| | | 1. Contracted
|
---|
| | | 2. Current
|
---|
| | | 3. To date
|
---|
Item Nbr Item Code | Unit Price | | 4. This Est
|
---|
Item Description | Units | Qty | Amount
|
---|
GROUP 6 BRIDGE AT STA. 9+40 | | |
|
0001 0001.10 | 1.35 | 1,584.000 | 2,138.40
|
BARRICADE, TYPE III | BDAY | 1,584.000 | 2,138.40
|
| | 26.000 | 35.10
|
| | 26.000 | 35.10
|
| | |
|
0002 0001.90 | 0.40 | 1,848.000 | 739.20
|
SIGN DAY | EACH | 1,848.000 | 739.20
|
| | 52.000 | 20.80
|
| | 52.000 | 20.80
|
| | |
|
0003 0001.98 | 1.50 | 792.000 | 1,188.00
|
CONTRACTOR FURNISHED SIGN | EACH | 792.000 | 1,188.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0004 0030.60 | 23,000.00 | 1.000 | 23,000.00
|
MOBILIZATION | LS | 1.000 | 23,000.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0005 1009.00 | 12,500.00 | 1.000 | 12,500.00
|
GENERAL CLEARING AND GRUBBING | LS | 1.000 | 12,500.00
|
| | 0.565 | 7,062.50
|
| | 0.565 | 7,062.50
|
| | |
|
0006 1011.00 | 7.50 | 100.000 | 750.00
|
WATER | kL | 100.000 | 750.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0007 1030.00 | 3.50 | 6,732.000 | 23,562.00
|
EARTHWORK MEASURED IN EMBANKMENT | m3 | 6,732.000 | 23,562.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0008 1136.01 | 500.00 | 4.000 | 2,000.00
|
REMOVE | EACH | 4.000 | 2,000.00
|
CONCRETE FILLED STEEL CAISSONS | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0009 1300.24 | 72.56 | 32.000 | 2,321.92
|
600 mm DRIVEWAY CULVERT PIPE | m | 32.000 | 2,321.92
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0010 6001.50 | 5,000.00 | 1.000 | 5,000.00
|
BENT NO.1 EXCAVATION | LS | 1.000 | 5,000.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0011 6001.51 | 5,000.00 | 1.000 | 5,000.00
|
BENT NO.2 EXCAVATION | LS | 1.000 | 5,000.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0012 6005.60 | 60.00 | 48.000 | 2,880.00
|
ELASTOMERIC BEARING | EACH | 48.000 | 2,880.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0013 6010.22 | 392.38 | 142.660 | 55,976.93
|
CLASS 47B-20 CONCRETE FOR BRIDGE | m3 | 142.660 | 55,976.93
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0014 6010.26 | 457.78 | 82.580 | 37,803.47
|
CLASS 47BD-30 CONCRETE FOR BRIDGE | m3 | 82.580 | 37,803.47
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0015 6011.11 | 65,000.00 | 1.000 | 65,000.00
|
PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE | LS | 1.000 | 65,000.00
|
AT STA. 9+40 | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0016 6020.00 | 1.32 | 10,426.000 | 13,762.32
|
REINFORCING STEEL FOR BRIDGE | kg | 10,426.000 | 13,762.32
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0017 6040.00 | 10,000.00 | 1.000 | 10,000.00
|
REMOVE STRUCTURE | EACH | 1.000 | 10,000.00
|
AT STA. 10+98.3 | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0018 6080.00 | 5.51 | 708.000 | 3,901.08
|
STRUCTURAL STEEL FOR SUBSTRUCTURE | kg | 708.000 | 3,901.08
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0019 6105.02 | 39.68 | 700.000 | 27,776.00
|
ROCK RIPRAP, TYPE B | Mg | 700.000 | 27,776.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0020 6200.00 | 82.02 | 426.400 | 34,973.33
|
CONCRETE PILING | m | 426.400 | 34,973.33
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0021 6310.00 | 129.17 | 367.000 | 47,405.39
|
STEEL SHEET PILING | m2 | 367.000 | 47,405.39
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0022 7020.00 | 1,500.00 | 2.000 | 3,000.00
|
BRIDGE APPROACH SECTIONS | EACH | 2.000 | 3,000.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0023 7021.47 | 1,500.00 | 2.000 | 3,000.00
|
MELT | EACH | 2.000 | 3,000.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0024 L006.00 | 250.00 | 1.000 | 250.00
|
COVER CROP SEEDING | ha | 1.000 | 250.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
GROUP 6 BRIDGE AT STA. 9+40 | | Contracted | 383,928.04
|
| | Current | 383,928.04
|
| | In place | 7,118.40
|
| | This Estimate | 7,118.40
|
| | |
|
Totals for contract | | Contracted | 383,928.04
|
---|
| | Current | 383,928.04
|
---|
| | In place | 7,118.40
|
---|
| | This Estimate | 7,118.40
|
---|