Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:1242 GARCIA-CHICOINE ENTERPRISES, INC.
Contract ID:4970
Estimate Number:0002
Pay Period End Date:06.08.2002
Contract Location:
DISTRICT 4 - DISTRICTWIDEEstimate Type:PROG
Contractor:
GARCIA-CHICOINE ENTERPRISES, INC.Date Let:10.25.2001
PO BOX 81097Date Awarded:11.09.2001
Date Contract Executed:11.21.2001
Date Notice to Proceed:11.21.2001
LINCOLN NE 68501-1097Date Work Began:05.20.2002
Phone:Date Physical Work Completed:
(402)434-5444Date Accepted:
Escrow Agent:
Surety Co:
INLAND INSURANCE COMPANY
Counties
ADAMS
Project Number PCT Fed State Project Number Description
41970 000  0.000 STPP-STWD(25)  GUARDRAIL
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$30,915.17$27,098.50$3,816.67
$31,527.50Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$30,915.17$27,098.50$3,816.67
$31,527.50Retainage$-309.15$-270.99$-38.16
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
98.06%Net Earnings$30,606.02$26,827.51$3,778.51
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$.00$.00$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments$.00$.00$.00
Payment$30,606.02$26,827.51$3,778.51
Project ManagerDiv. Head/Dist. Eng.
Weber, Kirk06.12.2002Meyer, Keith06.12.2002
Constr. Estimate Eng.Materials Eng.
Bartos, Steve06.12.2002
Controller Div. Processed
Burling, Laurie06.13.2002
Detailed breakdown of stockpiled materials
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 7 GUARDRAIL
0001                          L020.00 3.00912.0002,736.00
EROSION CONTROL SY 912.0002,736.00
1,148.8903,446.67
1,148.8903,446.67

0002                          0001.08 0.50260.000130.00
BARRICADE, TYPE II BDAY260.000130.00
112.00056.00
20.00010.00

0003                          0001.10 3.5052.000182.00
BARRICADE, TYPE III BDAY52.000182.00
52.000182.00
20.00070.00

0004                          0001.30 2.5052.000130.00
TYPE B HIGH INTENSITY WARNING LIGHT LDAY52.000130.00
44.000110.00
20.00050.00

0005                          0001.90 1.50338.000507.00
SIGN DAY EACH338.000507.00
352.000528.00
160.000240.00

0006                          0003.10 250.005.0001,250.00
FLAGGING DAY 5.0001,250.00
0.0000.00
0.0000.00

0007                          0030.70 3,800.001.0003,800.00
MOBILIZATION LS 1.0003,800.00
1.0003,800.00
0.0000.00

0008                          1009.00 2,000.001.0002,000.00
GENERAL CLEARING AND GRUBBING LS 1.0002,000.00
1.0002,000.00
0.0000.00

0009                          1033.00 3,500.003.42011,970.00
ROADWAY GRADING STA 3.42011,970.00
3.42011,970.00
0.0000.00

0010                          7017.00 3.40412.5001,402.50
REMOVE GUARDRAIL LF 412.5001,402.50
412.5001,402.50
0.0000.00

0011                          7024.27 1,855.004.0007,420.00
GUARDRAIL END TREATMENT, TYPE II EACH4.0007,420.00
4.0007,420.00
0.0000.00

GROUP 7 GUARDRAILContracted31,527.50
Current31,527.50
In place30,915.17
This Estimate3,816.67

Totals for contractContracted31,527.50
Current31,527.50
In place30,915.17
This Estimate3,816.67