| | | 1. Contracted
|
---|
| | | 2. Current
|
---|
| | | 3. To date
|
---|
Item Nbr Item Code | Unit Price | | 4. This Est
|
---|
Item Description | Units | Qty | Amount
|
---|
GROUP 6 BRIDGE AT STA. 6+57 | | |
|
0001 0001.10 | 1.50 | 1,180.000 | 1,770.00
|
BARRICADE, TYPE III | BDAY | 1,180.000 | 1,770.00
|
| | 285.000 | 427.50
|
| | 285.000 | 427.50
|
| | |
|
0002 0001.90 | 0.75 | 1,416.000 | 1,062.00
|
SIGN DAY | EACH | 1,416.000 | 1,062.00
|
| | 171.000 | 128.25
|
| | 171.000 | 128.25
|
| | |
|
0003 0001.99 | 1.00 | 708.000 | 708.00
|
CONTRACTOR FURNISHED SIGN DAY | EACH | 708.000 | 708.00
|
| | 76.000 | 76.00
|
| | 76.000 | 76.00
|
| | |
|
0004 0030.60 | 34,200.00 | 1.000 | 34,200.00
|
MOBILIZATION | LS | 1.000 | 34,200.00
|
| | 0.985 | 33,687.00
|
| | 0.985 | 33,687.00
|
| | |
|
0005 1000.00 | 250.00 | 1.000 | 250.00
|
LARGE TREE REMOVAL | EACH | 1.000 | 250.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0006 1009.00 | 1,500.00 | 1.000 | 1,500.00
|
GENERAL CLEARING AND GRUBBING | LS | 1.000 | 1,500.00
|
| | 0.500 | 750.00
|
| | 0.500 | 750.00
|
| | |
|
0007 1010.01 | 5.00 | 1,573.000 | 7,865.00
|
EXCAVATION (ESTABLISHED QUANTITY) | m3 | 1,573.000 | 7,865.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0008 1011.00 | 3.00 | 197.000 | 591.00
|
WATER | kL | 197.000 | 591.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0009 6001.50 | 6,500.00 | 1.000 | 6,500.00
|
BENT NO.1 EXCAVATION | LS | 1.000 | 6,500.00
|
| | 1.000 | 6,500.00
|
| | 1.000 | 6,500.00
|
| | |
|
0010 6001.51 | 6,500.00 | 1.000 | 6,500.00
|
BENT NO.2 EXCAVATION | LS | 1.000 | 6,500.00
|
| | 1.000 | 6,500.00
|
| | 1.000 | 6,500.00
|
| | |
|
0011 6010.22 | 490.49 | 119.950 | 58,834.28
|
CLASS 47B-20 CONCRETE FOR BRIDGE | m3 | 119.950 | 58,834.28
|
| | 40.550 | 19,889.37
|
| | 40.550 | 19,889.37
|
| | |
|
0012 6010.26 | 516.63 | 133.990 | 69,223.25
|
CLASS 47BD-30 CONCRETE FOR BRIDGE | m3 | 133.990 | 69,223.25
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0013 6020.00 | 1.43 | 23,717.000 | 33,915.31
|
REINFORCING STEEL FOR BRIDGE | kg | 23,717.000 | 33,915.31
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0014 6040.00 | 7,500.00 | 1.000 | 7,500.00
|
REMOVE STRUCTURE | EACH | 1.000 | 7,500.00
|
AT STA. 6+59.5 | | 0.700 | 5,250.00
|
| | 0.700 | 5,250.00
|
| | |
|
0015 6080.00 | 6.61 | 676.000 | 4,468.36
|
STRUCTURAL STEEL FOR SUBSTRUCTURE | kg | 676.000 | 4,468.36
|
| | 338.000 | 2,234.18
|
| | 338.000 | 2,234.18
|
| | |
|
0016 6105.02 | 43.00 | 461.000 | 19,823.00
|
ROCK RIPRAP, TYPE B | Mg | 461.000 | 19,823.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0017 6210.12 | 78.74 | 195.200 | 15,370.05
|
HP 250 mm X 62 kg STEEL PILING | m | 195.200 | 15,370.05
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0018 6210.14 | 85.30 | 164.200 | 14,006.26
|
HP 310 mm X 79 kg STEEL PILING | m | 164.200 | 14,006.26
|
| | 158.130 | 13,488.49
|
| | 158.130 | 13,488.49
|
| | |
|
0019 6310.00 | 129.17 | 322.000 | 41,592.74
|
STEEL SHEET PILING | m2 | 322.000 | 41,592.74
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0020 7020.00 | 1,250.00 | 4.000 | 5,000.00
|
BRIDGE APPROACH SECTIONS | EACH | 4.000 | 5,000.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0021 7021.47 | 1,500.00 | 4.000 | 6,000.00
|
MELT | EACH | 4.000 | 6,000.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0022 L006.00 | 175.00 | 0.500 | 87.50
|
COVER CROP SEEDING | ha | 0.500 | 87.50
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
GROUP 6 BRIDGE AT STA. 6+57 | | Contracted | 336,766.75
|
| | Current | 336,766.75
|
| | In place | 88,930.79
|
| | This Estimate | 88,930.79
|
| | |
|
Totals for contract | | Contracted | 336,766.75
|
---|
| | Current | 336,766.75
|
---|
| | In place | 88,930.79
|
---|
| | This Estimate | 88,930.79
|
---|