| | | 1. Contracted
|
---|
| | | 2. Current
|
---|
| | | 3. To date
|
---|
Item Nbr Item Code | Unit Price | | 4. This Est
|
---|
Item Description | Units | Qty | Amount
|
---|
GROUP 1 GRADING | | |
|
0001 L020.01 | 10.00 | 3,210.000 | 32,100.00
|
EROSION CONTROL, TYPE A | m2 | 3,210.000 | 32,100.00
|
| | 3,362.600 | 33,626.00
|
| | 0.000 | 0.00
|
| | |
|
0002 L020.03 | 2.50 | 34,458.000 | 86,145.00
|
EROSION CONTROL, TYPE C | m2 | 34,458.000 | 86,145.00
|
| | 35,516.700 | 88,791.75
|
| | 0.000 | 0.00
|
| | |
|
0003 L020.20 | 0.65 | 22,672.000 | 14,736.80
|
SLOPE PROTECTION NETTING | m2 | 22,672.000 | 14,736.80
|
| | 33,124.500 | 21,530.93
|
| | 0.000 | 0.00
|
| | |
|
0004 L021.01 | 30.00 | 105.000 | 3,150.00
|
EROSION CHECKS, TYPE A | BALE | 105.000 | 3,150.00
|
| | 105.000 | 3,150.00
|
| | 0.000 | 0.00
|
| | |
|
0005 L021.03 | 25.00 | 1,652.000 | 41,300.00
|
EROSION CHECKS, TYPE C | BALE | 1,652.000 | 41,300.00
|
| | 1,591.000 | 39,775.00
|
| | 0.000 | 0.00
|
| | |
|
0006 L021.11 | 25.00 | 133.000 | 3,325.00
|
EROSION CHECKS, TYPE ST-A | BALE | 133.000 | 3,325.00
|
| | 135.000 | 3,375.00
|
| | 0.000 | 0.00
|
| | |
|
0007 L021.14 | 25.00 | 280.000 | 7,000.00
|
EROSION CHECKS, TYPE ST-C | BALE | 280.000 | 7,000.00
|
| | 251.000 | 6,275.00
|
| | 0.000 | 0.00
|
| | |
|
0008 L022.25 | 9.00 | 10,102.000 | 90,918.00
|
FABRIC SILT FENCE, TYPE COIR FIBER | m | 10,102.000 | 90,918.00
|
| | 10,575.000 | 95,175.00
|
| | 0.000 | 0.00
|
| | |
|
0009 L022.75 | 17.00 | 864.800 | 14,701.60
|
TEMPORARY SILT CHECK | m | 864.800 | 14,701.60
|
| | 943.000 | 16,031.00
|
| | 0.000 | 0.00
|
| | |
|
0010 0030.10 | 23,500.00 | 1.000 | 23,500.00
|
MOBILIZATION | LS | 1.000 | 23,500.00
|
| | 1.000 | 23,500.00
|
| | 0.000 | 0.00
|
| | |
|
0011 1009.00 | 7,500.00 | 1.000 | 7,500.00
|
GENERAL CLEARING AND GRUBBING | LS | 1.000 | 7,500.00
|
| | 1.000 | 7,500.00
|
| | 0.000 | 0.00
|
| | |
|
0012 1010.00 | 1.37 | 426,783.000 | 584,692.71
|
EXCAVATION | m3 | 426,783.000 | 584,692.71
|
| | 426,783.000 | 584,692.71
|
| | 0.000 | 0.00
|
| | |
|
0013 1010.01 | 1.28 | 35,475.000 | 45,408.00
|
EXCAVATION (ESTABLISHED QUANTITY) | m3 | 35,475.000 | 45,408.00
|
| | 35,475.000 | 45,408.00
|
| | 0.000 | 0.00
|
| | |
|
0014 1011.00 | 0.25 | 4,268.000 | 1,067.00
|
WATER | kL | 4,268.000 | 1,067.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0015 1012.00 | 60.00 | 160.000 | 9,600.00
|
RIGHT-OF-WAY MARKERS | EACH | 160.000 | 9,600.00
|
| | 159.000 | 9,540.00
|
| | 0.000 | 0.00
|
| | |
|
0016 1040.00 | 0.24 | 1,030,000.000 | 247,200.00
|
SLOPE PROTECTION | m2 | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0017 1040.05 | 0.20 | 62,455.000 | 12,491.00
|
TEMPORARY SLOPE PROTECTION | m2 | 62,455.000 | 12,491.00
|
| | 56,000.000 | 11,200.00
|
| | 0.000 | 0.00
|
| | |
|
0018 1040.06 | 70.00 | 1,133.000 | 79,310.00
|
SLOPE PROTECTION MULCH | Mg | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0019 1041.00 | 0.72 | 5,683.000 | 4,091.76
|
SALVAGING AND PLACING TOPSOIL | m2 | 5,683.000 | 4,091.76
|
| | 5,807.600 | 4,181.47
|
| | 0.000 | 0.00
|
| | |
|
0020 1042.00 | 2.40 | 7,400.000 | 17,760.00
|
SALVAGING AND PLACING HYDRIC SOIL | m2 | 7,400.000 | 17,760.00
|
| | 18,006.300 | 43,215.12
|
| | 0.000 | 0.00
|
| | |
|
0021 1111.00 | 1.32 | 11,255.000 | 14,856.60
|
REMOVE FENCE | m | 10,040.000 | 13,252.80
|
| | 9,989.700 | 13,186.40
|
| | 0.000 | 0.00
|
| | |
|
0022 7017.00 | 6.50 | 1,737.000 | 11,290.50
|
REMOVE GUARDRAIL | m | 1,737.000 | 11,290.50
|
| | 1,737.000 | 11,290.50
|
| | 0.000 | 0.00
|
| | |
|
4000 1010.50 | 2.74 | 0.000 | 0.00
|
REMOVAL OF UNSUITABLE MATERIAL | m3 | 1,552.000 | 4,252.48
|
Removal of unsuitably wet material at Sta. 238-+ | | 2,989.000 | 8,189.86
|
| | 0.000 | 0.00
|
| | |
|
4010 1300.15 | 22.95 | 0.000 | 0.00
|
375 mm DRIVEWAY CULVERT PIPE | m | 24.400 | 559.98
|
Station 302+00 on the Right | | 24.400 | 559.98
|
| | 0.000 | 0.00
|
| | |
|
4011 1300.36 | 45.90 | 0.000 | 0.00
|
900 mm DRIVEWAY CULVERT PIPE | m | 13.400 | 615.06
|
Station 320+79 on the right | | 13.400 | 615.06
|
| | 0.000 | 0.00
|
| | |
|
4012 1041.00 | 0.61 | 0.000 | 0.00
|
SALVAGING AND PLACING TOPSOIL | m2 | 157,300.000 | 95,953.00
|
Soil that is NOT of the Prairie Fringed Orchid Seedbank | | 130,389.150 | 79,537.38
|
| | 0.000 | 0.00
|
| | |
|
4013 1040.00 | 0.366 | 0.000 | 0.00
|
SLOPE PROTECTION | m2 | 425,000.000 | 155,550.00
|
This item replaces item 0016 | | 401,225.710 | 146,848.61
|
| | 0.000 | 0.00
|
| | |
|
4014 1040.06 | 80.50 | 0.000 | 0.00
|
SLOPE PROTECTION MULCH | Mg | 468.000 | 37,674.00
|
This item replaces item 0018 | | 382.990 | 30,830.70
|
| | 0.000 | 0.00
|
| | |
|
4017 1905.03 | 263.46 | 0.000 | 0.00
|
MATERIAL DELIVERED NOT INCORPORATED | EACH | 99.000 | 26,082.54
|
Slope Protection Seeding which was not used on the project. | | 89.000 | 23,447.94
|
| | 0.000 | 0.00
|
| | |
|
GROUP 1 GRADING | | Contracted | 1,352,143.97
|
| | Current | 1,344,717.23
|
| | In place | 1,351,473.41
|
| | This Estimate | 0.00
|
| | |
|
GROUP 4 CULVERTS | | |
|
0023 0030.40 | 4,500.00 | 1.000 | 4,500.00
|
MOBILIZATION | LS | 1.000 | 4,500.00
|
| | 1.000 | 4,500.00
|
| | 0.000 | 0.00
|
| | |
|
0024 4035.00 | 100.00 | 2.000 | 200.00
|
REMOVE FLARED-END SECTION | EACH | 2.000 | 200.00
|
| | 2.000 | 200.00
|
| | 0.000 | 0.00
|
| | |
|
0025 4050.01 | 12.00 | 38.000 | 456.00
|
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS | m3 | 38.000 | 456.00
|
| | 38.000 | 456.00
|
| | 0.000 | 0.00
|
| | |
|
0026 4350.24 | 56.00 | 8.400 | 470.40
|
600 mm CORRUGATED METAL PIPE | m | 8.400 | 470.40
|
| | 8.400 | 470.40
|
| | 0.000 | 0.00
|
| | |
|
0027 4350.30 | 82.00 | 54.000 | 4,428.00
|
750 mm CORRUGATED METAL PIPE | m | 54.000 | 4,428.00
|
| | 54.000 | 4,428.00
|
| | 0.000 | 0.00
|
| | |
|
0028 4350.36 | 98.00 | 16.000 | 1,568.00
|
900 mm CORRUGATED METAL PIPE | m | 16.000 | 1,568.00
|
| | 16.000 | 1,568.00
|
| | 0.000 | 0.00
|
| | |
|
0029 4350.48 | 268.00 | 3.200 | 857.60
|
1200 mm CORRUGATED METAL PIPE | m | 3.200 | 857.60
|
| | 3.200 | 857.60
|
| | 0.000 | 0.00
|
| | |
|
0030 4360.24 | 150.00 | 4.000 | 600.00
|
600 mm METAL FLARED-END SECTION | EACH | 4.000 | 600.00
|
| | 4.000 | 600.00
|
| | 0.000 | 0.00
|
| | |
|
0031 4360.30 | 230.00 | 4.000 | 920.00
|
750 mm METAL FLARED-END SECTION | EACH | 4.000 | 920.00
|
| | 4.000 | 920.00
|
| | 0.000 | 0.00
|
| | |
|
0032 4360.36 | 355.00 | 2.000 | 710.00
|
900 mm METAL FLARED-END SECTION | EACH | 2.000 | 710.00
|
| | 2.000 | 710.00
|
| | 0.000 | 0.00
|
| | |
|
0033 4360.48 | 850.00 | 2.000 | 1,700.00
|
1200 mm METAL FLARED-END SECTION | EACH | 2.000 | 1,700.00
|
| | 2.000 | 1,700.00
|
| | 0.000 | 0.00
|
| | |
|
4002 4300.15 | 34.44 | 0.000 | 0.00
|
375 mm CULVERT PIPE | m | 34.400 | 1,184.74
|
Temporary culvert pipe to provide for drainage between the shoo-fly & new roadway. | | 34.400 | 1,184.74
|
| | 0.000 | 0.00
|
| | |
|
4003 4976.05 | 3,937.50 | 0.000 | 0.00
|
ADDITIONAL WORK | LS | 1.000 | 3,937.50
|
Extending culvert at south end of project which was not shown on the plans. | | 1.000 | 3,937.50
|
| | 0.000 | 0.00
|
| | |
|
4004 4024.73 | 2,100.00 | 0.000 | 0.00
|
CONCRETE FLUME, TYPE IV | EACH | 1.000 | 2,100.00
|
| | 1.000 | 2,100.00
|
| | 0.000 | 0.00
|
| | |
|
4005 4024.74 | 2,100.00 | 0.000 | 0.00
|
CONCRETE FLUME, TYPE V | EACH | 3.000 | 6,300.00
|
| | 3.000 | 6,300.00
|
| | 0.000 | 0.00
|
| | |
|
4006 4300.15 | 155.50 | 0.000 | 0.00
|
375 mm CULVERT PIPE | m | 53.660 | 8,344.13
|
For Flumes | | 58.290 | 9,064.10
|
| | 0.000 | 0.00
|
| | |
|
GROUP 4 CULVERTS | | Contracted | 16,410.00
|
| | Current | 38,276.37
|
| | In place | 38,996.34
|
| | This Estimate | 0.00
|
| | |
|
GROUP 7B FENCING | | |
|
0034 0030.70 | 1,000.00 | 1.000 | 1,000.00
|
MOBILIZATION | LS | 1.000 | 1,000.00
|
| | 1.000 | 1,000.00
|
| | 0.000 | 0.00
|
| | |
|
0035 7101.00 | 70.00 | 5.000 | 350.00
|
PRIVATE FENCE TERMINALS | EACH | 5.000 | 350.00
|
| | 8.000 | 560.00
|
| | 0.000 | 0.00
|
| | |
|
0036 7104.00 | 100.00 | 82.000 | 8,200.00
|
PULL POSTS | EACH | 93.000 | 9,300.00
|
| | 93.000 | 9,300.00
|
| | 0.000 | 0.00
|
| | |
|
0037 7105.00 | 70.00 | 7.000 | 490.00
|
CORNER POSTS | EACH | 5.000 | 350.00
|
| | 16.000 | 1,120.00
|
| | 0.000 | 0.00
|
| | |
|
0038 7106.15 | 200.00 | 2.000 | 400.00
|
4.5 m VEHICLE GATE | EACH | 4.000 | 800.00
|
| | 4.000 | 800.00
|
| | 0.000 | 0.00
|
| | |
|
0039 7110.02 | 15.33 | 1,650.000 | 25,294.50
|
0.9 METER CHAIN-LINK FENCE | m | 1,650.000 | 25,294.50
|
| | 1,607.000 | 24,635.31
|
| | 0.000 | 0.00
|
| | |
|
0040 7112.03 | 50.00 | 6.000 | 300.00
|
TAKE DOWN PANEL FOR 0.9 METER CHAIN-LINK FENCE | EACH | 6.000 | 300.00
|
| | 6.000 | 300.00
|
| | 0.000 | 0.00
|
| | |
|
0041 7115.02 | 75.00 | 24.000 | 1,800.00
|
END POST FOR 0.9 METER CHAIN-LINK FENCE | EACH | 24.000 | 1,800.00
|
| | 22.000 | 1,650.00
|
| | 0.000 | 0.00
|
| | |
|
0042 7116.02 | 75.00 | 24.000 | 1,800.00
|
CORNER POST FOR 0.9 m CHAIN-LINK FENCE | EACH | 24.000 | 1,800.00
|
| | 24.000 | 1,800.00
|
| | 0.000 | 0.00
|
| | |
|
0043 7117.02 | 100.00 | 24.000 | 2,400.00
|
PULL POST FOR 0.9 METER CHAIN-LINK FENCE | EACH | 24.000 | 2,400.00
|
| | 18.000 | 1,800.00
|
| | 0.000 | 0.00
|
| | |
|
0044 7130.00 | 2.99 | 12,278.000 | 36,711.22
|
BARBED WIRE FENCE | m | 10,675.000 | 31,918.25
|
| | 11,504.400 | 34,398.16
|
| | 0.000 | 0.00
|
| | |
|
4015 6960.02 | 7,764.25 | 0.000 | 0.00
|
ADDITIONAL WORK | LS | 1.000 | 7,764.25
|
For modification of the fence around culvert ends | | 1.000 | 7,764.25
|
| | 0.000 | 0.00
|
| | |
|
4016 6960.06 | 2.66 | 0.000 | 0.00
|
ADDITIONAL WORK | m | 1,650.000 | 4,389.00
|
To dig a trench and bury the bottom of the chain link fence 80mm below the surface of the ground. | | 1,607.000 | 4,274.62
|
| | 0.000 | 0.00
|
| | |
|
4021 1905.00 | 2,184.40 | 0.000 | 0.00
|
MATERIAL DELIVERED NOT INCORPORATED | LS | 1.000 | 2,184.40
|
Fencing Material (Posts, Wire & Ties) Delivered but not incorporated at wetland site number 1. | | 1.000 | 2,184.40
|
| | 0.000 | 0.00
|
| | |
|
4022 6960.02 | 2,614.00 | 0.000 | 0.00
|
ADDITIONAL WORK | LS | 1.000 | 2,614.00
|
For labor costs which the contractor incurred placing a portion of the fence on wetland site number 1. | | 1.000 | 2,614.00
|
| | 0.000 | 0.00
|
| | |
|
GROUP 7B FENCING | | Contracted | 78,745.72
|
| | Current | 92,264.40
|
| | In place | 94,200.74
|
| | This Estimate | 0.00
|
| | |
|
GROUP 9 BITUMINOUS | | |
|
0045 0002.40 | 23.10 | 425.900 | 9,838.29
|
TEMPORARY SOLID LINES | StaM | 425.900 | 9,838.29
|
| | 897.100 | 20,723.01
|
| | 0.000 | 0.00
|
| | |
|
0046 0002.45 | 23.10 | 212.950 | 4,919.15
|
TEMPORARY BROKEN LINES | StaM | 212.950 | 4,919.15
|
| | 245.800 | 5,677.98
|
| | 0.000 | 0.00
|
| | |
|
0047 0002.75 | 0.15 | 31,500.000 | 4,725.00
|
PERMANENT PAVEMENT MARKING | m | 31,500.000 | 4,725.00
|
| | 37,800.000 | 5,670.00
|
| | 0.000 | 0.00
|
| | |
|
0048 0030.90 | 24,000.00 | 1.000 | 24,000.00
|
MOBILIZATION | LS | 1.000 | 24,000.00
|
| | 1.000 | 24,000.00
|
| | 0.000 | 0.00
|
| | |
|
0049 2021.00 | 50.00 | 4.000 | 200.00
|
MAILBOX POST | EACH | 4.000 | 200.00
|
| | 4.000 | 200.00
|
| | 0.000 | 0.00
|
| | |
|
0050 8008.00 | 23.55 | 540.000 | 12,717.00
|
ARMOR COAT AGGREGATE | m3 | 540.000 | 12,717.00
|
| | 527.540 | 12,423.57
|
| | 0.000 | 0.00
|
| | |
|
0051 8029.84 | 1.55 | 63,474.000 | 98,384.70
|
BITUMINOUS FOUNDATION COURSE 100 mm | m2 | 63,474.000 | 98,384.70
|
| | 63,036.000 | 97,705.80
|
| | 0.000 | 0.00
|
| | |
|
0052 8111.00 | 175.00 | 252.000 | 44,100.00
|
SHOULDER SUBGRADE PREPARATION | StaM | 252.000 | 44,100.00
|
| | 252.000 | 44,100.00
|
| | 0.000 | 0.00
|
| | |
|
0053 9000.75 | 12.00 | 100.000 | 1,200.00
|
ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE | Mg | 100.000 | 1,200.00
|
SPS | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0054 9005.00 | 22.00 | 100.000 | 2,200.00
|
ASPHALTIC CONCRETE FOR PATCHING, TYPE | Mg | 100.000 | 2,200.00
|
SP2 | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0055 9005.23 | 13.92 | 22,750.000 | 316,680.00
|
ASPHALTIC CONCRETE, TYPE SPS | Mg | 22,750.000 | 316,680.00
|
| | 22,744.100 | 316,597.88
|
| | 0.000 | 0.00
|
| | |
|
0056 9005.30 | 20.00 | 35,080.000 | 701,600.00
|
ASPHALTIC CONCRETE, TYPE SP2(12.5) | Mg | 35,080.000 | 701,600.00
|
| | 35,218.220 | 704,364.40
|
| | 0.000 | 0.00
|
| | |
|
0057 9009.00 | 4.15 | 2,014.000 | 8,358.10
|
PLACEMENT OF ASPHALTIC CONCRETE FOR DRIVEWAYS ANDINTERSECTIONS | m2 | 2,014.000 | 8,358.10
|
| | 1,921.500 | 7,974.23
|
| | 0.000 | 0.00
|
| | |
|
0058 9020.92 | 177.25 | 5.400 | 957.15
|
PERFORMANCE GRADED BINDER (58-28) FOR STATE MAINTENANCEPATCHING | Mg | 5.400 | 957.15
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0059 9021.01 | 177.25 | 1,899.720 | 336,725.37
|
PERFORMANCE GRADED BINDER (64-22) | Mg | 3,138.220 | 556,249.50
|
| | 2,064.800 | 365,985.81
|
| | 0.000 | 0.00
|
| | |
|
0060 9021.03 | 177.25 | 1,228.500 | 217,751.63
|
PERFORMANCE GRADED BINDER (58-28) | Mg | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0061 9034.00 | 2.50 | 2,014.000 | 5,035.00
|
PREPARATION OF INTERSECTIONS AND DRIVEWAYS | m2 | 2,014.000 | 5,035.00
|
| | 1,921.500 | 4,803.75
|
| | 0.000 | 0.00
|
| | |
|
0062 9052.00 | 260.00 | 107.420 | 27,929.20
|
ARMOR COAT EMULSIFIED ASPHALT | kL | 107.420 | 27,929.20
|
| | 115.959 | 30,149.34
|
| | 0.000 | 0.00
|
| | |
|
0063 9053.00 | 0.30 | 68,779.000 | 20,633.70
|
TACK COAT | L | 68,779.000 | 20,633.70
|
| | 153,673.000 | 46,101.90
|
| | 0.000 | 0.00
|
| | |
|
0064 9110.01 | 50.00 | 40.000 | 2,000.00
|
RENTAL OF LOADER, FULLY OPERATED | HOUR | 40.000 | 2,000.00
|
| | 4.000 | 200.00
|
| | 0.000 | 0.00
|
| | |
|
0065 9110.02 | 50.00 | 40.000 | 2,000.00
|
RENTAL OF MOTOR GRADER, FULLY OPERATED | HOUR | 40.000 | 2,000.00
|
| | 13.000 | 650.00
|
| | 0.000 | 0.00
|
| | |
|
0066 9110.03 | 40.00 | 40.000 | 1,600.00
|
RENTAL OF DUMP TRUCK, FULLY OPERATED | HOUR | 40.000 | 1,600.00
|
| | 14.000 | 560.00
|
| | 0.000 | 0.00
|
| | |
|
0067 9110.07 | 35.00 | 40.000 | 1,400.00
|
RENTAL OF SKID LOADER, FULLY OPERATED | HOUR | 40.000 | 1,400.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0068 9111.00 | 2.00 | 2,849.000 | 5,698.00
|
WATER | kL | 2,849.000 | 5,698.00
|
| | 786.790 | 1,573.58
|
| | 0.000 | 0.00
|
| | |
|
0069 9170.00 | 80.00 | 98.107 | 7,848.56
|
EARTH SHOULDER CONSTRUCTION | StaM | 98.107 | 7,848.56
|
| | 98.107 | 7,848.56
|
| | 0.000 | 0.00
|
| | |
|
0070 9173.00 | 285.00 | 136.002 | 38,760.57
|
SUBGRADE PREPARATION | StaM | 136.002 | 38,760.57
|
| | 136.002 | 38,760.58
|
| | 0.000 | 0.00
|
| | |
|
0071 9179.23 | 400.00 | 39.350 | 15,740.00
|
COLD MILLING, CLASS 3 | StaM | 39.350 | 15,740.00
|
| | 39.350 | 15,740.00
|
| | 0.000 | 0.00
|
| | |
|
0072 9179.24 | 2,245.00 | 86.950 | 195,202.75
|
COLD MILLING, CLASS 4 | StaM | 86.950 | 195,202.75
|
| | 86.950 | 195,202.75
|
| | 0.000 | 0.00
|
| | |
|
0073 9188.01 | 2.35 | 35,809.000 | 84,151.15
|
BITUMINOUS SURFACE COURSE | m2 | 35,809.000 | 84,151.15
|
| | 35,807.960 | 84,148.70
|
| | 0.000 | 0.00
|
| | |
|
0074 9300.50 | 3,500.00 | 1.000 | 3,500.00
|
ASPHALT PAVEMENT SMOOTHNESS TESTING | LS | 1.000 | 3,500.00
|
| | 1.000 | 3,500.00
|
| | 0.000 | 0.00
|
| | |
|
4007 9173.10 | 370.714 | 0.000 | 0.00
|
SUBGRADE PREPARATION FOR WIDENING | StaM | 5.395 | 2,000.00
|
For Placing Asphalt Curb | | 5.395 | 2,000.00
|
| | 0.000 | 0.00
|
| | |
|
4008 9005.81 | 30.00 | 0.000 | 0.00
|
ASPHALTIC CONCRETE, TYPE SPS | Mg | 215.000 | 6,450.00
|
For widening to place curb | | 120.000 | 3,600.00
|
| | 0.000 | 0.00
|
| | |
|
4009 9030.00 | 8.00 | 0.000 | 0.00
|
CONSTRUCTING ASPHALTIC CONCRETE CURB | m | 539.500 | 4,316.00
|
| | 539.500 | 4,316.00
|
| | 0.000 | 0.00
|
| | |
|
4018 9300.56 | 0.435 | 0.000 | 0.00
|
SUPERPAVE QUALITY INCENTIVE | Mg | 35,218.220 | 15,319.93
|
INCENTIVE FOR AIRVOIDS AND DENSITY | | 35,218.220 | 15,319.93
|
| | 0.000 | 0.00
|
| | |
|
4019 9300.77 | 3.226 | 0.000 | 0.00
|
SMOOTHNESS INCENTIVE-PERFORMANCE GRADED BINDER | Mg | 494.707 | 1,595.92
|
| | 494.707 | 1,595.92
|
| | 0.000 | 0.00
|
| | |
|
4020 9300.60 | 0.364 | 0.000 | 0.00
|
SMOOTHNESS INCENTIVE-ASPHALTIC CONCRETE | Mg | 10,525.690 | 3,831.35
|
| | 10,525.690 | 3,831.35
|
| | 0.000 | 0.00
|
| | |
|
GROUP 9 BITUMINOUS | | Contracted | 2,195,855.31
|
| | Current | 2,231,141.01
|
| | In place | 2,065,325.04
|
| | This Estimate | 0.00
|
| | |
|
GROUP 10 GENERAL ITEMS | | |
|
0075 0001.08 | 0.50 | 11,260.000 | 5,630.00
|
BARRICADE, TYPE II | BDAY | 11,260.000 | 5,630.00
|
| | 5,348.000 | 2,674.00
|
| | 0.000 | 0.00
|
| | |
|
0076 0001.10 | 4.00 | 2,416.000 | 9,664.00
|
BARRICADE, TYPE III | BDAY | 2,416.000 | 9,664.00
|
| | 1,545.000 | 6,180.00
|
| | 0.000 | 0.00
|
| | |
|
0077 0001.30 | 3.98 | 376.000 | 1,496.48
|
TYPE B HIGH INTENSITY WARNING LIGHT | LDAY | 376.000 | 1,496.48
|
| | 247.000 | 983.06
|
| | 0.000 | 0.00
|
| | |
|
0078 0001.90 | 0.80 | 17,520.000 | 14,016.00
|
SIGN DAY | EACH | 17,520.000 | 14,016.00
|
| | 8,786.000 | 7,028.80
|
| | 0.000 | 0.00
|
| | |
|
0079 0002.30 | 3.00 | 900.000 | 2,700.00
|
PAVEMENT MARKING REMOVAL | m | 900.000 | 2,700.00
|
| | 900.000 | 2,700.00
|
| | 0.000 | 0.00
|
| | |
|
0080 0002.44 | 0.50 | 19,200.000 | 9,600.00
|
TEMPORARY PAVEMENT MARKING, TYPE PAINT | m | 19,200.000 | 9,600.00
|
| | 19,404.000 | 9,702.00
|
| | 0.000 | 0.00
|
| | |
|
0081 0003.10 | 195.00 | 360.000 | 70,200.00
|
FLAGGING | DAY | 360.000 | 70,200.00
|
| | 128.000 | 24,960.00
|
| | 0.000 | 0.00
|
| | |
|
0082 0010.04 | 800.00 | 1.000 | 800.00
|
FIELD OFFICE | EACH | 1.000 | 800.00
|
| | 1.000 | 800.00
|
| | 0.000 | 0.00
|
| | |
|
0083 0030.10 | 8,600.00 | 1.000 | 8,600.00
|
MOBILIZATION | LS | 1.000 | 8,600.00
|
| | 1.000 | 8,600.00
|
| | 0.000 | 0.00
|
| | |
|
4001 0001.06 | 0.25 | 0.000 | 0.00
|
VERTICAL PANELS | BDAY | 24,600.000 | 6,150.00
|
vercial panels for use on temporary roads | | 21,200.000 | 5,300.00
|
| | 0.000 | 0.00
|
| | |
|
GROUP 10 GENERAL ITEMS | | Contracted | 122,706.48
|
| | Current | 128,856.48
|
| | In place | 68,927.86
|
| | This Estimate | 0.00
|
| | |
|
Totals for contract | | Contracted | 3,765,861.48
|
---|
| | Current | 3,835,255.49
|
---|
| | In place | 3,618,923.39
|
---|
| | This Estimate | 0.00
|
---|