Nebraska Department of Roads | |
---|---|
Estimate Summary to Contractor | |
Vendor ID: | 2853 SIMON CONTRACTORS AND SUBSIDIARIES |
Contract ID: | 6082Y |
Estimate Number: | 0002 |
Pay Period End Date: | 05.18.2002 |
Contract Location: | ||
ARTHUR SOUTHEAST | Estimate Type: | PROG |
Contractor: | ||
SIMON CONTRACTORS AND SUBSIDIARIES | Date Let: | 07.12.2001 |
4819 S INDUSTRIAL SERVICE RD | Date Awarded: | 08.06.2001 |
PO BOX 347 | Date Contract Executed: | 09.05.2001 |
Date Notice to Proceed: | 09.05.2001 | |
CHEYENNE WY 82003 | Date Work Began: | |
Phone: | Date Physical Work Completed: | |
(307)632-7900 | Date Accepted: | |
Escrow Agent: | ||
Surety Co: | ||
LIBERTY MUTUAL INSURANCE COMPANY |
Counties |
---|
ARTHUR |
Project Number |   | PCT |   | Fed State Project Number |   | Description | |
---|---|---|---|---|---|---|---|
61082 000 |   | 0.000 |   | EACSTPE-1318(1) |   | BITUMINOUS |
Total to Date | Prev to Date | This Estimate | ||
Current Contract Amt | Total Earnings | $39,478.71 | $678.01 | $38,800.70 |
$270,662.68 | Stockpiled Materials | $.00 | $.00 | $.00 |
Original Contract Amt | Gross Earnings | $39,478.71 | $678.01 | $38,800.70 |
$270,662.68 | Retainage | $-394.79 | $-6.78 | $-388.01 |
Escrow Amount | $.00 | $.00 | $.00 | |
Percent Complete | Securities Encumbered | $.00 | $.00 | $.00 |
14.59% | Net Earnings | $39,083.92 | $671.23 | $38,412.69 |
Liquidated Damages | $.00 | $.00 | $.00 | |
Incentives | $.00 | $.00 | $.00 | |
Disincentives | $.00 | $.00 | $.00 | |
Other Contract Adj | $.00 | $.00 | $.00 | |
Appl of Training Adj | $.00 | $.00 | $.00 | |
Training Rates Adj | $.00 | $.00 | $.00 | |
Fuel Adj | $.00 | $.00 | $.00 | |
Bituminous Adj | $.00 | $.00 | $.00 | |
Autopay Adj | $.00 | $.00 | $.00 | |
Gasoline Adj | $.00 | $.00 | $.00 | |
Other Adj | $.00 | $.00 | $.00 | |
Price Adj | $.00 | $.00 | $.00 | |
Substandard Item Adj | $.00 | $.00 | $.00 | |
Asphalt Adj | $.00 | $.00 | $.00 | |
Diesel Fuel Adj | $.00 | $.00 | $.00 | |
Petrol Adj | $.00 | $.00 | $.00 | |
Total for Adjustments | $.00 | $.00 | $.00 | |
Payment | $39,083.92 | $671.23 | $38,412.69 | |
Project Manager | Div. Head/Dist. Eng. | |||
Shaner, Kitty | 05.20.2002 | O'Donnell, Les | 05.20.2002 | |
Constr. Estimate Eng. | Materials Eng. | |||
Bartos, Steve | 05.20.2002 | |||
Controller Div. Processed | ||||
Burling, Laurie | 05.21.2002 |
Detailed breakdown of stockpiled materials | ||||
---|---|---|---|---|
Total remaining for contract: | 0.00 |
1. Contracted | |||
---|---|---|---|
2. Current | |||
3. To date | |||
Item Nbr Item Code | Unit Price | 4. This Est | |
Item Description | Units | Qty | Amount |
GROUP 9 BITUMINOUS | |||
0001 0001.10 | 2.79 | 40.000 | 111.60 |
BARRICADE, TYPE III | BDAY | 40.000 | 111.60 |
20.000 | 55.80 | ||
20.000 | 55.80 | ||
0002 0001.30 | 4.24 | 40.000 | 169.60 |
TYPE B HIGH INTENSITY WARNING LIGHT | LDAY | 40.000 | 169.60 |
12.000 | 50.88 | ||
12.000 | 50.88 | ||
0003 0001.90 | 0.79 | 280.000 | 221.20 |
SIGN DAY | EACH | 280.000 | 221.20 |
44.000 | 34.76 | ||
44.000 | 34.76 | ||
0004 0003.10 | 220.37 | 20.000 | 4,407.40 |
FLAGGING | DAY | 20.000 | 4,407.40 |
4.000 | 881.48 | ||
4.000 | 881.48 | ||
0005 0030.90 | 19,941.60 | 1.000 | 19,941.60 |
MOBILIZATION | LS | 1.000 | 19,941.60 |
0.834 | 16,631.29 | ||
0.800 | 15,953.28 | ||
0006 2020.00 | 6.42 | 136.000 | 873.12 |
SPECIAL SURFACE COURSE FOR MAILBOX TURNOUTS | SY | 136.000 | 873.12 |
0.000 | 0.00 | ||
0.000 | 0.00 | ||
0007 2021.00 | 79.97 | 4.000 | 319.88 |
MAILBOX POST | EACH | 4.000 | 319.88 |
0.000 | 0.00 | ||
0.000 | 0.00 | ||
0008 8008.00 | 37.75 | 510.000 | 19,252.50 |
ARMOR COAT AGGREGATE | CY | 510.000 | 19,252.50 |
0.000 | 0.00 | ||
0.000 | 0.00 | ||
0009 9004.89 | 149.64 | 462.490 | 69,207.00 |
COLD IN-PLACE RECYCLING | STA | 462.490 | 69,207.00 |
52.250 | 7,818.69 | ||
52.250 | 7,818.69 | ||
0010 9005.21 | 7.49 | 200.000 | 1,498.00 |
PATCHING BITUMINOUS SAND | SY | 200.000 | 1,498.00 |
0.000 | 0.00 | ||
0.000 | 0.00 | ||
0011 9052.00 | 0.77 | 13,880.000 | 10,687.60 |
ARMOR COAT EMULSIFIED ASPHALT | GAL | 13,880.000 | 10,687.60 |
0.000 | 0.00 | ||
0.000 | 0.00 | ||
0012 9053.90 | 0.85 | 166,500.000 | 141,525.00 |
EMULSIFIED ASPHALT FOR COLD IN-PLACE RECYCLING | GAL | 166,500.000 | 141,525.00 |
16,362.000 | 13,907.70 | ||
16,362.000 | 13,907.70 | ||
0013 9111.25 | 36.54 | 67.000 | 2,448.18 |
WATER FOR COLD IN-PLACE RECYCLING, APPLIED | MGAL | 67.000 | 2,448.18 |
2.685 | 98.11 | ||
2.685 | 98.11 | ||
GROUP 9 BITUMINOUS | Contracted | 270,662.68 | |
Current | 270,662.68 | ||
In place | 39,478.71 | ||
This Estimate | 38,800.70 | ||
Totals for contract | Contracted | 270,662.68 | |
Current | 270,662.68 | ||
In place | 39,478.71 | ||
This Estimate | 38,800.70 |