| | Detailed breakdown of stockpiled materials | |
|
---|
Est Nbr: | 0001 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0013 | 9005.23 | ASPHALTIC CONCRETE, TYPE SPS | |
|
| | S.P. Initial Payment | 21,424.25 | 1
|
| | 2 A Gravel | |
|
| | S.P. Initial Payment | 21,654.40 | 1
|
| | 3/4 Crushed Rock | |
|
0014 | 9005.45 | ASPHALTIC CONCRETE, TYPE SP4(0.5) | |
|
| | S.P. Initial Payment | 15,527.70 | 1
|
| | 2 A Gravel | |
|
| | S.P. Initial Payment | 15,680.65 | 1
|
| | 3/4 Crushed Rock | |
|
| | Total for estimate 0001: | 74,287.00 |
|
Est Nbr: | 0002 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0013 | 9005.23 | ASPHALTIC CONCRETE, TYPE SPS | |
|
| | S.P. Initial Payment | 4,994.60 | 2
|
| | Wash Sand | |
|
0014 | 9005.45 | ASPHALTIC CONCRETE, TYPE SP4(0.5) | |
|
| | S.P. Initial Payment | 9,749.47 | 2
|
| | Crushed Gravel | |
|
| | S.P. Initial Payment | 46,977.16 | 2
|
| | Hills AS Fines | |
|
| | Total for estimate 0002: | 61,721.23 |
|
Est Nbr: | 0003 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0013 | 9005.23 | ASPHALTIC CONCRETE, TYPE SPS | |
|
| | S.P. Initial Payment | 31,751.54 | 3
|
| | 3/4 Crushed Rock | |
|
| | S.P. Initial Payment | 3,512.79 | 3
|
| | Wash Sand | |
|
0014 | 9005.45 | ASPHALTIC CONCRETE, TYPE SP4(0.5) | |
|
| | S.P. Initial Payment | 19,500.00 | 3
|
| | Crushed Gravel | |
|
| | Total for estimate 0003: | 54,764.33 |
|
Est Nbr: | 0004 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0014 | 9005.45 | ASPHALTIC CONCRETE, TYPE SP4(0.5) | |
|
| | S.P. Adjustment | -4,858.13 | 1
|
| | 2 A Gravel | |
|
| | S.P. Adjustment | -15,680.65 | 1
|
| | 3/4 Crushed Rock | |
|
| | S.P. Adjustment | -9,749.47 | 2
|
| | Crushed Gravel | |
|
| | S.P. Adjustment | -10,343.48 | 2
|
| | Hills AS Fines | |
|
| | S.P. Adjustment | -18,531.60 | 3
|
| | Crushed Gravel | |
|
| | Total for estimate 0004: | -59,163.33 |
|
Est Nbr: | 0005 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0014 | 9005.45 | ASPHALTIC CONCRETE, TYPE SP4(0.5) | |
|
| | S.P. Adjustment | -10,669.57 | 1
|
| | 2 A Gravel | |
|
| | S.P. Adjustment | -36,633.68 | 2
|
| | Hills AS Fines | |
|
| | S.P. Adjustment | -968.40 | 3
|
| | Crushed Gravel | |
|
| | Total for estimate 0005: | -48,271.65 |
|
| | Total remaining for contract: | 83,337.58 |
|
---|
| | | 1. Contracted
|
---|
| | | 2. Current
|
---|
| | | 3. To date
|
---|
Item Nbr Item Code | Unit Price | | 4. This Est
|
---|
Item Description | Units | Qty | Amount
|
---|
GROUP 9 BITUMINOUS | | |
|
0001 0001.08 | 0.50 | 23,760.000 | 11,880.00
|
BARRICADE, TYPE II | BDAY | 23,760.000 | 11,880.00
|
| | 22.000 | 11.00
|
| | 22.000 | 11.00
|
| | |
|
0002 0001.10 | 3.45 | 360.000 | 1,242.00
|
BARRICADE, TYPE III | BDAY | 360.000 | 1,242.00
|
| | 108.000 | 372.60
|
| | 56.000 | 193.20
|
| | |
|
0003 0001.75 | 5.75 | 420.000 | 2,415.00
|
TEMPORARY SIGN DAY | EACH | 420.000 | 2,415.00
|
| | 243.000 | 1,397.25
|
| | 148.000 | 851.00
|
| | |
|
0004 0001.90 | 1.10 | 5,850.000 | 6,435.00
|
SIGN DAY | EACH | 5,850.000 | 6,435.00
|
| | 1,757.000 | 1,932.70
|
| | 969.000 | 1,065.90
|
| | |
|
0005 0002.55 | 5.55 | 1,672.920 | 9,284.71
|
OVERLAY BROKEN LINES | STA | 1,672.920 | 9,284.71
|
| | 1,402.590 | 7,784.37
|
| | 607.620 | 3,372.29
|
| | |
|
0006 0002.60 | 5.55 | 3,345.840 | 18,569.41
|
OVERLAY SOLID LINES | STA | 3,345.840 | 18,569.41
|
| | 1,510.540 | 8,383.50
|
| | 228.000 | 1,265.40
|
| | |
|
0007 0003.10 | 164.00 | 100.000 | 16,400.00
|
FLAGGING | DAY | 100.000 | 16,400.00
|
| | 57.500 | 9,430.00
|
| | 29.000 | 4,756.00
|
| | |
|
0008 0003.20 | 250.00 | 50.000 | 12,500.00
|
FURNISHING AND OPERATING PILOT VEHICLE | DAY | 50.000 | 12,500.00
|
| | 19.000 | 4,750.00
|
| | 9.000 | 2,250.00
|
| | |
|
0009 0010.04 | 1,350.00 | 1.000 | 1,350.00
|
FIELD OFFICE | EACH | 1.000 | 1,350.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0010 0030.90 | 30,300.00 | 1.000 | 30,300.00
|
MOBILIZATION | LS | 1.000 | 30,300.00
|
| | 1.000 | 30,300.00
|
| | 0.000 | 0.00
|
| | |
|
0011 9000.75 | 19.80 | 100.000 | 1,980.00
|
ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE | TON | 100.000 | 1,980.00
|
SP4(0.5) | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0012 9005.00 | 24.00 | 100.000 | 2,400.00
|
ASPHALTIC CONCRETE FOR PATCHING, TYPE | TON | 100.000 | 2,400.00
|
SP4(0.5) | | 10.000 | 240.00
|
| | 10.000 | 240.00
|
| | |
|
0013 9005.23 | 12.55 | 11,150.000 | 139,932.50
|
ASPHALTIC CONCRETE, TYPE SPS | TON | 11,150.000 | 139,932.50
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0014 9005.45 | 19.80 | 32,310.000 | 639,738.00
|
ASPHALTIC CONCRETE, TYPE SP4(0.5) | TON | 32,310.000 | 639,738.00
|
| | 27,935.660 | 553,126.06
|
| | 22,233.630 | 440,225.87
|
| | |
|
0015 9020.91 | 179.50 | 5.400 | 969.30
|
PERFORMANCE GRADED BINDER (64-22) FOR STATE MAINTENANCEPATCHING | TON | 5.400 | 969.30
|
| | 0.560 | 100.52
|
| | 0.560 | 100.52
|
| | |
|
0016 9021.01 | 179.50 | 1,750.140 | 314,150.13
|
PERFORMANCE GRADED BINDER (64-22) | TON | 1,750.140 | 314,150.13
|
| | 1,473.430 | 264,480.69
|
| | 1,181.490 | 212,077.46
|
| | |
|
0017 9021.03 | 179.50 | 602.100 | 108,076.95
|
PERFORMANCE GRADED BINDER (58-28) | TON | 602.100 | 108,076.95
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0018 9053.00 | 0.80 | 45,700.000 | 36,560.00
|
TACK COAT | GAL | 45,700.000 | 36,560.00
|
| | 21,597.750 | 17,278.20
|
| | 15,795.000 | 12,636.00
|
| | |
|
0019 9110.01 | 45.00 | 60.000 | 2,700.00
|
RENTAL OF LOADER, FULLY OPERATED | HOUR | 60.000 | 2,700.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0020 9110.02 | 45.00 | 60.000 | 2,700.00
|
RENTAL OF MOTOR GRADER, FULLY OPERATED | HOUR | 60.000 | 2,700.00
|
| | 1.000 | 45.00
|
| | 1.000 | 45.00
|
| | |
|
0021 9110.03 | 39.00 | 60.000 | 2,340.00
|
RENTAL OF DUMP TRUCK, FULLY OPERATED | HOUR | 60.000 | 2,340.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0022 9110.07 | 31.00 | 60.000 | 1,860.00
|
RENTAL OF SKID LOADER, FULLY OPERATED | HOUR | 60.000 | 1,860.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0023 9179.23 | 132.90 | 557.640 | 74,110.36
|
COLD MILLING, CLASS 3 | STA | 557.640 | 74,110.36
|
| | 561.970 | 74,685.81
|
| | 0.000 | 0.00
|
| | |
|
0024 9179.43 | 24.30 | 1,115.280 | 27,101.30
|
COLD MILLING, CLASS 3 | STA | 1,115.280 | 27,101.30
|
TYPE A | | 1,123.940 | 27,311.74
|
| | 0.000 | 0.00
|
| | |
|
0025 9300.52 | 2,875.00 | 1.000 | 2,875.00
|
ASPHALT PAVEMENT SMOOTHNESS TESTING I/D | LS | 1.000 | 2,875.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
GROUP 9 BITUMINOUS | | Contracted | 1,467,869.66
|
| | Current | 1,467,869.66
|
| | In place | 1,001,629.44
|
| | This Estimate | 679,089.64
|
| | |
|
Totals for contract | | Contracted | 1,467,869.66
|
---|
| | Current | 1,467,869.66
|
---|
| | In place | 1,001,629.44
|
---|
| | This Estimate | 679,089.64
|
---|