| | | 1. Contracted
|
---|
| | | 2. Current
|
---|
| | | 3. To date
|
---|
Item Nbr Item Code | Unit Price | | 4. This Est
|
---|
Item Description | Units | Qty | Amount
|
---|
GROUP 6 BRIDGE AT STA. 30+53.55 | | |
|
0001 L001.01 | 600.00 | 2.000 | 1,200.00
|
SEEDING, TYPE A | ha | 2.000 | 1,200.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0002 L006.00 | 2,000.00 | 2.000 | 4,000.00
|
COVER CROP SEEDING | ha | 2.000 | 4,000.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0003 L032.75 | 85.00 | 10.000 | 850.00
|
MULCH | Mg | 10.000 | 850.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0004 0001.10 | 1.60 | 1,946.000 | 3,113.60
|
BARRICADE, TYPE III | BDAY | 1,946.000 | 3,113.60
|
| | 2,232.000 | 3,571.20
|
| | 336.000 | 537.60
|
| | |
|
0005 0001.30 | 1.10 | 556.000 | 611.60
|
TYPE B HIGH INTENSITY WARNING LIGHT | LDAY | 556.000 | 611.60
|
| | 558.000 | 613.80
|
| | 84.000 | 92.40
|
| | |
|
0006 0001.90 | 0.40 | 3,892.000 | 1,556.80
|
SIGN DAY | EACH | 3,892.000 | 1,556.80
|
| | 3,036.000 | 1,214.40
|
| | 476.000 | 190.40
|
| | |
|
0007 0030.60 | 25,000.00 | 1.000 | 25,000.00
|
MOBILIZATION | LS | 1.000 | 25,000.00
|
| | 1.000 | 25,000.00
|
| | 0.000 | 0.00
|
| | |
|
0008 1009.00 | 3,000.00 | 1.000 | 3,000.00
|
GENERAL CLEARING AND GRUBBING | LS | 1.000 | 3,000.00
|
| | 0.800 | 2,400.00
|
| | 0.800 | 2,400.00
|
| | |
|
0009 1010.01 | 2.15 | 4,782.000 | 10,281.30
|
EXCAVATION (ESTABLISHED QUANTITY) | m3 | 4,782.000 | 10,281.30
|
| | 3,500.000 | 7,525.00
|
| | 3,500.000 | 7,525.00
|
| | |
|
0010 1011.00 | 2.00 | 113.000 | 226.00
|
WATER | kL | 113.000 | 226.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0011 1300.24 | 52.00 | 18.000 | 936.00
|
600 mm DRIVEWAY CULVERT PIPE | m | 18.000 | 936.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0012 2010.00 | 42.00 | 126.000 | 5,292.00
|
CRUSHED ROCK SURFACE COURSE | m3 | 126.000 | 5,292.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0013 3050.15 | 290.00 | 37.600 | 10,904.00
|
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 | m3 | 37.600 | 10,904.00
|
| | 37.600 | 10,904.00
|
| | 0.000 | 0.00
|
| | |
|
0014 3051.10 | 1.20 | 2,388.000 | 2,865.60
|
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES | kg | 2,388.000 | 2,865.60
|
| | 2,388.000 | 2,865.60
|
| | 0.000 | 0.00
|
| | |
|
0015 4043.00 | 24.00 | 8.600 | 206.40
|
REMOVE CULVERT PIPE | m | 8.600 | 206.40
|
| | 8.600 | 206.40
|
| | 8.600 | 206.40
|
| | |
|
0016 4050.01 | 3.00 | 373.000 | 1,119.00
|
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS | m3 | 373.000 | 1,119.00
|
| | 118.000 | 354.00
|
| | 118.000 | 354.00
|
| | |
|
0017 4300.24 | 57.00 | 20.000 | 1,140.00
|
600 mm CULVERT PIPE | m | 20.000 | 1,140.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0018 4300.36 | 76.00 | 71.000 | 5,396.00
|
900 mm CULVERT PIPE | m | 71.000 | 5,396.00
|
| | 19.000 | 1,444.00
|
| | 19.000 | 1,444.00
|
| | |
|
0019 4310.24 | 225.00 | 1.000 | 225.00
|
600 mm FLARED-END SECTION | EACH | 1.000 | 225.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0020 4310.36 | 370.00 | 6.000 | 2,220.00
|
900 mm FLARED-END SECTION | EACH | 6.000 | 2,220.00
|
| | 4.000 | 1,480.00
|
| | 4.000 | 1,480.00
|
| | |
|
0021 6000.10 | 2,000.00 | 1.000 | 2,000.00
|
ABUTMENT NO.1 EXCAVATION | LS | 1.000 | 2,000.00
|
| | 1.000 | 2,000.00
|
| | 0.000 | 0.00
|
| | |
|
0022 6000.11 | 2,000.00 | 1.000 | 2,000.00
|
ABUTMENT NO.2 EXCAVATION | LS | 1.000 | 2,000.00
|
| | 1.000 | 2,000.00
|
| | 0.000 | 0.00
|
| | |
|
0023 6001.00 | 7,000.00 | 1.000 | 7,000.00
|
BENT NO.1 EXCAVATION | LS | 1.000 | 7,000.00
|
| | 1.000 | 7,000.00
|
| | 0.000 | 0.00
|
| | |
|
0024 6001.01 | 7,000.00 | 1.000 | 7,000.00
|
BENT NO.2 EXCAVATION | LS | 1.000 | 7,000.00
|
| | 1.000 | 7,000.00
|
| | 0.000 | 0.00
|
| | |
|
0025 6010.22 | 310.00 | 198.600 | 61,566.00
|
CLASS 47B-20 CONCRETE FOR BRIDGE | m3 | 198.600 | 61,566.00
|
| | 198.600 | 61,566.00
|
| | 0.000 | 0.00
|
| | |
|
0026 6010.26 | 300.00 | 184.500 | 55,350.00
|
CLASS 47BD-30 CONCRETE FOR BRIDGE | m3 | 184.500 | 55,350.00
|
| | 184.500 | 55,350.00
|
| | 0.000 | 0.00
|
| | |
|
0027 6020.00 | 1.10 | 27,690.000 | 30,459.00
|
REINFORCING STEEL FOR BRIDGE | kg | 27,690.000 | 30,459.00
|
| | 27,690.000 | 30,459.00
|
| | 0.000 | 0.00
|
| | |
|
0028 6040.00 | 10,000.00 | 1.000 | 10,000.00
|
REMOVE STRUCTURE | EACH | 1.000 | 10,000.00
|
AT STA. 30+59 | | 1.000 | 10,000.00
|
| | 0.000 | 0.00
|
| | |
|
0029 6080.00 | 4.00 | 1,256.000 | 5,024.00
|
STRUCTURAL STEEL FOR SUBSTRUCTURE | kg | 1,256.000 | 5,024.00
|
| | 1,256.000 | 5,024.00
|
| | 0.000 | 0.00
|
| | |
|
0030 6105.02 | 25.00 | 864.000 | 21,600.00
|
ROCK RIPRAP, TYPE B | Mg | 864.000 | 21,600.00
|
| | 120.000 | 3,000.00
|
| | 0.000 | 0.00
|
| | |
|
0031 6210.12 | 70.00 | 377.000 | 26,390.00
|
HP 250 mm X 62 kg STEEL PILING | m | 377.000 | 26,390.00
|
| | 370.500 | 25,935.00
|
| | 0.000 | 0.00
|
| | |
|
0032 7020.00 | 1,400.00 | 4.000 | 5,600.00
|
BRIDGE APPROACH SECTIONS | EACH | 4.000 | 5,600.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0033 7021.45 | 1,200.00 | 4.000 | 4,800.00
|
BREAKAWAY CABLE TERMINAL | EACH | 4.000 | 4,800.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0601 6210.32 | 42.00 | 0.000 | 0.00
|
PAY CUT-OFF FOR 250 mm X 62 kg STEEL PILING | m | 20.000 | 840.00
|
In accordance with Paragraph 2, Subsection 703.05 of the 1997 Metric Specs. | | 6.500 | 273.00
|
| | 0.000 | 0.00
|
| | |
|
GROUP 6 BRIDGE AT STA. 30+53.55 | | Contracted | 318,932.30
|
| | Current | 319,772.30
|
| | In place | 267,185.40
|
| | This Estimate | 14,229.80
|
| | |
|
Totals for contract | | Contracted | 318,932.30
|
---|
| | Current | 319,772.30
|
---|
| | In place | 267,185.40
|
---|
| | This Estimate | 14,229.80
|
---|