75 | 8,840.000 | 307,190.00
|
ASPHALTIC CONCRETE, TYPE SP3(12.5) | Mg | 8,840.000 | 307,190.00
|
| | 4,479.700 | 155,669.57
|
| | 0.000 | 0.00
|
| | |
|
0050 9009.00 | 14.58 | 54.000 | 787.32
|
PLACEMENT OF ASPHALTIC CONCRETE FOR DRIVEWAYS ANDINTERSECTIONS | m2 | 54.000 | 787.32
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0051 9021.01 | 195.97 | 477.360 | 93,548.24
|
PERFORMANCE GRADED BINDER (64-22) | Mg | 477.360 | 93,548.24
|
| | 201.000 | 39,389.97
|
| | 110.000 | 21,556.70
|
| | |
|
0052 9030.00 | 25.49 | 274.000 | 6,984.26
|
CONSTRUCTING ASPHALTIC CONCRETE CURB | m | 274.000 | 6,984.26
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0053 9034.00 | 2.13 | 54.000 | 115.02
|
PREPARATION OF INTERSECTIONS AND DRIVEWAYS | m2 | 54.000 | 115.02
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0054 9053.00 | 0.28 | 8,310.000 | 2,326.80
|
TACK COAT | L | 8,310.000 | 2,326.80
|
| | 3,879.920 | 1,086.38
|
| | 0.000 | 0.00
|
| | |
|
0055 9111.00 | 4.89 | 3,477.000 | 17,002.53
|
WATER | kL | 3,477.000 | 17,002.53
|
| | 318.500 | 1,557.46
|
| | 0.000 | 0.00
|
| | |
|
0056 9140.00 | 138.55 | 16.042 | 2,222.62
|
JOINT SEALING - ASPHALT TO CONCRETE | StaM | 16.042 | 2,222.62
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0057 9170.00 | 279.13 | 39.876 | 11,130.59
|
EARTH SHOULDER CONSTRUCTION | StaM | 39.876 | 11,130.59
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0058 9188.50 | 25.56 | 365.000 | 9,329.40
|
SURFACING UNDER GUARDRAIL | m2 | 365.000 | 9,329.40
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0059 9300.50 | 2,771.00 | 1.000 | 2,771.00
|
ASPHALT PAVEMENT SMOOTHNESS TESTING | LS | 1.000 | 2,771.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
4008 2018.00 | 18.334 | 0.000 | 0.00
|
CRUSHED CONCRETE FOR TEMPORARY SURFACING | Mg | 330.000 | 6,050.22
|
Temporary Roads. | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
GROUP 3 CONCRETE PAVEMENT | | Contracted | 940,557.12
|
| | Current | 946,607.34
|
| | In place | 402,739.63
|
| | This Estimate | 21,556.70
|
| | |
|
GROUP 4 CULVERTS | | |
|
0060 P120.60 | 271.00 | 4.000 | 1,084.00
|
1500 mm CULVERT PIPE, TYPE 2 | m | 4.000 | 1,084.00
|
| | 4.000 | 1,084.00
|
| | 0.000 | 0.00
|
| | |
|
0061 P310.48 | 187.05 | 21.500 | 4,021.58
|
1200 mm CULVERT PIPE, TYPE 2,4 OR 5 | m | 21.500 | 4,021.58
|
| | 21.500 | 4,021.58
|
| | 0.000 | 0.00
|
| | |
|
0062 P400.36 | 161.24 | 59.500 | 9,593.78
|
900 mm CULVERT PIPE, TYPE 2,5,7 OR 8 | m | 59.500 | 9,593.78
|
| | 59.500 | 9,593.78
|
| | 29.750 | 4,796.89
|
| | |
|
0063 P500.24 | 75.26 | 58.500 | 4,402.71
|
600 mm CULVERT PIPE, TYPE 2,4,5,7 OR 8 | m | 58.500 | 4,402.71
|
| | 89.000 | 6,698.14
|
| | 0.000 | 0.00
|
| | |
|
0064 P500.30 | 160.68 | 75.500 | 12,131.34
|
750 mm CULVERT PIPE, TYPE 2,4,5,7 or 8 | m | 75.500 | 12,131.34
|
| | 75.500 | 12,131.34
|
| | 0.000 | 0.00
|
| | |
|
0065 0030.40 | 3,562.00 | 1.000 | 3,562.00
|
MOBILIZATION | LS | 1.000 | 3,562.00
|
| | 2.000 | 7,124.00
|
| | 0.000 | 0.00
|
| | |
|
0066 4002.00 | 2.13 | 228.000 | 485.64
|
CAST IRON COVER AND FRAME | kg | 228.000 | 485.64
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0067 4005.00 | 1.71 | 790.000 | 1,350.90
|
CAST IRON RING AND COVER | kg | 790.000 | 1,350.90
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0068 4015.00 | 96.00 | 4.000 | 384.00
|
ADJUST MANHOLE TO GRADE | EACH | 4.000 | 384.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0069 4015.50 | 1,248.00 | 2.000 | 2,496.00
|
RECONSTRUCT MANHOLE | EACH | 2.000 | 2,496.00
|
| | 1.000 | 1,248.00
|
| | 0.000 | 0.00
|
| | |
|
0070 4035.00 | 100.00 | 4.000 | 400.00
|
REMOVE FLARED-END SECTION | EACH | 4.000 | 400.00
|
| | 2.000 | 200.00
|
| | 0.000 | 0.00
|
| | |
|
0071 4035.25 | 163.00 | 2.000 | 326.00
|
REMOVE AND SALVAGE FLARED-END SECTION | EACH | 2.000 | 326.00
|
| | 2.000 | 326.00
|
| | 0.000 | 0.00
|
| | |
|
0072 4040.00 | 127.00 | 2.000 | 254.00
|
REMOVE HEADWALLS FROM CULVERTS | EACH | 2.000 | 254.00
|
| | 2.000 | 254.00
|
| | 0.000 | 0.00
|
| | |
|
0073 4050.01 | 3.33 | 433.000 | 1,441.89
|
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS | m3 | 433.000 | 1,441.89
|
| | 372.500 | 1,240.43
|
| | 0.000 | 0.00
|
| | |
|
0074 4310.24 | 248.00 | 8.000 | 1,984.00
|
600 mm FLARED-END SECTION | EACH | 8.000 | 1,984.00
|
| | 4.000 | 992.00
|
| | 0.000 | 0.00
|
| | |
|
0075 4310.30 | 296.00 | 2.000 | 592.00
|
750 mm FLARED-END SECTION | EACH | 2.000 | 592.00
|
| | 2.000 | 592.00
|
| | 0.000 | 0.00
|
| | |
|
0076 4310.36 | 343.00 | 2.000 | 686.00
|
900 mm FLARED-END SECTION | EACH | 2.000 | 686.00
|
| | 2.000 | 686.00
|
| | 1.000 | 343.00
|
| | |
|
0077 4310.48 | 599.00 | 2.000 | 1,198.00
|
1200 mm FLARED-END SECTION | EACH | 2.000 | 1,198.00
|
| | 2.000 | 1,198.00
|
| | 0.000 | 0.00
|
| | |
|
0078 4461.60 | 111.00 | 2.000 | 222.00
|
INSTALL 1500 mm CONCRETE FLARED-END SECTION | EACH | 2.000 | 222.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
4000 0030.00 | | 1.000 |
|
MOBILIZATION | LS | 2.000 | 0.00
|
Mobilization for Sanitary Sewer Re-location | | 1.000 | 5,000.00
|
| | 0.000 | 0.00
|
| | |
|
4001 4805.24 | 331.3648 | 0.000 | 0.00
|
600 mm STEEL CASING | m | 96.012 | 31,815.00
|
Installed (Open Cut) | | 95.000 | 31,479.66
|
| | 0.000 | 0.00
|
| | |
|
4002 4762.10 | 236.2205 | 0.000 | 0.00
|
250 mm DUCTILE IRON SEWER PIPE | m | 109.728 | 25,920.00
|
| | 108.000 | 25,511.81
|
| | 0.000 | 0.00
|
| | |
|
4003 W301.00 | 126.00 | 0.000 | 0.00
|
600 mm X 250 mm CASING SPACER | EACH | 48.000 | 6,048.00
|
| | 48.000 | 6,048.00
|
| | 0.000 | 0.00
|
| | |
|
4004 W357.40 | 185.00 | 0.000 | 0.00
|
200 mm - 45 DEGREE BEND | EACH | 2.000 | 370.00
|
| | 2.000 | 370.00
|
| | 0.000 | 0.00
|
| | |
|
4005 W358.22 | 196.00 | 0.000 | 0.00
|
250 mm X 200 mm REDUCER | EACH | 2.000 | 392.00
|
| | 2.000 | 392.00
|
| | 0.000 | 0.00
|
| | |
|
4006 W357.43 | 229.00 | 0.000 | 0.00
|
250 mm - 45 DEGREE BEND | EACH | 2.000 | 458.00
|
| | 2.000 | 458.00
|
| | 0.000 | 0.00
|
| | |
|
4007 W180.02 | 1,431.00 | 0.000 | 0.00
|
ANCHOR BLOCKS | LS | 1.000 | 1,431.00
|
| | 1.000 | 1,431.00
|
| | 0.000 | 0.00
|
| | |
|
4011 6603.00 | 22,920.32 | 0.000 | 0.00
|
DEWATERING | LS | 1.000 | 22,920.32
|
CO #1-Sanitary Sewer Relocation At Vallley East. | | 1.000 | 22,920.32
|
| | 1.000 | 22,920.32
|
| | |
|
4013 4050.01 | 11.84 | 0.000 | 0.00
|
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS | m3 | 440.000 | 5,209.60
|
Sta 7900+22 Culvert. | | 440.000 | 5,209.60
|
| | 440.000 | 5,209.60
|
| | |
|
4014 4300.24 | 143.14 | 0.000 | 0.00
|
600 mm CULVERT PIPE | m | 30.500 | 4,365.77
|
Culvert Sta. 7900+22. | | 30.500 | 4,365.77
|
| | 30.500 | 4,365.77
|
| | |
|
4015 4310.24 | 576.22 | 0.000 | 0.00
|
600 mm FLARED-END SECTION | EACH | 2.000 | 1,152.44
|
Culvert Sta. 7900+22. | | 2.000 | 1,152.44
|
| | 2.000 | 1,152.44
|
| | |
|
4016 4976.05 | 3,571.70 | 0.000 | 0.00
|
ADDITIONAL WORK | LS | 1.000 | 3,571.70
|
CO #1 & CO #6-Sanitary Sewer. | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
GROUP 4 CULVERTS | | Contracted | 46,615.84
|
| | Current | 155,269.67
|
| | In place | 151,727.87
|
| | This Estimate | 38,788.02
|
| | |
|
GROUP 5 SEEDING | | |
|
0079 L001.02 | 1,151.64 | 15.600 | 17,965.58
|
SEEDING, TYPE B | ha | 15.600 | 17,965.58
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0080 L020.02 | 1.39 | 1,314.000 | 1,826.46
|
EROSION CONTROL, TYPE B | m2 | 1,314.000 | 1,826.46
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0081 L032.75 | 83.13 | 78.000 | 6,484.14
|
MULCH | Mg | 78.000 | 6,484.14
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0082 0030.50 | 277.00 | 1.000 | 277.00
|
MOBILIZATION | LS | 1.000 | 277.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
GROUP 5 SEEDING | | Contracted | 26,553.18
|
| | Current | 26,553.18
|
| | In place | 0.00
|
| | This Estimate | 0.00
|
| | |
|
GROUP 6 BRIDGE AT STA. 1188+21.542 | | |
|
0083 0030.60 | 73,882.00 | 1.000 | 73,882.00
|
MOBILIZATION | LS | 1.000 | 73,882.00
|
| | 1.000 | 73,882.00
|
| | 0.000 | 0.00
|
| | |
|
0084 3050.15 | 189.36 | 150.800 | 28,555.49
|
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 | m3 | 150.800 | 28,555.49
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0085 3051.10 | 1.33 | 10,270.000 | 13,659.10
|
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES | kg | 10,270.000 | 13,659.10
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0086 6000.10 | 22,297.00 | 1.000 | 22,297.00
|
ABUTMENT NO.1 EXCAVATION | LS | 1.000 | 22,297.00
|
| | 1.000 | 22,297.00
|
| | 0.000 | 0.00
|
| | |
|
0087 6000.11 | 22,297.00 | 1.000 | 22,297.00
|
ABUTMENT NO.2 EXCAVATION | LS | 1.000 | 22,297.00
|
| | 1.000 | 22,297.00
|
| | 0.000 | 0.00
|
| | |
|
0088 6000.20 | 30,935.00 | 1.000 | 30,935.00
|
PIER NO.1 EXCAVATION | LS | 1.000 | 30,935.00
|
| | 1.000 | 30,935.00
|
| | 0.000 | 0.00
|
| | |
|
0089 6005.35 | 124.29 | 28.200 | 3,504.98
|
PRECOMPRESSED POLYURETHANE FOAM JOINT | m | 28.200 | 3,504.98
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0090 6005.83 | 866.00 | 5.000 | 4,330.00
|
FIXED BEARING | EACH | 5.000 | 4,330.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0091 6010.22 | 438.06 | 176.100 | 77,142.37
|
CLASS 47B-20 CONCRETE FOR BRIDGE | m3 | 176.100 | 77,142.37
|
| | 136.100 | 59,619.97
|
| | 136.100 | 59,619.97
|
| | |
|
0092 6010.26 | 313.54 | 233.500 | 73,211.59
|
CLASS 47BD-30 CONCRETE FOR BRIDGE | m3 | 233.500 | 73,211.59
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0093 6071.11 | 238,454.00 | 1.000 | 238,454.00
|
STEEL SUPERSTRUCTURE | LS | 1.000 | 238,454.00
|
AT STA. 1188+21.542 | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0094 6080.00 | 2.48 | 950.000 | 2,356.00
|
STRUCTURAL STEEL FOR SUBSTRUCTURE | kg | 950.000 | 2,356.00
|
| | 950.000 | 2,356.00
|
| | 950.000 | 2,356.00
|
| | |
|
0095 6100.00 | 5,459.00 | 1.000 | 5,459.00
|
FLOOR DRAINS | EACH | 1.000 | 5,459.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0096 6131.50 | 1.33 | 44,130.000 | 58,692.90
|
EPOXY COATED REINFORCING STEEL | kg | 44,130.000 | 58,692.90
|
| | 14,989.000 | 19,935.37
|
| | 13,495.000 | 17,948.35
|
| | |
|
0097 6139.50 | 27.46 | 52.000 | 1,427.92
|
SUBSURFACE DRAINAGE MATTING | m2 | 52.000 | 1,427.92
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0098 6210.50 | 59.16 | 1,185.700 | 70,146.01
|
PIPE PILING | m | 1,185.700 | 70,146.01
|
| | 1,411.580 | 83,509.07
|
| | 0.000 | 0.00
|
| | |
|
0099 6951.12 | 1.75 | 1,905.000 | 3,333.75
|
SHEAR CONNECTORS | EACH | 1,905.000 | 3,333.75
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0100 7110.06 | 116.78 | 62.400 | 7,287.07
|
1.8 METER CHAIN-LINK FENCE | m | 62.400 | 7,287.07
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0101 8091.00 | 11.99 | 155.000 | 1,858.45
|
GRANULAR BACKFILL | m3 | 155.000 | 1,858.45
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
6000 6970.00 | 690.00 | 0.000 | 0.00
|
FREIGHT | LS | 1.000 | 690.00
|
Item #96, Epoxy Coated Reinforcing Steel. | | 1.000 | 690.00
|
| | 0.000 | 0.00
|
| | |
|
6001 6210.61 | 118.32 | 0.000 | 0.00
|
PILE SPLICE | EACH | 34.000 | 4,022.88
|
Item #98, Pipe Piling Splices | | 34.000 | 4,022.88
|
| | 0.000 | 0.00
|
| | |
|
GROUP 6 BRIDGE AT STA. 1188+21.542 | | Contracted | 738,829.63
|
| | Current | 743,542.51
|
| | In place | 319,544.29
|
| | This Estimate | 79,924.32
|
| | |
|
GROUP 6A BRIDGE AT STA. 1294+95.455 | | |
|
0102 0030.60 | 105,955.00 | 1.000 | 105,955.00
|
MOBILIZATION | LS | 1.000 | 105,955.00
|
| | 1.000 | 105,955.00
|
| | 0.000 | 0.00
|
| | |
|
0103 3050.15 | 190.22 | 158.900 | 30,225.96
|
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 | m3 | 158.900 | 30,225.96
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0104 3051.10 | 1.31 | 10,365.000 | 13,578.15
|
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES | kg | 10,365.000 | 13,578.15
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0105 6000.10 | 2,252.00 | 1.000 | 2,252.00
|
ABUTMENT NO.1 EXCAVATION | LS | 1.000 | 2,252.00
|
| | 1.000 | 2,252.00
|
| | 0.000 | 0.00
|
| | |
|
0106 6000.11 | 2,252.00 | 1.000 | 2,252.00
|
ABUTMENT NO.2 EXCAVATION | LS | 1.000 | 2,252.00
|
| | 1.000 | 2,252.00
|
| | 0.000 | 0.00
|
| | |
|
0107 6000.20 | 9,256.00 | 1.000 | 9,256.00
|
PIER NO.1 EXCAVATION | LS | 1.000 | 9,256.00
|
| | 1.000 | 9,256.00
|
| | 0.000 | 0.00
|
| | |
|
0108 6000.21 | 8,056.00 | 1.000 | 8,056.00
|
PIER NO.2 EXCAVATION | LS | 1.000 | 8,056.00
|
| | 1.000 | 8,056.00
|
| | 0.000 | 0.00
|
| | |
|
0109 6000.22 | 5,401.00 | 1.000 | 5,401.00
|
PIER NO.3 EXCAVATION | LS | 1.000 | 5,401.00
|
| | 1.000 | 5,401.00
|
| | 0.000 | 0.00
|
| | |
|
0110 6000.23 | 5,859.00 | 1.000 | 5,859.00
|
PIER NO.4 EXCAVATION | LS | 1.000 | 5,859.00
|
| | 1.000 | 5,859.00
|
| | 0.000 | 0.00
|
| | |
|
0111 6005.35 | 121.11 | 33.900 | 4,105.63
|
PRECOMPRESSED POLYURETHANE FOAM JOINT | m | 33.900 | 4,105.63
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0112 6005.78 | 374.34 | 24.000 | 8,984.16
|
EXPANSION BEARING, TFE TYPE | EACH | 24.000 | 8,984.16
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0113 6005.83 | 86.71 | 24.000 | 2,081.04
|
FIXED BEARING | EACH | 24.000 | 2,081.04
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0114 6010.22 | 308.02 | 475.000 | 146,309.50
|
CLASS 47B-20 CONCRETE FOR BRIDGE | m3 | 475.000 | 146,309.50
|
| | 392.000 | 120,743.84
|
| | 0.000 | 0.00
|
| | |
|
0115 6010.26 | 272.33 | 579.000 | 157,679.07
|
CLASS 47BD-30 CONCRETE FOR BRIDGE | m3 | 579.000 | 157,679.07
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0116 6011.11 | 325,528.00 | 1.000 | 325,528.00
|
PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE | LS | 1.000 | 325,528.00
|
AT STA, 1294+95.455 | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0117 6080.00 | 2.42 | 1,360.000 | 3,291.20
|
STRUCTURAL STEEL FOR SUBSTRUCTURE | kg | 1,360.000 | 3,291.20
|
| | 1,360.000 | 3,291.20
|
| | 1,360.000 | 3,291.20
|
| | |
|
0118 6095.00 | 479.69 | 25.000 | 11,992.25
|
STEEL DIAPHRAGM | EACH | 25.000 | 11,992.25
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0119 6100.00 | 593.00 | 4.000 | 2,372.00
|
FLOOR DRAINS | EACH | 4.000 | 2,372.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0120 6107.00 | 40.93 | 826.000 | 33,808.18
|
CONCRETE SLOPE PROTECTION | m2 | 826.000 | 33,808.18
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0121 6131.50 | 1.30 | 111,135.000 | 144,475.50
|
EPOXY COATED REINFORCING STEEL | kg | 111,135.000 | 144,475.50
|
| | 44,630.000 | 58,019.00
|
| | 0.000 | 0.00
|
| | |
|
0122 6139.50 | 27.59 | 56.000 | 1,545.04
|
SUBSURFACE DRAINAGE MATTING | m2 | 56.000 | 1,545.04
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0123 6200.00 | 72.95 | 1,603.500 | 116,975.33
|
CONCRETE PILING | m | 1,603.500 | 116,975.33
|
| | 1,603.200 | 116,953.44
|
| | 0.000 | 0.00
|
| | |
|
0124 6210.12 | 73.07 | 408.000 | 29,812.56
|
HP 250 mm X 62 kg STEEL PILING | m | 408.000 | 29,812.56
|
| | 784.800 | 57,345.34
|
| | 0.000 | 0.00
|
| | |
|
0125 6210.14 | 54.69 | 549.000 | 30,024.81
|
HP 310 mm X 79 kg STEEL PILING | m | 549.000 | 30,024.81
|
| | 1,049.540 | 57,399.34
|
| | 0.000 | 0.00
|
| | |
|
0126 7110.06 | 116.70 | 67.200 | 7,842.24
|
1.8 METER CHAIN-LINK FENCE | m | 67.200 | 7,842.24
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0127 8091.00 | 12.01 | 180.000 | 2,161.80
|
GRANULAR BACKFILL | m3 | 180.000 | 2,161.80
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
GROUP 6A BRIDGE AT STA. 1294+95.455 | | Contracted | 1,211,823.41
|
| | Current | 1,211,823.41
|
| | In place | 552,783.16
|
| | This Estimate | 3,291.20
|
| | |
|
GROUP 7 GUARDRAIL | | |
|
0128 0030.70 | 718.00 | 1.000 | 718.00
|
MOBILIZATION | LS | 1.000 | 718.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0129 7011.20 | 48.22 | 72.390 | 3,490.65
|
W-BEAM GUARDRAIL | m | 72.390 | 3,490.65
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0130 7020.00 | 1,386.00 | 8.000 | 11,088.00
|
BRIDGE APPROACH SECTIONS | EACH | 8.000 | 11,088.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0131 7021.70 | 1,829.00 | 8.000 | 14,632.00
|
GUARDRAIL END TREATMENT, SRT-350 | EACH | 8.000 | 14,632.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
GROUP 7 GUARDRAIL | | Contracted | 29,928.65
|
| | Current | 29,928.65
|
| | In place | 0.00
|
| | This Estimate | 0.00
|
| | |
|
GROUP 10 GENERAL ITEMS | | |
|
0132 0001.08 | 0.50 | 400.000 | 200.00
|
BARRICADE, TYPE II | BDAY | 400.000 | 200.00
|
| | 5,288.000 | 2,644.00
|
| | 503.000 | 251.50
|
| | |
|
0133 0001.10 | 1.94 | 5,609.000 | 10,881.46
|
BARRICADE, TYPE III | BDAY | 5,609.000 | 10,881.46
|
| | 5,977.000 | 11,595.38
|
| | 731.000 | 1,418.14
|
| | |
|
0134 0001.30 | 1.39 | 1,334.000 | 1,854.26
|
TYPE B HIGH INTENSITY WARNING LIGHT | LDAY | 1,334.000 | 1,854.26
|
| | 2,016.000 | 2,802.24
|
| | 180.000 | 250.20
|
| | |
|
0135 0001.75 | 3.88 | 160.000 | 620.80
|
TEMPORARY SIGN DAY | EACH | 160.000 | 620.80
|
| | 315.000 | 1,222.20
|
| | 0.000 | 0.00
|
| | |
|
0136 0001.90 | 0.39 | 14,940.000 | 5,826.60
|
SIGN DAY | EACH | 14,940.000 | 5,826.60
|
| | 7,387.000 | 2,880.93
|
| | 879.000 | 342.81
|
| | |
|
0137 0002.30 | 2.00 | 200.000 | 400.00
|
PAVEMENT MARKING REMOVAL | m | 200.000 | 400.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0138 0002.44 | 0.67 | 1,200.000 | 804.00
|
TEMPORARY PAVEMENT MARKING, TYPE PAINT | m | 1,200.000 | 804.00
|
| | 2,915.700 | 1,953.52
|
| | 0.000 | 0.00
|
| | |
|
0139 0003.10 | 327.83 | 50.000 | 16,391.50
|
FLAGGING | DAY | 50.000 | 16,391.50
|
| | 40.000 | 13,113.20
|
| | 0.000 | 0.00
|
| | |
|
0140 0010.04 | 582.00 | 1.000 | 582.00
|
FIELD OFFICE | EACH | 1.000 | 582.00
|
| | 1.000 | 582.00
|
| | 0.000 | 0.00
|
| | |
|
0141 0020.00 | 0.80 | 1,000.000 | 800.00
|
TRAINING | HOUR | 1,000.000 | 800.00
|
| | 749.000 | 599.20
|
| | 0.000 | 0.00
|
| | |
|
0142 0030.10 | 111.00 | 1.000 | 111.00
|
MOBILIZATION | LS | 1.000 | 111.00
|
| | 1.000 | 111.00
|
| | 0.000 | 0.00
|
| | |
|
4009 0001.06 | 0.263 | 0.000 | 0.00
|
VERTICAL PANELS | BDAY | 13,500.000 | 3,550.50
|
Traffic Control. | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
GROUP 10 GENERAL ITEMS | | Contracted | 38,471.62
|
| | Current | 42,022.12
|
| | In place | 37,503.67
|
| | This Estimate | 2,262.65
|
| | |
|
Totals for contract | | Contracted | 5,077,869.74
|
---|
| | Current | 5,197,303.50
|
---|
| | In place | 3,283,408.30
|
---|
| | This Estimate | 166,729.79
|
---|