Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:0774 DIXON CONSTRUCTION CO.
Contract ID:3329
Estimate Number:0022
Pay Period End Date:07.21.2001
Contract Location:
ALBION EASTEstimate Type:PROG
Contractor:
DIXON CONSTRUCTION CO.Date Let:01.13.2000
409 DRIFTWOODDate Awarded:01.20.2000
PO BOX KDate Contract Executed:02.10.2000
Date Notice to Proceed:02.10.2000
CORRECTIONVILLE IA 51016-0047Date Work Began:04.03.2000
Phone:Date Physical Work Completed:
(712)372-4224Date Accepted:
Escrow Agent:
Surety Co:
EMPLOYERS MUTUAL CASUALTY COMPANY
Counties
BOONE
Project Number PCT Fed State Project Number Description
31329 000B  0.000 EACSTPD-91-5(112)  GR CULV BR GDRL BIT
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$1,030,103.07$1,018,534.92$11,568.15
$1,039,060.81Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$1,030,103.07$1,018,534.92$11,568.15
$928,286.29Retainage$-10,301.03$-10,185.35$-115.68
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
99.14%Net Earnings$1,019,802.04$1,008,349.57$11,452.47
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$.00$.00$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments$.00$.00$.00
Payment$1,019,802.04$1,008,349.57$11,452.47
Project ManagerDiv. Head/Dist. Eng.
Hyland, Tom07.23.2001Boyle, Pat07.26.2001
Constr. Estimate Eng.Materials Eng.
Bartos, Steve07.26.2001
Controller Div. Processed
Burling, Laurie07.27.2001
Detailed breakdown of stockpiled materials
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          L006.00 75.003.500262.50
COVER CROP SEEDING ha 3.500262.50
5.201390.08
1.701127.58

0002                          L020.00 1.504,845.0007,267.50
EROSION CONTROL m2 4,845.0007,267.50
4,845.0007,267.50
0.0000.00

0003                          L020.01 1.503,216.0004,824.00
EROSION CONTROL, TYPE A m2 3,216.0004,824.00
3,216.0004,824.00
0.0000.00

0004                          L020.10 5.473,513.00019,216.11
EROSION CONTROL, TYPE HV m2 3,513.00019,216.11
3,513.00019,216.11
0.0000.00

0005                          L021.01 28.00260.0007,280.00
EROSION CHECKS, TYPE A BALE260.0007,280.00
264.0007,392.00
0.0000.00

0006                          L022.11 8.20769.4006,309.08
FABRIC SILT FENCE-LOW POROSITY m 769.4006,309.08
738.4006,054.88
0.0000.00

0007                          L022.75 16.40258.0004,231.20
TEMPORARY SILT CHECK m 258.0004,231.20
284.7004,669.08
0.0000.00

0008                          0030.10 10,000.001.00010,000.00
MOBILIZATION LS 1.00010,000.00
1.00010,000.00
0.0000.00

0009                          1009.00 1,800.001.0001,800.00
GENERAL CLEARING AND GRUBBING LS 1.0001,800.00
1.0001,800.00
0.0000.00

0010                          1010.01 1.5936,574.00058,152.66
EXCAVATION (ESTABLISHED QUANTITY) m3 36,574.00058,152.66
38,441.00061,121.19
1,867.0002,968.53

0011                          1011.00 1.501,826.0002,739.00
WATER kL 1,826.0002,739.00
0.0000.00
0.0000.00

0012                          1012.00 65.006.000390.00
RIGHT-OF-WAY MARKERS EACH6.000390.00
6.000390.00
0.0000.00

0013                          1040.05 0.2818,480.0005,174.40
TEMPORARY SLOPE PROTECTION m2 18,480.0005,174.40
18,480.0005,174.40
0.0000.00

0014                          1041.00 0.2411,900.0002,856.00
SALVAGING AND PLACING TOPSOIL m2 11,900.0002,856.00
11,900.0002,856.00
0.0000.00

0015                          1102.00 2.825,679.00016,014.78
REMOVE ASPHALT SURFACE m2 5,679.00016,014.78
603.4171,701.64
0.0000.00

0016                          1120.00 120.002.000240.00
REMOVE DISCHARGE STRUCTURE EACH2.000240.00
2.000240.00
0.0000.00

0017                          1125.00 1,950.001.0001,950.00
CLEAR TRACT EACH1.0001,950.00
1.0001,950.00
0.0000.00

0018                          1500.60 36.0075.0002,700.00
INSTALL 1500 mm CORRUGATED METAL PIPE m 75.0002,700.00
82.2972,962.69
0.0000.00

0019                          7017.00 17.40328.0005,707.20
REMOVE GUARDRAIL m 328.0005,707.20
333.0005,794.20
0.0000.00

0020                          9110.01 65.0020.0001,300.00
RENTAL OF LOADER, FULLY OPERATED HOUR20.0001,300.00
29.0001,885.00
0.0000.00

0021                          9110.03 50.0020.0001,000.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR20.0001,000.00
0.0000.00
0.0000.00

0022                          9110.07 40.0020.000800.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR20.000800.00
7.500300.00
0.0000.00

0410                          9110.10 89.250.0000.00
RENTAL OF EXCAVATOR, FULLY OPERATED HOUR5.000446.25
6.500580.13
0.0000.00

0411                          9110.02 63.000.0000.00
RENTAL OF MOTOR GRADER, FULLY OPERATED HOUR25.0001,575.00
25.5001,606.50
0.0000.00

0412                          9110.12 73.500.0000.00
RENTAL OF SCRAPER, FULLY OPERATED HOUR7.000514.50
6.000441.00
0.0000.00

0413                          9110.03 52.500.0000.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR5.000262.50
1.00052.50
0.0000.00

GROUP 1 GRADINGContracted160,214.43
Current163,012.68
In place148,668.90
This Estimate3,096.11

GROUP 4 CULVERT
0023                          0030.40 16,000.001.00016,000.00
MOBILIZATION LS 1.00016,000.00
1.00016,000.00
0.0000.00

0024                          1043.50 2.20450.000990.00
RIPRAP FILTER FABRIC m2 450.000990.00
450.000990.00
450.000990.00

0025                          4040.00 228.001.000228.00
REMOVE HEADWALLS FROM CULVERTS EACH1.000228.00
1.000228.00
0.0000.00

0026                          4045.00 5,556.001.0005,556.00
REMOVE STRUCTURE EACH1.0005,556.00
1.0005,556.00
0.0000.00

0027                          4050.01 21.006.000126.00
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 6.000126.00
6.000126.00
0.0000.00

0028                          4051.01 14.161,161.00016,439.76
EXCAVATION FOR BOX CULVERTS m3 1,161.00016,439.76
1,161.00016,439.76
0.0000.00

0029                          4101.06 414.80181.01075,082.95
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 181.01075,082.95
181.01075,082.95
0.0000.00

0030                          4151.00 1.4610,008.00014,611.68
REINFORCING STEEL FOR BOX CULVERT kg 10,008.00014,611.68
10,008.00014,611.68
0.0000.00

0031                          4350.24 70.0011.000770.00
600 mm CORRUGATED METAL PIPE m 11.000770.00
11.000770.00
0.0000.00

0032                          4360.24 220.001.000220.00
600 mm METAL FLARED-END SECTION EACH1.000220.00
1.000220.00
0.0000.00

0033                          6104.00 19.00380.0007,220.00
BROKEN CONCRETE RIPRAP Mg 380.0007,220.00
380.0007,220.00
0.0000.00

0407                          1500.24 4.600.0000.00
INSTALL 600 mm CORRUGATED METAL PIPE m 9.14042.04
9.14042.04
0.0000.00

0408                          2011.05 18.520.0000.00
CRUSHED ROCK FOR TEMPORARY SURFACING Mg 12.972240.24
12.972240.24
0.0000.00

0423                          2015.02 41.480.0000.00
CRUSHED ROCK BEDDING m3 18.160753.28
18.160753.28
0.0000.00

409                           2001.20 6.950.0000.00
GRAVEL FOR TEMPORARY SURFACING m3 23.841165.69
23.851165.76
0.0000.00

GROUP 4 CULVERTContracted137,244.39
Current138,445.65
In place138,445.71
This Estimate990.00

GROUP 6 BRIDGE AT STA. 78+57
0034                          0030.60 70,000.001.00070,000.00
MOBILIZATION LS 1.00070,000.00
1.00070,000.00
0.0000.00

0035                          3017.55 19.00958.00018,202.00
SOIL GRID CONFINEMENT SYSTEM m2 958.00018,202.00
0.0000.00
0.0000.00

0036                          3050.15 235.80129.00030,418.20
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 m3 129.00030,418.20
129.00030,418.20
0.0000.00

0037                          3051.10 1.108,389.0009,227.90
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES kg 8,389.0009,227.90
8,389.0009,227.90
0.0000.00

0038                          6000.10 7,000.001.0007,000.00
ABUTMENT NO.1 EXCAVATION LS 1.0007,000.00
1.0007,000.00
0.0000.00

0039                          6000.11 7,000.001.0007,000.00
ABUTMENT NO.2 EXCAVATION LS 1.0007,000.00
1.0007,000.00
0.0000.00

0040                          6005.35 200.0027.0005,400.00
PRECOMPRESSED POLYURETHANE FOAM JOINT m 27.0005,400.00
27.0005,400.00
0.0000.00

0041                          6005.78 1,000.004.0004,000.00
EXPANSION BEARING, TFE TYPE EACH4.0004,000.00
4.0004,000.00
0.0000.00

0042                          6005.83 800.004.0003,200.00
FIXED BEARING EACH4.0003,200.00
4.0003,200.00
0.0000.00

0043                          6010.22 393.0079.80031,361.40
CLASS 47B-20 CONCRETE FOR BRIDGE m3 79.80031,361.40
79.80031,361.40
0.0000.00

0044                          6010.26 340.60179.10061,001.46
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 179.10061,001.46
179.10061,001.47
0.0000.00

0045                          6011.11 100,000.001.000100,000.00
PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE LS 1.000100,000.00
1.000100,000.00
0.0000.00

0046                          6040.00 27,000.001.00027,000.00
REMOVE STRUCTURE EACH1.00027,000.00
1.00027,000.00
0.0000.00

0047                          6080.00 5.50206.0001,133.00
STRUCTURAL STEEL FOR SUBSTRUCTURE kg 206.0001,133.00
206.0001,133.00
0.0000.00

0048                          6095.00 900.003.0002,700.00
STEEL DIAPHRAGM EACH3.0002,700.00
3.0002,700.00
0.0000.00

0049                          6131.50 1.1020,426.00022,468.60
EPOXY COATED REINFORCING STEEL kg 20,426.00022,468.60
20,954.00023,049.40
0.0000.00

0050                          6139.50 32.0072.0002,304.00
SUBSURFACE DRAINAGE MATTING m2 72.0002,304.00
72.0002,304.00
0.0000.00

0051                          6210.50 25.00980.00024,500.00
PIPE PILING m 980.00024,500.00
984.39024,609.75
0.0000.00

0052                          6310.00 129.12263.00033,958.56
STEEL SHEET PILING m2 263.00033,958.56
255.62933,006.82
0.0000.00

0053                          8091.00 30.00286.0008,580.00
GRANULAR BACKFILL m3 286.0008,580.00
286.0008,580.00
0.0000.00

0415                          3017.55 19.000.0000.00
SOIL GRID CONFINEMENT SYSTEM m2 -958.000-18,202.00
0.0000.00
0.0000.00

0416                          3017.55 24.150.0000.00
SOIL GRID CONFINEMENT SYSTEM m2 958.00023,135.70
958.00023,135.70
0.0000.00

0418                          0095.00 522.000.0000.00
ADDITIONAL FREIGHT LS 1.000522.00
1.000522.00
0.0000.00

0419                          3800.50 0.60950.0000.00
REINFORCING STEEL STOCKPILED kg 425.000259.04
425.000259.04
0.0000.00

0601                          6210.61 50.000.0000.00
PILE SPLICE EACH6.000300.00
7.000350.00
0.0000.00

GROUP 6 BRIDGE AT STA. 78+57Contracted469,455.12
Current475,469.86
In place475,258.68
This Estimate0.00

GROUP 7 GUARDRAIL
0054                          0030.70 2,500.001.0002,500.00
MOBILIZATION LS 1.0002,500.00
1.0002,500.00
0.0000.00

0055                          7011.20 41.0060.9602,499.36
W-BEAM GUARDRAIL m 60.9602,499.36
64.7702,655.57
0.0000.00

0056                          7020.00 1,200.004.0004,800.00
BRIDGE APPROACH SECTIONS EACH4.0004,800.00
4.0004,800.00
0.0000.00

0057                          7021.70 1,400.004.0005,600.00
GUARDRAIL END TREATMENT, SRT-350 EACH4.0005,600.00
4.0005,600.00
0.0000.00

GROUP 7 GUARDRAILContracted15,399.36
Current15,399.36
In place15,555.57
This Estimate0.00

GROUP 9 BITUMINOUS
0058                          L001.01 1,930.003.5006,755.00
SEEDING, TYPE A ha 3.5006,755.00
3.0085,805.44
3.0085,805.44

0059                          L001.02 1,520.000.500760.00
SEEDING, TYPE B ha 0.500760.00
0.372565.44
0.372565.44

0060                          L032.75 73.0018.0001,314.00
MULCH Mg 18.0001,314.00
11.583845.56
11.583845.56

0061                          0030.90 22,400.001.00022,400.00
MOBILIZATION LS 1.00022,400.00
1.00022,400.00
0.0000.00

0062                          2010.00 45.0010.000450.00
CRUSHED ROCK SURFACE COURSE m3 10.000450.00
43.2351,945.58
0.0000.00

0063                          2020.00 12.0068.000816.00
SPECIAL SURFACE COURSE FOR MAILBOX TURNOUTS m2 68.000816.00
68.000816.00
0.0000.00

0064                          2020.50 49.60622.00030,851.20
SURFACING m2 622.00030,851.20
692.89234,367.44
0.0000.00

0065                          2021.00 100.001.000100.00
MAILBOX POST EACH1.000100.00
1.000100.00
0.0000.00

0066                          8008.00 137.1038.0005,209.80
ARMOR COAT AGGREGATE m3 38.0005,209.80
0.0000.00
0.0000.00

0067                          9052.00 261.607.6802,009.09
ARMOR COAT EMULSIFIED ASPHALT kL 7.6802,009.09
6.8701,797.19
0.0000.00

0068                          9111.00 2.00129.000258.00
WATER kL 129.000258.00
0.0000.00
0.0000.00

0069                          9170.00 250.0015.6643,916.00
EARTH SHOULDER CONSTRUCTION StaM15.6643,916.00
10.1502,537.50
0.0000.00

0070                          9173.20 2.206,094.00013,406.80
SUBGRADE PREPARATION m2 6,094.00013,406.80
5,862.89212,898.36
0.0000.00

0071                          9188.01 5.205,170.00026,884.00
BITUMINOUS SURFACE COURSE m2 5,170.00026,884.00
5,170.00026,884.00
0.0000.00

0072                          9188.50 44.50302.00013,439.00
SURFACING UNDER GUARDRAIL m2 302.00013,439.00
302.00013,439.00
0.0000.00

0401                          9006.63 52.083670.0000.00
ASPHALTIC CONCRETE, TYPE 11 OR 11R Mg 0.0000.00
0.0000.00
0.0000.00

0402                          0030.02 3,150.000.0000.00
REMOBILIZATION LS 0.0000.00
0.0000.00
0.0000.00

0404                          9006.63 52.083670.0000.00
ASPHALTIC CONCRETE, TYPE 11 OR 11R Mg 1,363.38071,009.83
1,363.38071,009.83
0.0000.00

0405                          0030.02 3,150.000.0000.00
REMOBILIZATION LS 1.0003,150.00
1.0003,150.00
0.0000.00

0406                          0003.10 178.500.0000.00
FLAGGING DAY 3.000535.50
3.000535.50
0.0000.00

0414                          A900.10 5,670.000.0000.00
ADDITIONAL WORK EACH1.0005,670.00
1.0005,670.00
0.0000.00

0421                          1102.01 3.210.0000.00
REMOVE ASPHALT SURFACE m2 5,198.00016,685.58
5,198.00016,685.58
0.0000.00

0422                          0030.00 1.000
MOBILIZATION LS 2.0000.00
1.000498.75
0.0000.00

GROUP 9 BITUMINOUSContracted128,568.89
Current226,118.55
In place221,951.17
This Estimate7,216.44

GROUP 10 GENERAL ITEMS
0073                          0001.08 0.502,835.0001,417.50
BARRICADE, TYPE II BDAY2,835.0001,417.50
17,156.0008,578.00
0.0000.00

0074                          0001.10 1.501,566.0002,349.00
BARRICADE, TYPE III BDAY1,566.0002,349.00
4,288.0006,432.00
48.00072.00

0075                          0001.30 1.80432.000777.60
TYPE B HIGH INTENSITY WARNING LIGHT LDAY432.000777.60
793.0001,427.40
32.00057.60

0076                          0001.90 0.507,020.0003,510.00
SIGN DAY EACH7,020.0003,510.00
12,909.0006,454.50
272.000136.00

0077                          0002.30 2.50140.000350.00
PAVEMENT MARKING REMOVAL m 140.000350.00
175.000437.50
0.0000.00

0078                          0002.39 1.002,500.0002,500.00
TEMPORARY PAVEMENT MARKING, TYPE II m 2,500.0002,500.00
183.000183.00
0.0000.00

0079                          0010.04 3,000.001.0003,000.00
FIELD OFFICE EACH1.0003,000.00
0.0000.00
0.0000.00

0080                          0030.00 3,500.001.0003,500.00
MOBILIZATION LS 1.0003,500.00
1.0003,500.00
0.0000.00

0403                          0003.10 178.500.0000.00
FLAGGING DAY 0.0000.00
0.0000.00
0.0000.00

0420                          0002.31 0.78750.0000.00
TEMPORARY PAVEMENT MARKING m 4,077.0003,210.64
4,077.0003,210.64
0.0000.00

GROUP 10 GENERAL ITEMSContracted17,404.10
Current20,614.74
In place30,223.04
This Estimate265.60

Totals for contractContracted928,286.29
Current1,038,562.08
In place1,030,103.07
This Estimate11,568.15