| | | 1. Contracted
|
---|
| | | 2. Current
|
---|
| | | 3. To date
|
---|
Item Nbr Item Code | Unit Price | | 4. This Est
|
---|
Item Description | Units | Qty | Amount
|
---|
GROUP 3 CONCRETE PAVEMENT | | |
|
0001 0001.08 | 0.50 | 32,000.000 | 16,000.00
|
BARRICADE, TYPE II | BDAY | 32,000.000 | 16,000.00
|
| | 29,380.000 | 14,690.00
|
| | 4,466.000 | 2,233.00
|
| | |
|
0002 0001.10 | 1.25 | 1,112.000 | 1,390.00
|
BARRICADE, TYPE III | BDAY | 1,112.000 | 1,390.00
|
| | 926.000 | 1,157.50
|
| | 155.000 | 193.75
|
| | |
|
0003 0001.75 | 4.00 | 960.000 | 3,840.00
|
TEMPORARY SIGN DAY | EACH | 960.000 | 3,840.00
|
| | 2,503.000 | 10,012.00
|
| | 351.000 | 1,404.00
|
| | |
|
0004 0001.90 | 0.50 | 1,946.000 | 973.00
|
SIGN DAY | EACH | 1,946.000 | 973.00
|
| | 3,593.000 | 1,796.50
|
| | 630.000 | 315.00
|
| | |
|
0005 0002.44 | 0.10 | 95,292.000 | 9,529.20
|
TEMPORARY PAVEMENT MARKING, TYPE PAINT | LF | 95,292.000 | 9,529.20
|
| | 91,061.276 | 9,106.14
|
| | 6,217.653 | 621.77
|
| | |
|
0006 0002.97 | 25.00 | 160.000 | 4,000.00
|
FLASHING ARROW PANEL | DAY | 160.000 | 4,000.00
|
| | 197.000 | 4,925.00
|
| | 27.000 | 675.00
|
| | |
|
0007 0003.10 | 265.00 | 160.000 | 42,400.00
|
FLAGGING | DAY | 160.000 | 42,400.00
|
| | 8.000 | 2,120.00
|
| | 0.000 | 0.00
|
| | |
|
0008 0005.10 | 50.00 | 139.000 | 6,950.00
|
TRAFFIC CONTROL MANAGEMENT | DAY | 139.000 | 6,950.00
|
| | 64.000 | 3,200.00
|
| | 10.000 | 500.00
|
| | |
|
0009 0030.30 | 58,000.00 | 1.000 | 58,000.00
|
MOBILIZATION | LS | 1.000 | 58,000.00
|
| | 1.000 | 58,000.00
|
| | 0.000 | 0.00
|
| | |
|
0010 3008.15 | 22.00 | 27,054.000 | 595,188.00
|
DOWEL BAR RETROFIT | EACH | 27,054.000 | 595,188.00
|
| | 26,673.000 | 586,806.00
|
| | 0.000 | 0.00
|
| | |
|
0011 3008.20 | 10.00 | 11,915.000 | 119,150.00
|
CROSS STITCHING | EACH | 11,915.000 | 119,150.00
|
| | 12,765.000 | 127,650.00
|
| | 1,034.000 | 10,340.00
|
| | |
|
0012 3040.11 | 120.00 | 121.800 | 14,616.00
|
CONCRETE PAVEMENT REPAIR, TYPE A, FULL DEPTH | SY | 121.800 | 14,616.00
|
| | 102.618 | 12,314.16
|
| | 0.157 | 18.84
|
| | |
|
0013 3040.12 | 105.00 | 346.400 | 36,372.00
|
CONCRETE PAVEMENT REPAIR, TYPE B, FULL DEPTH | SY | 346.400 | 36,372.00
|
| | 470.884 | 49,442.83
|
| | 0.000 | 0.00
|
| | |
|
0014 3040.13 | 85.00 | 839.500 | 71,357.50
|
CONCRETE PAVEMENT REPAIR, TYPE C, FULL DEPTH | SY | 839.500 | 71,357.50
|
| | 961.743 | 81,748.16
|
| | 0.000 | 0.00
|
| | |
|
0015 3040.16 | 210.00 | 38.200 | 8,022.00
|
CONCRETE PAVEMENT REPAIR, TYPE B, PARTIAL DEPTH | SY | 38.200 | 8,022.00
|
| | 94.490 | 19,842.90
|
| | 0.000 | 0.00
|
| | |
|
0016 3040.18 | 220.00 | 602.500 | 132,550.00
|
CONCRETE PAVEMENT REPAIR, TYPE A, PARTIAL DEPTH | SY | 602.500 | 132,550.00
|
| | 1,130.360 | 248,679.20
|
| | 0.000 | 0.00
|
| | |
|
0017 3210.10 | 2.15 | 115,550.000 | 248,432.50
|
DIAMOND GRINDING AND TEXTURING CONCRETE PAVEMENT | SY | 115,550.000 | 248,432.50
|
| | 119,217.609 | 256,317.86
|
| | 0.000 | 0.00
|
| | |
|
0018 3211.25 | 2.00 | 1,687.000 | 3,374.00
|
SEALING CRACKS | LF | 1,687.000 | 3,374.00
|
| | 497.000 | 994.00
|
| | 497.000 | 994.00
|
| | |
|
0019 3211.30 | 0.58 | 327,828.000 | 190,140.24
|
SEALING JOINTS | LF | 327,828.000 | 190,140.24
|
| | 212,288.110 | 123,127.10
|
| | 182,710.610 | 105,972.15
|
| | |
|
0020 3221.05 | 145.00 | 156.600 | 22,707.00
|
CONCRETE PAVEMENT, CLASS PR-3625 | SY | 156.600 | 22,707.00
|
JOINT REPAIR | | 145.244 | 21,060.38
|
| | 0.000 | 0.00
|
| | |
|
0021 3300.50 | 500.00 | 1.000 | 500.00
|
PORTLAND CEMENT CONCRETE SMOOTHNESS TESTING | LS | 1.000 | 500.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0022 7502.14 | 1.80 | 92,828.000 | 167,090.40
|
4" WHITE PREFORMED PAVEMENT MARKING, TYPE 4, GROOVED | LF | 92,828.000 | 167,090.40
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0023 7503.14 | 1.85 | 74,262.000 | 137,384.70
|
4" YELLOW PREFORMED PAVEMENT MARKING, TYPE 4, GROOVED | LF | 74,262.000 | 137,384.70
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0024 0005.50 | -500.00 | 0.000 | 0.00
|
TRAFFIC CONTROL MANAGEMENT ASSESSMENT | EACH | 5.000 | -2,500.00
|
Penalty assessment for traffic control deficiency. | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
GROUP 3 CONCRETE PAVEMENT | | Contracted | 1,889,966.54
|
| | Current | 1,887,466.54
|
| | In place | 1,632,989.73
|
| | This Estimate | 123,267.51
|
| | |
|
Totals for contract | | Contracted | 1,889,966.54
|
---|
| | Current | 1,887,466.54
|
---|
| | In place | 1,632,989.73
|
---|
| | This Estimate | 123,267.51
|
---|