Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:0013 DIAMOND ENGINEERING COMPANY/THE
Contract ID:4415A
Estimate Number:0020
Pay Period End Date:04.29.2002
Contract Location:
GRAND ISLAND SOUTHEstimate Type:PROG
Contractor:
DIAMOND ENGINEERING COMPANY/THEDate Let:12.07.2000
1521 W ANNADate Awarded:01.02.2001
PO BOX 1327Date Contract Executed:02.06.2001
Date Notice to Proceed:02.06.2001
GRAND ISLAND NE 68802Date Work Began:04.02.2001
Phone:Date Physical Work Completed:
(308)382-8362Date Accepted:
Escrow Agent:
Surety Co:
TRAVELERS CASUALTY AND SURETY COMPANY OF AMERICA
Counties
HALL
Project Number PCT Fed State Project Number Description
41415A 000  0.000 STPE-STPAA-2235(2)  GRAD, CULV, BR, GDRL, BIT
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$1,370,306.93$1,369,306.93$1,000.00
$1,426,836.00Stockpiled Materials$.00$320.02$-320.02
Original Contract AmtGross Earnings$1,370,306.93$1,369,626.95$679.98
$1,402,914.24Retainage$-13,703.07$-13,693.07$-10.00
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
96.04%Net Earnings$1,356,603.86$1,355,933.88$669.98
Liquidated Damages-$13,728.00-$13,104.00-$624.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$-56.52$-56.52$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments-$13,784.52-$13,160.52-$624.00
Payment$1,342,819.34$1,342,773.36$45.98
Project ManagerDiv. Head/Dist. Eng.
Woodgate, Gerald04.29.2002Meyer, Keith04.29.2002
Constr. Estimate Eng.Materials Eng.
Bartos, Steve04.29.2002
Controller Div. Processed
Burling, Laurie04.30.2002
Detailed breakdown of stockpiled materials
Est Nbr:0001
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00416011.11 PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE
S.P. Initial Payment21,700.00G-00954
type 2 prestressed concrete beams 59'-9"
Total for estimate 0001:21,700.00
Est Nbr:0003
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00486131.50 EPOXY COATED REINFORCING STEEL
S.P. Initial Payment9,193.031651
epoxy coated rebar
S.P. Adjustment-655.121651
epoxy coated rebar
00726011.11 PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE
S.P. Initial Payment24,200.0095917317
Prestressed Concrete type 2 Beams
00796131.50 EPOXY COATED REINFORCING STEEL
S.P. Initial Payment2,621.811651
epoxy coated rebar
Total for estimate 0003:35,359.72
Est Nbr:0004
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00486131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-203.401651
epoxy coated rebar
Total for estimate 0004:-203.40
Est Nbr:0005
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00486131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-661.871651
epoxy coated rebar
Total for estimate 0005:-661.87
Est Nbr:0006
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00486131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-1,511.941651
epoxy coated rebar
Total for estimate 0006:-1,511.94
Est Nbr:0007
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00416011.11 PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE
S.P. Adjustment-21,700.00G-00954
type 2 prestressed concrete beams 59'-9"
00796131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-180.351651
epoxy coated rebar
Total for estimate 0007:-21,880.35
Est Nbr:0008
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00796131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-844.181651
epoxy coated rebar
Total for estimate 0008:-844.18
Est Nbr:0009
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00796131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-826.691651
epoxy coated rebar
Total for estimate 0009:-826.69
Est Nbr:0010
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00486131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-4,018.671651
epoxy coated rebar
00796131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-707.841651
epoxy coated rebar
Total for estimate 0010:-4,726.51
Est Nbr:0011
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00486131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-51.771651
epoxy coated rebar
00796131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-62.751651
epoxy coated rebar
Total for estimate 0011:-114.52
Est Nbr:0012
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00486131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-498.041651
epoxy coated rebar
00726011.11 PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE
S.P. Adjustment-24,200.0095917317
Prestressed Concrete type 2 Beams
Total for estimate 0012:-24,698.04
Est Nbr:0013
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00486131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-215.851651
epoxy coated rebar
Total for estimate 0013:-215.85
Est Nbr:0014
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00486131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-348.921651
epoxy coated rebar
Total for estimate 0014:-348.92
Est Nbr:0015
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00486131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-584.501651
epoxy coated rebar
Total for estimate 0015:-584.50
Est Nbr:0016
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00486131.50 EPOXY COATED REINFORCING STEEL
S.P. Adjustment-122.931651
epoxy coated rebar
Total for estimate 0016:-122.93
Est Nbr:0020
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00486131.50 EPOXY COATED REINFORCING STEEL
S.P. Closure-320.021651
epoxy coated rebar
Total for estimate 0020:-320.02
Total remaining for contract:-0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          L006.00 200.003.000600.00
COVER CROP SEEDING ha 3.000600.00
0.0000.00
0.0000.00

0002                          0030.10 2,500.001.0002,500.00
MOBILIZATION LS 1.0002,500.00
1.0002,500.00
0.0000.00

0003                          1000.00 150.0050.0007,500.00
LARGE TREE REMOVAL EACH50.0007,500.00
109.00016,350.00
0.0000.00

0004                          1011.00 2.001,304.0002,608.00
WATER kL 1,304.0002,608.00
0.0000.00
0.0000.00

0005                          1030.00 5.2712,417.00065,437.59
EARTHWORK MEASURED IN EMBANKMENT m3 12,417.00065,437.59
12,417.00065,437.60
0.0000.00

0006                          1101.00 4.50896.0004,032.00
REMOVE PAVEMENT m2 896.0004,032.00
981.5004,416.75
0.0000.00

0007                          1101.25 8.20139.0001,139.80
SAWING PAVEMENT m 139.0001,139.80
200.4001,643.28
0.0000.00

0008                          1300.24 60.0016.000960.00
600 mm DRIVEWAY CULVERT PIPE m 16.000960.00
16.000960.00
0.0000.00

0009                          7017.00 7.50222.9001,671.75
REMOVE GUARDRAIL m 222.9001,671.75
215.8001,618.50
0.0000.00

4001                          L022.25 10.000.0000.00
FABRIC SILT FENCE, TYPE COIR FIBER m 914.0009,140.00
837.0008,370.00
0.0000.00

GROUP 1 GRADINGContracted86,449.14
Current95,589.14
In place101,296.13
This Estimate0.00

GROUP 4 CULVERTS
0010                          0030.40 5,300.001.0005,300.00
MOBILIZATION LS 1.0005,300.00
1.0005,300.00
0.0000.00

0011                          1043.50 1.50114.000171.00
RIPRAP FILTER FABRIC m2 114.000171.00
114.000171.00
0.0000.00

0012                          4018.50 250.002.000500.00
TAPPING EXISTING PIPE EACH2.000500.00
0.0000.00
0.0000.00

0013                          4035.00 150.002.000300.00
REMOVE FLARED-END SECTION EACH2.000300.00
0.0000.00
0.0000.00

0014                          4040.00 200.001.000200.00
REMOVE HEADWALLS FROM CULVERTS EACH1.000200.00
1.000200.00
0.0000.00

0015                          4043.50 25.0051.2001,280.00
REMOVE SEWER PIPE m 51.2001,280.00
25.600640.00
0.0000.00

0016                          4050.01 10.50910.0009,555.00
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 910.0009,555.00
880.0009,240.00
0.0000.00

0017                          4054.60 443.0011.0004,873.00
TEMPORARY SHORING m 0.0000.00
AT STA. 140+91.304 0.0000.00
0.0000.00

0018                          4054.61 443.0016.5007,309.50
TEMPORARY SHORING m 0.0000.00
AT STA. 158+24.5 0.0000.00
0.0000.00

0019                          4300.36 110.0026.5002,915.00
900 mm CULVERT PIPE m 26.5002,915.00
26.5002,915.00
0.0000.00

0020                          4310.36 350.004.0001,400.00
900 mm FLARED-END SECTION EACH4.0001,400.00
4.0001,400.00
0.0000.00

0021                          4450.54 410.00156.00063,960.00
1350 mm REINFORCED CONCRETE PIPE m 156.00063,960.00
156.00063,960.00
0.0000.00

0022                          4460.54 1,175.006.0007,050.00
1350 mm CONCRETE FLARED-END SECTION EACH6.0007,050.00
6.0007,050.00
0.0000.00

0023                          6105.02 50.00152.0007,600.00
ROCK RIPRAP, TYPE B Mg 152.0007,600.00
141.0007,050.00
0.0000.00

4007                          4976.05 4,761.000.0000.00
ADDITIONAL WORK LS 1.0004,761.00
Eliminate the Phasing of Culvert Crossing construction 1.0004,761.00
0.0000.00

GROUP 4 CULVERTSContracted112,413.50
Current104,992.00
In place102,687.00
This Estimate0.00

GROUP 6 BRIDGE AT STA. 141+47.475
0024                          0030.60 31,000.001.00031,000.00
MOBILIZATION LS 1.00031,000.00
1.00031,000.00
0.0000.00

0025                          1010.01 5.00165.000825.00
EXCAVATION (ESTABLISHED QUANTITY) m3 165.000825.00
165.000825.00
0.0000.00

0026                          1043.50 3.50322.0001,127.00
RIPRAP FILTER FABRIC m2 322.0001,127.00
322.0001,127.00
0.0000.00

0027                          3050.15 291.00127.80037,189.80
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 m3 127.80037,189.80
127.80037,189.80
0.0000.00

0028                          3051.10 1.578,548.00013,420.36
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES kg 8,548.00013,420.36
8,548.00013,420.36
0.0000.00

0029                          6000.10 1,700.001.0001,700.00
ABUTMENT NO.1 EXCAVATION LS 1.0001,700.00
1.0001,700.00
0.0000.00

0030                          6000.11 1,700.001.0001,700.00
ABUTMENT NO.2 EXCAVATION LS 1.0001,700.00
1.0001,700.00
0.0000.00

0031                          6001.50 8,500.001.0008,500.00
BENT NO.1 EXCAVATION LS 1.0008,500.00
1.0008,500.00
0.0000.00

0032                          6001.51 8,500.001.0008,500.00
BENT NO.2 EXCAVATION LS 1.0008,500.00
1.0008,500.00
0.0000.00

0033                          6001.52 8,500.001.0008,500.00
BENT NO.3 EXCAVATION LS 1.0008,500.00
1.0008,500.00
0.0000.00

0034                          6005.78 915.002.0001,830.00
EXPANSION BEARING, TFE TYPE EACH2.0001,830.00
2.0001,830.00
0.0000.00

0035                          6007.01 28.00729.00020,412.00
CLASS I REPAIR m2 729.00020,412.00
729.00020,412.00
0.0000.00

0036                          6007.02 170.00146.00024,820.00
CLASS II REPAIR m2 146.00024,820.00
54.3009,231.00
0.0000.00

0037                          6007.03 300.005.0001,500.00
CLASS III REPAIR m2 5.0001,500.00
0.740222.00
0.0000.00

0038                          6008.40 40.00924.00036,960.00
PLACING, FINISHING, AND CURING CONCRETE OVERLAY-SF m2 924.00036,960.00
924.00036,960.00
0.0000.00

0039                          6010.22 427.00111.30047,525.10
CLASS 47B-20 CONCRETE FOR BRIDGE m3 111.30047,525.10
111.30047,525.11
0.0000.00

0040                          6010.26 518.0066.60034,498.80
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 66.60034,498.80
66.60034,498.80
0.0000.00

0041                          6011.11 40,000.001.00040,000.00
PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE LS 1.00040,000.00
AT STA. 141+47.475 1.00040,000.00
0.0000.00

0042                          6016.02 475.0062.30029,592.50
CONCRETE FOR OVERLAYS-SF m3 62.30029,592.50
70.73633,599.61
0.0000.00

0043                          6030.00 29,000.001.00029,000.00
PREPARATION OF BRIDGE EACH1.00029,000.00
AT STA. 141+47.475 1.00029,000.00
0.0000.00

0044                          6080.00 5.77376.0002,169.52
STRUCTURAL STEEL FOR SUBSTRUCTURE kg 376.0002,169.52
376.0002,169.52
0.0000.00

0045                          6095.00 1,000.002.0002,000.00
STEEL DIAPHRAGM EACH2.0002,000.00
2.0002,000.00
0.0000.00

0046                          6104.00 22.0055.0001,210.00
BROKEN CONCRETE RIPRAP Mg 55.0001,210.00
55.0001,210.00
0.0000.00

0047                          6105.02 41.00290.00011,890.00
ROCK RIPRAP, TYPE B Mg 290.00011,890.00
294.68012,081.88
0.0000.00

0048                          6131.50 1.5715,644.00024,561.08
EPOXY COATED REINFORCING STEEL kg 15,644.00024,561.08
15,644.00024,561.08
0.0000.00

0049                          6139.50 28.0041.0001,148.00
SUBSURFACE DRAINAGE MATTING m2 41.0001,148.00
41.0001,148.00
0.0000.00

0050                          6200.00 120.00364.00043,680.00
CONCRETE PILING m 364.00043,680.00
361.30043,356.00
0.0000.00

0051                          6310.00 152.00163.80024,897.60
STEEL SHEET PILING m2 163.80024,897.60
163.80024,897.60
0.0000.00

0052                          6510.60 7,600.001.0007,600.00
BRIDGE SHORING LS 1.0007,600.00
1.0007,600.00
0.0000.00

0053                          8091.00 12.00100.0001,200.00
GRANULAR BACKFILL m3 100.0001,200.00
29.300351.60
0.0000.00

4003                          L999.00 9,575.000.0000.00
COMPENSATION FOR ADDITIONAL COST LS 1.0009,575.00
Compensation for error in pile location. 1.0009,575.00
0.0000.00

4008                          6210.59 72.000.0000.00
PAY CUT-OFF m 2.700194.40
1997 metric specifications 2.700194.40
0.0000.00

GROUP 6 BRIDGE AT STA. 141+47.475Contracted498,956.76
Current508,726.16
In place494,885.76
This Estimate0.00

GROUP 6A BRIDGE AT STA. 157+63.465
0054                          0030.60 32,000.001.00032,000.00
MOBILIZATION LS 1.00032,000.00
1.00032,000.00
0.0000.00

0055                          1010.01 7.00100.000700.00
EXCAVATION (ESTABLISHED QUANTITY) m3 100.000700.00
100.000700.00
0.0000.00

0056                          1043.50 3.50269.000941.50
RIPRAP FILTER FABRIC m2 269.000941.50
269.000941.50
0.0000.00

0057                          3050.15 291.00127.80037,189.80
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 m3 127.80037,189.80
127.80037,189.80
0.0000.00

0058                          3051.10 1.578,548.00013,420.36
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES kg 8,548.00013,420.36
8,548.00013,420.36
0.0000.00

0059                          6000.10 850.001.000850.00
ABUTMENT NO.1 EXCAVATION LS 1.000850.00
1.000850.00
0.0000.00

0060                          6000.11 850.001.000850.00
ABUTMENT NO.2 EXCAVATION LS 1.000850.00
1.000850.00
0.0000.00

0061                          6001.50 8,500.001.0008,500.00
BENT NO.1 EXCAVATION LS 1.0008,500.00
1.0008,500.00
0.0000.00

0062                          6001.51 8,500.001.0008,500.00
BENT NO.2 EXCAVATION LS 1.0008,500.00
1.0008,500.00
0.0000.00

0063                          6001.52 8,500.001.0008,500.00
BENT NO.3 EXCAVATION LS 1.0008,500.00
1.0008,500.00
0.0000.00

0064                          6001.53 8,500.001.0008,500.00
BENT NO.4 EXCAVATION LS 1.0008,500.00
1.0008,500.00
0.0000.00

0065                          6005.78 910.002.0001,820.00
EXPANSION BEARING, TFE TYPE EACH2.0001,820.00
2.0001,820.00
0.0000.00

0066                          6007.01 28.00759.00021,252.00
CLASS I REPAIR m2 759.00021,252.00
759.00021,252.00
0.0000.00

0067                          6007.02 170.00152.00025,840.00
CLASS II REPAIR m2 152.00025,840.00
8.1001,377.00
0.0000.00

0068                          6007.03 300.005.0001,500.00
CLASS III REPAIR m2 5.0001,500.00
0.0000.00
0.0000.00

0069                          6008.40 40.00962.00038,480.00
PLACING, FINISHING, AND CURING CONCRETE OVERLAY-SF m2 962.00038,480.00
962.00038,480.00
0.0000.00

0070                          6010.22 427.00121.50051,880.50
CLASS 47B-20 CONCRETE FOR BRIDGE m3 121.50051,880.50
121.50051,880.52
0.0000.00

0071                          6010.26 518.0070.90036,726.20
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 70.90036,726.20
70.90036,726.20
0.0000.00

0072                          6011.11 43,500.001.00043,500.00
PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE LS 1.00043,500.00
AT STA. 157+63.465 1.00043,500.00
0.0000.00

0073                          6016.02 475.0064.80030,780.00
CONCRETE FOR OVERLAYS-SF m3 64.80030,780.00
65.37031,050.75
0.0000.00

0074                          6030.00 31,500.001.00031,500.00
PREPARATION OF BRIDGE EACH1.00031,500.00
AT STA. 157+63.465 1.00031,500.00
0.0000.00

0075                          6080.00 5.77522.0003,011.94
STRUCTURAL STEEL FOR SUBSTRUCTURE kg 522.0003,011.94
522.0003,011.94
0.0000.00

0076                          6095.00 1,000.002.0002,000.00
STEEL DIAPHRAGM EACH2.0002,000.00
0.0000.00
0.0000.00

0077                          6104.00 22.0055.0001,210.00
BROKEN CONCRETE RIPRAP Mg 55.0001,210.00
55.0001,210.00
0.0000.00

0078                          6105.02 41.00230.0009,430.00
ROCK RIPRAP, TYPE B Mg 230.0009,430.00
241.8309,915.03
0.0000.00

0079                          6131.50 1.5716,614.00026,083.98
EPOXY COATED REINFORCING STEEL kg 16,614.00026,083.98
16,614.00026,083.99
0.0000.00

0080                          6139.50 28.0041.0001,148.00
SUBSURFACE DRAINAGE MATTING m2 41.0001,148.00
41.0001,148.00
0.0000.00

0081                          6200.00 120.00459.60055,152.00
CONCRETE PILING m 459.60055,152.00
459.20055,104.00
0.0000.00

0082                          6310.00 152.00163.80024,897.60
STEEL SHEET PILING m2 163.80024,897.60
163.80024,897.60
0.0000.00

0083                          6510.60 7,600.001.0007,600.00
BRIDGE SHORING LS 1.0007,600.00
1.0007,600.00
0.0000.00

0084                          8091.00 12.00100.0001,200.00
GRANULAR BACKFILL m3 100.0001,200.00
24.340292.08
0.0000.00

4004                          6960.02 2,061.550.0000.00
ADDITIONAL WORK LS 1.0002,061.55
REMOVAL OF SPREAD FOOTING @ STA. 158+07 1.0002,061.55
0.0000.00

4009                          6210.59 72.000.0000.00
PAY CUT-OFF m 0.40028.80
1997 metric standard specifications 0.40028.80
0.0000.00

4010                          9110.10 117.350.0000.00
RENTAL OF EXCAVATOR, FULLY OPERATED HOUR20.0002,347.00
20.0002,347.00
0.0000.00

4011                          9110.01 77.350.0000.00
RENTAL OF LOADER, FULLY OPERATED HOUR5.000386.75
5.000386.75
0.0000.00

4012                          W357.43 352.000.0000.00
250 mm - 45 DEGREE BEND EACH1.000352.00
1.000352.00
0.0000.00

4013                          6960.02 981.550.0000.00
ADDITIONAL WORK LS 1.000981.55
1.000981.55
0.0000.00

4014                          6960.02 1,200.000.0000.00
ADDITIONAL WORK LS 1.0001,200.00
1.0001,200.00
0.0000.00

GROUP 6A BRIDGE AT STA. 157+63.465Contracted534,963.88
Current542,321.53
In place514,158.42
This Estimate0.00

GROUP 7 GUARDRAIL
0085                          0030.70 500.001.000500.00
MOBILIZATION LS 1.000500.00
1.000500.00
0.0000.00

0086                          7011.20 42.86213.3609,144.61
W-BEAM GUARDRAIL m 213.3609,144.61
213.3609,144.60
0.0000.00

0087                          7020.00 1,106.258.0008,850.00
BRIDGE APPROACH SECTIONS EACH8.0008,850.00
8.0008,850.00
0.0000.00

0088                          7021.70 1,639.008.00013,112.00
GUARDRAIL END TREATMENT, SRT-350 EACH8.00013,112.00
8.00013,112.00
0.0000.00

GROUP 7 GUARDRAILContracted31,606.61
Current31,606.61
In place31,606.60
This Estimate0.00

GROUP 9 BITUMINOUS
0089                          0002.30 3.00705.0002,115.00
PAVEMENT MARKING REMOVAL m 705.0002,115.00
705.0002,115.00
0.0000.00

0090                          0002.38 4.001,500.0006,000.00
TEMPORARY PAVEMENT MARKING, TYPE I m 1,500.0006,000.00
1,500.0006,000.00
0.0000.00

0091                          0003.51 29.00470.00013,630.00
INSTALL CONCRETE PROTECTION BARRIER m 470.00013,630.00
329.0009,541.00
0.0000.00

0092                          0003.70 750.008.0006,000.00
TEMPORARY RUMBLE STRIP EACH8.0006,000.00
8.0006,000.00
0.0000.00

0093                          0003.75 9,900.002.00019,800.00
TEMPORARY TRAFFIC SIGNAL EACH2.00019,800.00
2.00019,800.00
0.0000.00

0094                          0030.90 1,000.001.0001,000.00
MOBILIZATION LS 1.0001,000.00
1.0001,000.00
1.0001,000.00

0095                          2001.00 10.00319.0003,190.00
GRAVEL SURFACE COURSE m3 319.0003,190.00
312.3093,123.09
0.0000.00

0096                          2009.10 250.006.1471,536.75
GRAVEL EMBEDMENT StaM6.1471,536.75
6.1471,536.75
0.0000.00

0097                          3031.08 45.00338.00015,210.00
205 mm CONCRETE BASE COURSE m2 0.0000.00
0.0000.00
0.0000.00

0098                          8111.20 2.50690.0001,725.00
SHOULDER SUBGRADE PREPARATION m2 690.0001,725.00
690.0001,725.00
0.0000.00

0099                          9005.25 66.10430.00028,423.00
ASPHALTIC CONCRETE, TYPE SP1(12.5) Mg 0.0000.00
0.0000.00
0.0000.00

0100                          9021.01 210.0023.2204,876.20
PERFORMANCE GRADED BINDER (64-22) Mg 0.0000.00
0.0000.00
0.0000.00

0101                          9053.00 0.35620.000217.00
TACK COAT L 0.0000.00
0.0000.00
0.0000.00

0102                          9111.00 2.0014.00028.00
WATER kL 14.00028.00
0.0000.00
0.0000.00

0103                          9173.20 2.50338.000845.00
SUBGRADE PREPARATION m2 338.000845.00
338.000845.00
0.0000.00

0104                          9188.50 42.00198.0008,316.00
SURFACING UNDER GUARDRAIL m2 198.0008,316.00
198.0008,316.00
0.0000.00

4000                          0003.46 8,400.000.0000.00
MOVING CONCRETE PROTECTION BARRIER LS 1.0008,400.00
Transport Concrete Protection Barrier 0.5004,200.00
0.0000.00

4002                          3075.10 37.210.0000.00
155 mm CONCRETE PAVEMENT, CLASS 47B-20 m2 177.1686,592.42
177.1686,592.42
0.0000.00

4005                          3075.50 45.000.0000.00
255 mm CONCRETE PAVEMENT, CLASS 47B-20 m2 750.00033,750.00
Substitute 155mm Pavement & 205mm Conc. Base Course w/255mm 780.55035,124.76
0.0000.00

4006                          3091.36 46.000.0000.00
155 mm CONCRETE PAVEMENT CLASS 47B-HE-25 m2 110.0005,060.00
110.0005,060.00
0.0000.00

GROUP 9 BITUMINOUSContracted112,911.95
Current117,988.17
In place110,979.02
This Estimate1,000.00

GROUP 10 GENERAL ITEMS
0105                          0001.08 0.504,740.0002,370.00
BARRICADE, TYPE II BDAY4,740.0002,370.00
1,610.000805.00
0.0000.00

0106                          0001.10 2.001,896.0003,792.00
BARRICADE, TYPE III BDAY1,896.0003,792.00
1,044.0002,088.00
0.0000.00

0107                          0001.30 2.50474.0001,185.00
TYPE B HIGH INTENSITY WARNING LIGHT LDAY474.0001,185.00
515.0001,287.50
0.0000.00

0108                          0001.90 0.6516,116.00010,475.40
SIGN DAY EACH16,116.00010,475.40
7,190.0004,673.50
0.0000.00

0109                          0010.04 1,950.001.0001,950.00
FIELD OFFICE EACH1.0001,950.00
0.0000.00
0.0000.00

0110                          0030.00 5,840.001.0005,840.00
MOBILIZATION LS 1.0005,840.00
1.0005,840.00
0.0000.00

GROUP 10 GENERAL ITEMSContracted25,612.40
Current25,612.40
In place14,694.00
This Estimate0.00

Totals for contractContracted1,402,914.24
Current1,426,836.01
In place1,370,306.93
This Estimate1,000.00