Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:2282 KNIGHT ASPHALT, INC.
Contract ID:3352X
Estimate Number:0003
Pay Period End Date:05.18.2002
Contract Location:
NIOBRARA STATE PARKEstimate Type:PROG
Contractor:
KNIGHT ASPHALT, INC.Date Let:02.07.2002
PO BOX 180Date Awarded:02.14.2002
Date Contract Executed:02.21.2002
Date Notice to Proceed:02.21.2002
CHAPMAN NE 68827Date Work Began:04.08.2002
Phone:Date Physical Work Completed:
(308)986-2254Date Accepted:
Escrow Agent:
Surety Co:
UNIVERSAL SURETY COMPANY
Counties
KNOX
Project Number PCT Fed State Project Number Description
31352 000  0.000 SRR-54(9)  GR CULV GDRL BIT
31352A 000  0.000 SRR-54(11)  GR CULV
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$105,043.90$23,235.36$81,808.54
$1,212,890.38Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$105,043.90$23,235.36$81,808.54
$1,212,890.38Retainage$-1,050.44$-232.35$-818.09
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
8.66%Net Earnings$103,993.46$23,003.01$80,990.45
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$648.76$3.66$645.10
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments$648.76$3.66$645.10
Payment$104,642.22$23,006.67$81,635.55
Project ManagerDiv. Head/Dist. Eng.
Mead, Terry05.19.2002Hausman, Larry05.21.2002
Constr. Estimate Eng.Materials Eng.
Bartos, Steve05.21.2002
Controller Div. Processed
Burling, Laurie05.22.2002
Detailed breakdown of stockpiled materials
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          L006.00 180.006.6501,197.00
COVER CROP SEEDING ha 6.6501,197.00
0.0000.00
0.0000.00

0002                          L020.00 1.508,062.00012,093.00
EROSION CONTROL m2 8,062.00012,093.00
0.0000.00
0.0000.00

0003                          L020.01 5.75840.0004,830.00
EROSION CONTROL, TYPE A m2 840.0004,830.00
0.0000.00
0.0000.00

0004                          L020.07 1.506,568.0009,852.00
EROSION CONTROL, TYPE B-1 m2 6,568.0009,852.00
0.0000.00
0.0000.00

0005                          L020.08 5.203,060.00015,912.00
EROSION CONTROL, TYPE AA m2 3,060.00015,912.00
0.0000.00
0.0000.00

0006                          L020.09 13.00414.0005,382.00
EROSION CONTROL, TYPE AAA m2 414.0005,382.00
0.0000.00
0.0000.00

0007                          L021.01 15.0066.000990.00
EROSION CHECKS, TYPE A BALE66.000990.00
0.0000.00
0.0000.00

0008                          L021.21 16.00276.0004,416.00
EROSION CHECKS, TYPE AA BALE276.0004,416.00
0.0000.00
0.0000.00

0009                          L021.22 16.006.00096.00
EROSION CHECKS, TYPE AAA BALE6.00096.00
0.0000.00
0.0000.00

0010                          L022.25 6.25847.0005,293.75
FABRIC SILT FENCE, TYPE COIR FIBER m 847.0005,293.75
1,046.0006,537.50
144.000900.00

0011                          L022.75 27.00296.8008,013.60
TEMPORARY SILT CHECK m 296.8008,013.60
0.0000.00
0.0000.00

0012                          0030.10 4,100.481.0004,100.48
MOBILIZATION LS 1.0004,100.48
1.0004,100.48
1.0004,100.48

0013                          1009.00 2,000.001.0002,000.00
GENERAL CLEARING AND GRUBBING LS 1.0002,000.00
FOR PROJECT SRR-54(9) 0.9001,800.00
0.0000.00

0015                          1010.00 1.5347,166.00072,163.98
EXCAVATION m3 47,166.00072,163.98
25,641.70039,231.80
25,498.00039,011.94

0016                          1010.10 1.572,853.0004,479.21
EXCAVATION, BORROW m3 2,853.0004,479.21
0.0000.00
0.0000.00

0017                          1011.00 1.602,501.0004,001.60
WATER kL 2,501.0004,001.60
0.0000.00
0.0000.00

0018                          1102.00 3.90592.0002,308.80
REMOVE ASPHALT SURFACE m2 592.0002,308.80
0.0000.00
-800.000-3,120.00

0019                          1109.00 8.20124.0001,016.80
REMOVE CURB m 124.0001,016.80
0.0000.00
0.0000.00

0020                          9110.01 60.0010.000600.00
RENTAL OF LOADER, FULLY OPERATED HOUR10.000600.00
0.0000.00
0.0000.00

0021                          9110.03 50.0010.000500.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR10.000500.00
0.0000.00
0.0000.00

0022                          9110.07 40.0010.000400.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR10.000400.00
0.0000.00
0.0000.00

GROUP 1 GRADINGContracted159,646.22
Current159,646.22
In place51,669.78
This Estimate40,892.42

GROUP 4 CULVERTS
0024                          P250.24 65.00120.4007,826.00
600 mm CULVERT PIPE, TYPE 3 OR 4 m 120.4007,826.00
0.0000.00
0.0000.00

0025                          0030.40 280.301.000280.30
MOBILIZATION LS 1.000280.30
0.0000.00
0.0000.00

0028                          4050.01 7.3622.000161.92
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 22.000161.92
0.0000.00
0.0000.00

0031                          4310.24 198.005.000990.00
600 mm FLARED-END SECTION EACH5.000990.00
0.0000.00
0.0000.00

GROUP 4 CULVERTSContracted9,258.22
Current9,258.22
In place0.00
This Estimate0.00

GROUP 7 GUARDRAIL
0036                          0030.70 760.001.000760.00
MOBILIZATION LS 1.000760.00
0.0000.00
0.0000.00

0037                          7015.00 18.05348.8006,295.84
CABLE GUARDRAIL m 348.8006,295.84
0.0000.00
0.0000.00

0038                          7023.00 1,309.004.0005,236.00
TERMINAL ANCHORAGE SECTIONS EACH4.0005,236.00
0.0000.00
0.0000.00

GROUP 7 GUARDRAILContracted12,291.84
Current12,291.84
In place0.00
This Estimate0.00

GROUP 9 BITUMINOUS
0039                          L001.02 1,099.003.0003,297.00
SEEDING, TYPE B ha 3.0003,297.00
0.0000.00
0.0000.00

0040                          L032.75 70.0014.000980.00
MULCH Mg 14.000980.00
0.0000.00
0.0000.00

0041                          P250.15 65.3613.500882.36
375 mm CULVERT PIPE, TYPE 3 OR 4 m 13.500882.36
0.0000.00
0.0000.00

0042                          P250.18 72.3612.000868.32
450 mm CULVERT PIPE, TYPE 3 OR 4 m 12.000868.32
0.0000.00
0.0000.00

0043                          P250.24 81.69163.90013,388.99
600 mm CULVERT PIPE, TYPE 3 OR 4 m 163.90013,388.99
0.0000.00
0.0000.00

0044                          0030.90 72,000.001.00072,000.00
MOBILIZATION LS 1.00072,000.00
0.0000.00
0.0000.00

0045                          4004.00 2.691,770.0004,761.30
CAST IRON GRATE kg 1,770.0004,761.30
0.0000.00
0.0000.00

0046                          4024.73 1,454.0010.00014,540.00
CONCRETE FLUME, TYPE IV EACH10.00014,540.00
0.0000.00
0.0000.00

0047                          4024.74 1,454.005.0007,270.00
CONCRETE FLUME, TYPE V EACH5.0007,270.00
0.0000.00
0.0000.00

0048                          4105.59 0.0043.1600.00
CLASS 47B-20 CONCRETE FOR INLET AND JUNCTION BOX m3 43.1600.00
0.0000.00
0.0000.00

0049                          4155.50 0.001,016.1000.00
REINFORCING STEEL FOR INLET AND JUNCTION BOX kg 1,016.1000.00
0.0000.00
0.0000.00

0050                          4310.18 175.001.000175.00
450 mm FLARED-END SECTION EACH1.000175.00
0.0000.00
0.0000.00

0051                          4310.24 196.009.0001,764.00
600 mm FLARED-END SECTION EACH9.0001,764.00
0.0000.00
0.0000.00

0052                          9005.24 27.0213,340.000360,446.80
ASPHALTIC CONCRETE, TYPE SPL Mg 13,340.000360,446.80
0.0000.00
0.0000.00

0053                          9009.00 3.501,180.0004,130.00
PLACEMENT OF ASPHALTIC CONCRETE FOR DRIVEWAYS ANDINTERSECTIONS m2 1,180.0004,130.00
0.0000.00
0.0000.00

0054                          9021.01 195.00720.360140,470.20
PERFORMANCE GRADED BINDER (64-22) Mg 720.360140,470.20
0.0000.00
0.0000.00

0055                          9030.00 7.003,979.00027,853.00
CONSTRUCTING ASPHALTIC CONCRETE CURB m 3,979.00027,853.00
0.0000.00
0.0000.00

0056                          9034.00 2.981,180.0003,516.40
PREPARATION OF INTERSECTIONS AND DRIVEWAYS m2 1,180.0003,516.40
0.0000.00
0.0000.00

0057                          9053.00 0.4516,240.0007,308.00
TACK COAT L 16,240.0007,308.00
0.0000.00
0.0000.00

0058                          9111.00 4.00623.0002,492.00
WATER kL 623.0002,492.00
0.0000.00
0.0000.00

0059                          9170.00 208.0062.63813,028.70
EARTH SHOULDER CONSTRUCTION StaM62.63813,028.70
0.0000.00
0.0000.00

0060                          9173.20 1.7531,959.00055,928.25
SUBGRADE PREPARATION m2 31,959.00055,928.25
0.0000.00
0.0000.00

GROUP 9 BITUMINOUSContracted735,100.33
Current735,100.33
In place0.00
This Estimate0.00

GROUP 10 GENERAL ITEMS
0061                          0001.10 0.502,112.0001,056.00
BARRICADE, TYPE III BDAY2,112.0001,056.00
91.00045.50
53.00026.50

0062                          0001.30 0.50528.000264.00
TYPE B HIGH INTENSITY WARNING LIGHT LDAY528.000264.00
40.00020.00
14.0007.00

0063                          0001.90 1.001,216.0001,216.00
SIGN DAY EACH1,216.0001,216.00
110.000110.00
54.00054.00

0064                          0003.10 200.0010.0002,000.00
FLAGGING DAY 10.0002,000.00
0.0000.00
0.0000.00

0065                          0010.04 1,500.000.7501,125.00
FIELD OFFICE EACH0.7501,125.00
0.7501,125.00
0.0000.00

0066                          0030.00 3,362.071.0003,362.07
MOBILIZATION LS 1.0003,362.07
1.0003,362.07
0.0000.00

GROUP 10 GENERAL ITEMSContracted9,023.07
Current9,023.07
In place4,662.57
This Estimate87.50

GROUP 1 GRADING
0012                          0030.10 3,899.521.0003,899.52
MOBILIZATION LS 1.0003,899.52
1.0003,899.52
1.0003,899.52

0014                          1009.01 6,000.001.0006,000.00
GENERAL CLEARING AND GRUBBING LS 1.0006,000.00
FOR PROJECT SRR-54(11) 1.0006,000.00
0.100600.00

0015                          1010.00 1.535,310.0008,124.30
EXCAVATION m3 5,310.0008,124.30
0.0000.00
0.0000.00

0016                          1010.10 1.5759,282.00093,072.74
EXCAVATION, BORROW m3 59,282.00093,072.74
0.0000.00
0.0000.00

0017                          1011.00 1.601,290.0002,064.00
WATER kL 1,290.0002,064.00
0.0000.00
0.0000.00

0018                          1102.00 3.902,683.00010,463.70
REMOVE ASPHALT SURFACE m2 2,683.00010,463.70
2,508.0009,781.20
2,308.0009,001.20

GROUP 1 GRADINGContracted123,624.26
Current123,624.26
In place19,680.72
This Estimate13,500.72

GROUP 4 CULVERTS
0023                          P120.36 642.2174.70047,973.09
900 mm CULVERT PIPE, TYPE 2 m 74.70047,973.09
0.0000.00
0.0000.00

0025                          0030.40 3,274.701.0003,274.70
MOBILIZATION LS 1.0003,274.70
1.0003,274.70
1.0003,274.70

0026                          1010.05 7.003,400.00023,800.00
SPECIAL EXCAVATION m3 3,400.00023,800.00
3,400.00023,800.00
3,230.00022,610.00

0027                          1043.61 3.211,338.0004,294.98
GEOTEXTILE FABRIC m2 1,338.0004,294.98
0.0000.00
0.0000.00

0028                          4050.01 7.367.00051.52
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 7.00051.52
0.0000.00
0.0000.00

0029                          4115.25 421.3672.40030,506.46
CLASS 47B-20 CONCRETE m3 72.40030,506.46
FOR RISER AND PIPE SUPPORT 0.0000.00
0.0000.00

0030                          4163.25 1.536,536.00010,000.08
REINFORCING STEEL kg 6,536.00010,000.08
FOR RISER AND PIPE SUPPORT 0.0000.00
0.0000.00

0032                          4764.54 13.12131.5001,725.28
100 mm PERFORATED P.V.C. PIPE UNDERDRAIN m 131.5001,725.28
110.0001,443.20
110.0001,443.20

0033                          4803.10 124.2526.8003,329.90
250 mm P.V.C. PIPE m 26.8003,329.90
0.0000.00
0.0000.00

0034                          6105.02 25.251,130.00028,532.50
ROCK RIPRAP, TYPE B Mg 1,130.00028,532.50
0.0000.00
0.0000.00

0035                          8091.00 15.00663.0009,945.00
GRANULAR BACKFILL m3 663.0009,945.00
0.0000.00
0.0000.00

GROUP 4 CULVERTSContracted163,433.51
Current163,433.51
In place28,517.90
This Estimate27,327.90

GROUP 10 GENERAL ITEMS
0065                          0010.04 1,500.000.250375.00
FIELD OFFICE EACH0.250375.00
0.250375.00
0.0000.00

0066                          0030.00 137.931.000137.93
MOBILIZATION LS 1.000137.93
1.000137.93
0.0000.00

GROUP 10 GENERAL ITEMSContracted512.93
Current512.93
In place512.93
This Estimate0.00

Totals for contractContracted1,212,890.38
Current1,212,890.38
In place105,043.90
This Estimate81,808.54