Nebraska Department of Roads | |
---|---|
Estimate Summary to Contractor | |
Vendor ID: | 1809 CAPITAL CONTRACTORS, INC. |
Contract ID: | 6347 |
Estimate Number: | 0001 |
Pay Period End Date: | 06.14.2003 |
Contract Location: | ||
Big Springs | Estimate Type: | PROG |
Reference Post 104.27 | ||
Contractor: | ||
CAPITAL CONTRACTORS, INC. | Date Let: | |
1001 N 9TH ST | Date Awarded: | |
PO BOX 80098 | Date Contract Executed: | 05.23.2003 |
Date Notice to Proceed: | 05.23.2003 | |
LINCOLN NE 68501 | Date Work Began: | 05.24.2003 |
Phone: | Date Physical Work Completed: | |
(402)476-1021 | Date Accepted: | |
Escrow Agent: | ||
Surety Co: | ||
UNIVERSAL SURETY COMPANY |
Counties |
---|
DEUEL |
Project Number |   | PCT |   | Fed State Project Number |   | Description | |
---|---|---|---|---|---|---|---|
61347 000 |   | 0.000 |   | ER-80-3(131) |   | Clean Up - Big Springs |
Total to Date | Prev to Date | This Estimate | ||
Current Contract Amt | Total Earnings | $124,519.56 | $.00 | $124,519.56 |
$124,519.56 | Stockpiled Materials | $.00 | $.00 | $.00 |
Original Contract Amt | Gross Earnings | $124,519.56 | $.00 | $124,519.56 |
$124,519.56 | Retainage | $.00 | $.00 | $.00 |
Escrow Amount | $.00 | $.00 | $.00 | |
Percent Complete | Securities Encumbered | $.00 | $.00 | $.00 |
100.00% | Net Earnings | $124,519.56 | $.00 | $124,519.56 |
Liquidated Damages | $.00 | $.00 | $.00 | |
Incentives | $.00 | $.00 | $.00 | |
Disincentives | $.00 | $.00 | $.00 | |
Other Contract Adj | $.00 | $.00 | $.00 | |
Appl of Training Adj | $.00 | $.00 | $.00 | |
Training Rates Adj | $.00 | $.00 | $.00 | |
Fuel Adj | $.00 | $.00 | $.00 | |
Bituminous Adj | $.00 | $.00 | $.00 | |
Autopay Adj | $.00 | $.00 | $.00 | |
Gasoline Adj | $.00 | $.00 | $.00 | |
Other Adj | $.00 | $.00 | $.00 | |
Price Adj | $.00 | $.00 | $.00 | |
Substandard Item Adj | $.00 | $.00 | $.00 | |
Asphalt Adj | $.00 | $.00 | $.00 | |
Diesel Fuel Adj | $.00 | $.00 | $.00 | |
Petrol Adj | $.00 | $.00 | $.00 | |
Total for Adjustments | $.00 | $.00 | $.00 | |
Payment | $124,519.56 | $.00 | $124,519.56 | |
Project Manager | Div. Head/Dist. Eng. | |||
Thomsen, Toby | 06.16.2003 | O'Donnell, Les | 06.17.2003 | |
Constr. Estimate Eng. | Materials Eng. | |||
Hitzeman, Bill | 06.17.2003 | |||
Controller Div. Processed | ||||
Burling, Laurie | 06.17.2003 |
Detailed breakdown of stockpiled materials | ||||
---|---|---|---|---|
Total remaining for contract: | 0.00 |
1. Contracted | |||
---|---|---|---|
2. Current | |||
3. To date | |||
Item Nbr Item Code | Unit Price | 4. This Est | |
Item Description | Units | Qty | Amount |
Bridge @ Ref. Post 104.27 | |||
0001 B120.00 | 124,519.56 | 1.000 | 124,519.56 |
EMERGENCY REPAIR | LS | 1.000 | 124,519.56 |
Clean up of debris from Bridge 104.27 collapse | 1.000 | 124,519.56 | |
1.000 | 124,519.56 | ||
Bridge @ Ref. Post 104.27 | Contracted | 124,519.56 | |
Current | 124,519.56 | ||
In place | 124,519.56 | ||
This Estimate | 124,519.56 | ||
Totals for contract | Contracted | 124,519.56 | |
Current | 124,519.56 | ||
In place | 124,519.56 | ||
This Estimate | 124,519.56 |