| | Detailed breakdown of stockpiled materials | |
|
---|
Est Nbr: | 0001 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0012 | 9000.75 | ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE | |
|
| | S.P. Initial Payment | 676.00 | 10304
|
| | Crushed Granite 3/4" | |
|
| | S.P. Initial Payment | 424.50 | 10304
|
| | 2A Gravel | |
|
| | S.P. Initial Payment | 346.00 | 10304
|
| | Sluice Sand | |
|
0013 | 9005.00 | ASPHALTIC CONCRETE FOR PATCHING, TYPE | |
|
| | S.P. Initial Payment | 814.00 | 10304
|
| | Crushed Granite 3/4" | |
|
| | S.P. Initial Payment | 872.00 | 10304
|
| | Sharp Crushed Gravel | |
|
| | S.P. Initial Payment | 368.00 | 10304
|
| | Crushed River Rock | |
|
| | S.P. Initial Payment | 797.75 | 10304
|
| | Crushed Rock Fines | |
|
| | S.P. Initial Payment | 142.50 | 10304
|
| | Airport Millings | |
|
0014 | 9005.23 | ASPHALTIC CONCRETE, TYPE SPS | |
|
| | S.P. Initial Payment | 10,369.84 | 10304
|
| | Crushed Granite 3/4" | |
|
| | S.P. Initial Payment | 6,511.83 | 10304
|
| | 2A Gravel | |
|
| | S.P. Initial Payment | 5,307.64 | 10304
|
| | Sluice Sand | |
|
0015 | 9005.45 | ASPHALTIC CONCRETE, TYPE SP4(0.5) | |
|
| | S.P. Initial Payment | 55,612.48 | 10304
|
| | Crushed Granite 3/4" | |
|
| | S.P. Initial Payment | 59,575.04 | 10304
|
| | Sharp Crushed Gravel | |
|
| | S.P. Initial Payment | 25,141.76 | 10304
|
| | Crushed River Rock | |
|
| | S.P. Initial Payment | 54,502.28 | 10304
|
| | Crushed Rock Fines | |
|
| | S.P. Initial Payment | 9,735.60 | 10304
|
| | Airport Millings | |
|
0013 | 9005.00 | ASPHALTIC CONCRETE FOR PATCHING, TYPE | |
|
| | S.P. Initial Payment | 325.60 | 10304
|
| | Crushed Granite 3/4" | |
|
| | S.P. Initial Payment | 348.80 | 10304
|
| | Sharp Crushed Gravel | |
|
| | S.P. Initial Payment | 147.20 | 10304
|
| | Crushed River Rock | |
|
| | S.P. Initial Payment | 319.10 | 10304
|
| | Crushed Rock Fines | |
|
| | S.P. Initial Payment | 57.00 | 10304
|
| | Airport Millings | |
|
0014 | 9005.23 | ASPHALTIC CONCRETE, TYPE SPS | |
|
| | S.P. Initial Payment | 1,257.36 | 10304
|
| | Crushed Granite 3/4" | |
|
| | S.P. Initial Payment | 789.57 | 10304
|
| | 2A Gravel | |
|
| | S.P. Initial Payment | 643.56 | 10304
|
| | Sluice Sand | |
|
0015 | 9005.45 | ASPHALTIC CONCRETE, TYPE SP4(0.5) | |
|
| | S.P. Initial Payment | 6,707.36 | 10304
|
| | Crushed Granite 3/4" | |
|
| | S.P. Initial Payment | 7,185.28 | 10304
|
| | Sharp Crushed Gravel | |
|
| | S.P. Initial Payment | 3,032.32 | 10304
|
| | Crushed River Rock | |
|
| | S.P. Initial Payment | 6,573.46 | 10304
|
| | Crushed Rock Fines | |
|
| | S.P. Initial Payment | 1,174.20 | 10304
|
| | Airport Millings | |
|
| | Total for estimate 0001: | 259,758.03 |
|
| | Total remaining for contract: | 259,758.03 |
|
---|
| | | 1. Contracted
|
---|
| | | 2. Current
|
---|
| | | 3. To date
|
---|
Item Nbr Item Code | Unit Price | | 4. This Est
|
---|
Item Description | Units | Qty | Amount
|
---|
GROUP 9 BITUMINOUS | | |
|
0001 0001.10 | 4.00 | 228.000 | 912.00
|
BARRICADE, TYPE III | BDAY | 228.000 | 912.00
|
| | 664.000 | 2,656.00
|
| | 196.000 | 784.00
|
| | |
|
0002 0001.30 | 4.00 | 114.000 | 456.00
|
TYPE B HIGH INTENSITY WARNING LIGHT | LDAY | 114.000 | 456.00
|
| | 96.000 | 384.00
|
| | 28.000 | 112.00
|
| | |
|
0003 0001.75 | 7.00 | 132.000 | 924.00
|
TEMPORARY SIGN DAY | EACH | 132.000 | 924.00
|
| | 225.000 | 1,575.00
|
| | 85.000 | 595.00
|
| | |
|
0004 0001.90 | 0.80 | 4,902.000 | 3,921.60
|
SIGN DAY | EACH | 4,902.000 | 3,921.60
|
| | 2,172.000 | 1,737.60
|
| | 880.000 | 704.00
|
| | |
|
0005 0002.55 | 6.25 | 1,178.000 | 7,362.50
|
OVERLAY BROKEN LINES | STA | 1,178.000 | 7,362.50
|
| | 592.603 | 3,703.77
|
| | 592.603 | 3,703.77
|
| | |
|
0006 0002.60 | 6.25 | 2,356.000 | 14,725.00
|
OVERLAY SOLID LINES | STA | 2,356.000 | 14,725.00
|
| | 1,073.486 | 6,709.29
|
| | 1,073.486 | 6,709.29
|
| | |
|
0007 0003.10 | 200.00 | 66.000 | 13,200.00
|
FLAGGING | DAY | 66.000 | 13,200.00
|
| | 85.500 | 17,100.00
|
| | 31.000 | 6,200.00
|
| | |
|
0008 0010.04 | 900.00 | 0.500 | 450.00
|
FIELD OFFICE | EACH | 0.500 | 450.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0009 0030.90 | 25,426.83 | 1.000 | 25,426.83
|
MOBILIZATION | LS | 1.000 | 25,426.83
|
| | 1.000 | 25,426.83
|
| | 0.000 | 0.00
|
| | |
|
0010 3040.12 | 152.00 | 35.900 | 5,456.80
|
CONCRETE PAVEMENT REPAIR, TYPE B, FULL DEPTH | SY | 35.900 | 5,456.80
|
| | 256.054 | 38,920.21
|
| | 41.533 | 6,313.02
|
| | |
|
0011 3221.05 | 130.00 | 211.600 | 27,508.00
|
CONCRETE PAVEMENT, CLASS PR-3625 | SY | 211.600 | 27,508.00
|
JOINT REPAIR | | 528.598 | 68,717.74
|
| | 91.466 | 11,890.58
|
| | |
|
0012 9000.75 | 9.50 | 500.000 | 4,750.00
|
ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE | TON | 500.000 | 4,750.00
|
SPS | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0013 9005.00 | 24.00 | 250.000 | 6,000.00
|
ASPHALTIC CONCRETE FOR PATCHING, TYPE | TON | 250.000 | 6,000.00
|
SP4(0.5) | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0014 9005.23 | 13.10 | 7,670.000 | 100,477.00
|
ASPHALTIC CONCRETE, TYPE SPS | TON | 7,670.000 | 100,477.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0015 9005.45 | 20.10 | 17,080.000 | 343,308.00
|
ASPHALTIC CONCRETE, TYPE SP4(0.5) | TON | 17,080.000 | 343,308.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0016 9020.92 | 167.00 | 27.000 | 4,509.00
|
PERFORMANCE GRADED BINDER (58-28) FOR STATE MAINTENANCEPATCHING | TON | 27.000 | 4,509.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0017 9021.01 | 167.00 | 935.820 | 156,281.94
|
PERFORMANCE GRADED BINDER (64-22) | TON | 935.820 | 156,281.94
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0018 9021.03 | 167.00 | 414.180 | 69,168.06
|
PERFORMANCE GRADED BINDER (58-28) | TON | 414.180 | 69,168.06
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0019 9053.00 | 0.90 | 39,490.000 | 35,541.00
|
TACK COAT | GAL | 39,490.000 | 35,541.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0020 9110.01 | 55.00 | 70.000 | 3,850.00
|
RENTAL OF LOADER, FULLY OPERATED | HOUR | 70.000 | 3,850.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0021 9110.02 | 55.00 | 70.000 | 3,850.00
|
RENTAL OF MOTOR GRADER, FULLY OPERATED | HOUR | 70.000 | 3,850.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0022 9110.03 | 40.00 | 70.000 | 2,800.00
|
RENTAL OF DUMP TRUCK, FULLY OPERATED | HOUR | 70.000 | 2,800.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0023 9110.07 | 35.00 | 70.000 | 2,450.00
|
RENTAL OF SKID LOADER, FULLY OPERATED | HOUR | 70.000 | 2,450.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0024 9179.23 | 80.00 | 589.110 | 47,128.80
|
COLD MILLING, CLASS 3 | STA | 589.110 | 47,128.80
|
| | 592.687 | 47,414.96
|
| | 592.687 | 47,414.96
|
| | |
|
0025 9179.43 | 57.75 | 586.261 | 33,856.57
|
COLD MILLING, CLASS 3 | STA | 586.261 | 33,856.57
|
A | | 523.634 | 30,239.86
|
| | 523.634 | 30,239.86
|
| | |
|
4000 3040.13 | 131.25 | 0.000 | 0.00
|
CONCRETE PAVEMENT REPAIR, TYPE C, FULL DEPTH | SY | 427.000 | 56,043.75
|
| | 428.720 | 56,269.50
|
| | 82.054 | 10,769.59
|
| | |
|
4001 0001.08 | 0.50 | 0.000 | 0.00
|
BARRICADE, TYPE II | BDAY | 1,320.000 | 660.00
|
| | 1,058.000 | 529.00
|
| | 191.000 | 95.50
|
| | |
|
0001 0001.10 | 4.00 | 24.000 | 96.00
|
BARRICADE, TYPE III | BDAY | 24.000 | 96.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0002 0001.30 | 4.00 | 24.000 | 96.00
|
TYPE B HIGH INTENSITY WARNING LIGHT | LDAY | 24.000 | 96.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0003 0001.75 | 7.00 | 28.000 | 196.00
|
TEMPORARY SIGN DAY | EACH | 28.000 | 196.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0004 0001.90 | 0.80 | 336.000 | 268.80
|
SIGN DAY | EACH | 336.000 | 268.80
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0005 0002.55 | 6.25 | 143.000 | 893.75
|
OVERLAY BROKEN LINES | STA | 143.000 | 893.75
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0006 0002.60 | 6.25 | 286.000 | 1,787.50
|
OVERLAY SOLID LINES | STA | 286.000 | 1,787.50
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0007 0003.10 | 200.00 | 14.000 | 2,800.00
|
FLAGGING | DAY | 14.000 | 2,800.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0008 0010.04 | 900.00 | 0.500 | 450.00
|
FIELD OFFICE | EACH | 0.500 | 450.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0009 0030.90 | 4,573.17 | 1.000 | 4,573.17
|
MOBILIZATION | LS | 1.000 | 4,573.17
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0013 9005.00 | 24.00 | 100.000 | 2,400.00
|
ASPHALTIC CONCRETE FOR PATCHING, TYPE | TON | 100.000 | 2,400.00
|
SP4(0.5) | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0014 9005.23 | 13.10 | 930.000 | 12,183.00
|
ASPHALTIC CONCRETE, TYPE SPS | TON | 930.000 | 12,183.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0015 9005.45 | 20.10 | 2,060.000 | 41,406.00
|
ASPHALTIC CONCRETE, TYPE SP4(0.5) | TON | 2,060.000 | 41,406.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0017 9021.01 | 167.00 | 116.640 | 19,478.88
|
PERFORMANCE GRADED BINDER (64-22) | TON | 116.640 | 19,478.88
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0018 9021.03 | 167.00 | 50.220 | 8,386.74
|
PERFORMANCE GRADED BINDER (58-28) | TON | 50.220 | 8,386.74
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0019 9053.00 | 0.90 | 4,770.000 | 4,293.00
|
TACK COAT | GAL | 4,770.000 | 4,293.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0020 9110.01 | 55.00 | 15.000 | 825.00
|
RENTAL OF LOADER, FULLY OPERATED | HOUR | 15.000 | 825.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0021 9110.02 | 55.00 | 15.000 | 825.00
|
RENTAL OF MOTOR GRADER, FULLY OPERATED | HOUR | 15.000 | 825.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0022 9110.03 | 40.00 | 15.000 | 600.00
|
RENTAL OF DUMP TRUCK, FULLY OPERATED | HOUR | 15.000 | 600.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0023 9110.07 | 35.00 | 15.000 | 525.00
|
RENTAL OF SKID LOADER, FULLY OPERATED | HOUR | 15.000 | 525.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0024 9179.23 | 80.00 | 71.558 | 5,724.64
|
COLD MILLING, CLASS 3 | STA | 71.558 | 5,724.64
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0025 9179.43 | 57.75 | 71.558 | 4,132.47
|
COLD MILLING, CLASS 3 | STA | 71.558 | 4,132.47
|
A | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
GROUP 9 BITUMINOUS | | Contracted | 1,026,254.06
|
| | Current | 1,082,957.81
|
| | In place | 301,383.76
|
| | This Estimate | 125,531.57
|
| | |
|
Totals for contract | | Contracted | 1,026,254.06
|
---|
| | Current | 1,082,957.81
|
---|
| | In place | 301,383.76
|
---|
| | This Estimate | 125,531.57
|
---|