Nebraska Department of Roads | |
---|---|
Estimate Summary to Contractor | |
Vendor ID: | 0929 MIDLANDS CONTRACTING, INC. |
Contract ID: | 7860 |
Estimate Number: | 0003 |
Pay Period End Date: | 07.12.2003 |
Contract Location: | ||
HAYES CENTER NORTHEAST | Estimate Type: | PROG |
Contractor: | ||
MIDLANDS CONTRACTING, INC. | Date Let: | 03.13.2003 |
10075 1ST AVE | Date Awarded: | 04.09.2003 |
PO BOX 1065 | Date Contract Executed: | 05.08.2003 |
Date Notice to Proceed: | 05.08.2003 | |
KEARNEY NE 68848-1065 | Date Work Began: | 06.02.2003 |
Phone: | Date Physical Work Completed: | |
(308)237-7979 | Date Accepted: | |
Escrow Agent: | ||
Surety Co: | ||
UNITED STATES FIDELITY AND GUARANTY COMPANY |
Counties |
---|
HAYES |
Project Number |   | PCT |   | Fed State Project Number |   | Description | |
---|---|---|---|---|---|---|---|
70860 000 |   | 0.000 |   | BRO-7043(6) |   | CULVERTS |
Total to Date | Prev to Date | This Estimate | ||
Current Contract Amt | Total Earnings | $95,426.84 | $89,265.64 | $6,161.20 |
$96,821.02 | Stockpiled Materials | $.00 | $.00 | $.00 |
Original Contract Amt | Gross Earnings | $95,426.84 | $89,265.64 | $6,161.20 |
$96,821.02 | Retainage | $-954.27 | $-892.66 | $-61.61 |
Escrow Amount | $.00 | $.00 | $.00 | |
Percent Complete | Securities Encumbered | $.00 | $.00 | $.00 |
98.56% | Net Earnings | $94,472.57 | $88,372.98 | $6,099.59 |
Liquidated Damages | $.00 | $.00 | $.00 | |
Incentives | $.00 | $.00 | $.00 | |
Disincentives | $.00 | $.00 | $.00 | |
Other Contract Adj | $.00 | $.00 | $.00 | |
Appl of Training Adj | $.00 | $.00 | $.00 | |
Training Rates Adj | $.00 | $.00 | $.00 | |
Fuel Adj | $-23.63 | $.00 | $-23.63 | |
Bituminous Adj | $.00 | $.00 | $.00 | |
Autopay Adj | $.00 | $.00 | $.00 | |
Gasoline Adj | $.00 | $.00 | $.00 | |
Other Adj | $.00 | $.00 | $.00 | |
Price Adj | $.00 | $.00 | $.00 | |
Substandard Item Adj | $.00 | $.00 | $.00 | |
Asphalt Adj | $.00 | $.00 | $.00 | |
Diesel Fuel Adj | $.00 | $.00 | $.00 | |
Petrol Adj | $.00 | $.00 | $.00 | |
Total for Adjustments | -$23.63 | $.00 | -$23.63 | |
Payment | $94,448.94 | $88,372.98 | $6,075.96 | |
Project Manager | Project Engineer | |||
Stadler, Lisa | 07.14.2003 | Collins, Duane | 07.14.2003 | |
Div. Head/Dist. Eng. | Constr. Estimate Eng. | |||
Vosburg, Kurt | 07.14.2003 | Bartos, Steve | 07.15.2003 | |
Controller Div. Processed | ||||
Burling, Laurie | 07.15.2003 |
Detailed breakdown of stockpiled materials | ||||
---|---|---|---|---|
Total remaining for contract: | 0.00 |
1. Contracted | |||
---|---|---|---|
2. Current | |||
3. To date | |||
Item Nbr Item Code | Unit Price | 4. This Est | |
Item Description | Units | Qty | Amount |
GROUP 4 CULVERT AT STA. 16+60 | |||
0001 0001.10 | 1.60 | 620.000 | 992.00 |
BARRICADE, TYPE III | BDAY | 620.000 | 992.00 |
350.000 | 560.00 | ||
100.000 | 160.00 | ||
0002 0001.90 | 0.80 | 744.000 | 595.20 |
SIGN DAY | EACH | 744.000 | 595.20 |
584.000 | 467.20 | ||
184.000 | 147.20 | ||
0003 0001.99 | 1.10 | 372.000 | 409.20 |
CONTRACTOR FURNISHED SIGN DAY | EACH | 372.000 | 409.20 |
0.000 | 0.00 | ||
0.000 | 0.00 | ||
0004 0030.40 | 9,500.00 | 1.000 | 9,500.00 |
MOBILIZATION | LS | 1.000 | 9,500.00 |
1.000 | 9,500.00 | ||
0.000 | 0.00 | ||
0005 1009.00 | 1,500.00 | 1.000 | 1,500.00 |
GENERAL CLEARING AND GRUBBING | LS | 1.000 | 1,500.00 |
1.000 | 1,500.00 | ||
1.000 | 1,500.00 | ||
0006 1011.00 | 17.00 | 25.000 | 425.00 |
WATER | MGAL | 25.000 | 425.00 |
0.000 | 0.00 | ||
0.000 | 0.00 | ||
0007 1030.00 | 6.00 | 606.000 | 3,636.00 |
EARTHWORK MEASURED IN EMBANKMENT | CY | 606.000 | 3,636.00 |
606.000 | 3,636.00 | ||
606.000 | 3,636.00 | ||
0008 1300.18 | 13.00 | 36.000 | 468.00 |
18" DRIVEWAY CULVERT PIPE | LF | 36.000 | 468.00 |
36.000 | 468.00 | ||
36.000 | 468.00 | ||
0009 4051.01 | 18.00 | 730.000 | 13,140.00 |
EXCAVATION FOR BOX CULVERTS | CY | 730.000 | 13,140.00 |
730.000 | 13,140.00 | ||
0.000 | 0.00 | ||
0010 4101.06 | 312.00 | 162.510 | 50,703.12 |
CLASS 47B-3000 OR AX-3000 CONCRETE FOR BOX CULVERT | CY | 162.510 | 50,703.12 |
162.510 | 50,703.12 | ||
0.000 | 0.00 | ||
0011 4151.00 | 0.75 | 18,670.000 | 14,002.50 |
REINFORCING STEEL FOR BOX CULVERT | LB | 18,670.000 | 14,002.50 |
18,670.000 | 14,002.50 | ||
0.000 | 0.00 | ||
0012 6040.00 | 1,200.00 | 1.000 | 1,200.00 |
REMOVE STRUCTURE | EACH | 1.000 | 1,200.00 |
AT STA. 16+66 | 1.000 | 1,200.00 | |
0.000 | 0.00 | ||
0013 L006.00 | 250.00 | 1.000 | 250.00 |
COVER CROP SEEDING | ACRE | 1.000 | 250.00 |
1.000 | 250.00 | ||
1.000 | 250.00 | ||
GROUP 4 CULVERT AT STA. 16+60 | Contracted | 96,821.02 | |
Current | 96,821.02 | ||
In place | 95,426.82 | ||
This Estimate | 6,161.20 | ||
Totals for contract | Contracted | 96,821.02 | |
Current | 96,821.02 | ||
In place | 95,426.82 | ||
This Estimate | 6,161.20 |