Nebraska Department of Roads | |
---|---|
Estimate Summary to Contractor | |
Vendor ID: | 2831 MUSSELMAN AND HALL CONTRACTORS, LLC |
Contract ID: | 3903A |
Estimate Number: | 0007 |
Pay Period End Date: | 06.18.2003 |
Contract Location: | ||
DISTRICT 3 - DISTRICTWIDE | Estimate Type: | FINL |
Contractor: | ||
MUSSELMAN AND HALL CONTRACTORS, LLC | Date Let: | 08.01.2002 |
4922 E BLUE BANKS | Date Awarded: | 08.05.2002 |
P O BOX 300858 | Date Contract Executed: | 08.16.2002 |
Date Notice to Proceed: | 08.16.2002 | |
KANSAS CITY MO 64130 | Date Work Began: | 01.27.2003 |
Phone: | Date Physical Work Completed: | |
(816)861-1234 | Date Accepted: | 04.14.2003 |
Escrow Agent: | ||
Surety Co: | ||
ST. PAUL FIRE & MARINE INSURANCE COMPANY |
Counties |
---|
CEDAR |
DIXON |
MADISON |
PIERCE |
Project Number |   | PCT |   | Fed State Project Number |   | Description | |
---|---|---|---|---|---|---|---|
39903A 000 |   | 0.000 |   | PM-D3(1015) |   | CONCRETE PAVEMENT |
Total to Date | Prev to Date | This Estimate | ||
Current Contract Amt | Total Earnings | $329,899.27 | $329,899.27 | $.00 |
$391,518.62 | Stockpiled Materials | $.00 | $.00 | $.00 |
Original Contract Amt | Gross Earnings | $329,899.27 | $329,899.27 | $.00 |
$343,158.34 | Retainage | $.00 | $-3,298.99 | $3,298.99 |
Escrow Amount | $.00 | $.00 | $.00 | |
Percent Complete | Securities Encumbered | $.00 | $.00 | $.00 |
84.26% | Net Earnings | $329,899.27 | $326,600.28 | $3,298.99 |
Liquidated Damages | $.00 | $.00 | $.00 | |
Incentives | $.00 | $.00 | $.00 | |
Disincentives | $.00 | $.00 | $.00 | |
Other Contract Adj | $.00 | $.00 | $.00 | |
Appl of Training Adj | $.00 | $.00 | $.00 | |
Training Rates Adj | $.00 | $.00 | $.00 | |
Fuel Adj | $.00 | $.00 | $.00 | |
Bituminous Adj | $.00 | $.00 | $.00 | |
Autopay Adj | $.00 | $.00 | $.00 | |
Gasoline Adj | $.00 | $.00 | $.00 | |
Other Adj | $.00 | $.00 | $.00 | |
Price Adj | $.00 | $.00 | $.00 | |
Substandard Item Adj | $.00 | $.00 | $.00 | |
Asphalt Adj | $.00 | $.00 | $.00 | |
Diesel Fuel Adj | $.00 | $.00 | $.00 | |
Petrol Adj | $.00 | $.00 | $.00 | |
Total for Adjustments | $.00 | $.00 | $.00 | |
Payment | $329,899.27 | $326,600.28 | $3,298.99 | |
Project Manager | Div. Head/Dist. Eng. | |||
Mueting, Curt | 08.07.2003 | Boyle, Pat | 08.08.2003 | |
Constr. Estimate Eng. | Materials Eng. | |||
Davis, Carl | 08.12.2003 | Hall, David | 08.12.2003 | |
Controller Div. Processed | ||||
Harring, Joyce | 08.29.2003 |
Detailed breakdown of stockpiled materials | ||||
---|---|---|---|---|
Total remaining for contract: | 0.00 |
1. Contracted | |||
---|---|---|---|
2. Current | |||
3. To date | |||
Item Nbr Item Code | Unit Price | 4. This Est | |
Item Description | Units | Qty | Amount |
GROUP 3 CONCRETE PAVEMENT | |||
0001 0001.10 | 1.00 | 356.000 | 356.00 |
BARRICADE, TYPE III | BDAY | 356.000 | 356.00 |
0.000 | 0.00 | ||
0.000 | 0.00 | ||
0002 0001.30 | 1.00 | 178.000 | 178.00 |
TYPE B HIGH INTENSITY WARNING LIGHT | LDAY | 178.000 | 178.00 |
0.000 | 0.00 | ||
0.000 | 0.00 | ||
0003 0001.75 | 1.00 | 270.000 | 270.00 |
TEMPORARY SIGN DAY | EACH | 270.000 | 270.00 |
521.000 | 521.00 | ||
0.000 | 0.00 | ||
0004 0001.90 | 1.00 | 1,424.000 | 1,424.00 |
SIGN DAY | EACH | 1,424.000 | 1,424.00 |
0.000 | 0.00 | ||
0.000 | 0.00 | ||
0005 0003.10 | 1.00 | 90.000 | 90.00 |
FLAGGING | DAY | 90.000 | 90.00 |
81.000 | 81.00 | ||
0.000 | 0.00 | ||
0006 0003.20 | 1.00 | 45.000 | 45.00 |
FURNISHING AND OPERATING PILOT VEHICLE | DAY | 45.000 | 45.00 |
32.500 | 32.50 | ||
0.000 | 0.00 | ||
0007 0030.30 | 7,250.00 | 1.000 | 7,250.00 |
MOBILIZATION | LS | 1.000 | 7,250.00 |
1.000 | 7,250.00 | ||
0.000 | 0.00 | ||
0008 3211.25 | 1.00 | 13,672.000 | 13,672.00 |
SEALING CRACKS | LF | 13,672.000 | 13,672.00 |
18,299.000 | 18,299.00 | ||
0.000 | 0.00 | ||
0009 3211.30 | 0.61 | 245,162.000 | 149,548.82 |
SEALING JOINTS | LF | 245,162.000 | 149,548.82 |
195,965.000 | 119,538.65 | ||
0.000 | 0.00 | ||
0010 9140.00 | 48.00 | 2,069.000 | 99,312.00 |
JOINT SEALING - ASPHALT TO CONCRETE | STA | 2,069.000 | 99,312.00 |
1,350.090 | 64,804.32 | ||
0.000 | 0.00 | ||
0011 9140.40 | 0.36 | 197,257.000 | 71,012.52 |
CRACK SEALING BITUMINOUS SURFACING | LF | 340,480.000 | 122,572.80 |
340,480.000 | 122,572.80 | ||
0.000 | 0.00 | ||
4001 0096.00 | -3,200.00 | 0.000 | 0.00 |
DEDUCTION | LS | 1.000 | -3,200.00 |
Sealant material used was not the material specified. | 1.000 | -3,200.00 | |
0.000 | 0.00 | ||
GROUP 3 CONCRETE PAVEMENT | Contracted | 343,158.34 | |
Current | 391,518.62 | ||
In place | 329,899.27 | ||
This Estimate | 0.00 | ||
Totals for contract | Contracted | 343,158.34 | |
Current | 391,518.62 | ||
In place | 329,899.27 | ||
This Estimate | 0.00 |