Nebraska Department of Roads | |
---|---|
Estimate Summary to Contractor | |
Vendor ID: | 0539 BROWN & BROWN, INC. |
Contract ID: | 87801 |
Estimate Number: | 0003 |
Pay Period End Date: | 09.14.2002 |
Contract Location: | ||
NORDEN EAST & WEST | Estimate Type: | PROG |
Contractor: | ||
BROWN & BROWN, INC. | Date Let: | 05.23.2002 |
124 INDIANA | Date Awarded: | 05.30.2002 |
PO BOX 2000 | Date Contract Executed: | 06.13.2002 |
Date Notice to Proceed: | 06.13.2002 | |
SALINA KS 67402-2000 | Date Work Began: | |
Phone: | Date Physical Work Completed: | |
(785)827-4439 | Date Accepted: | |
Escrow Agent: | ||
Surety Co: | ||
HARTFORD FIRE INSURANCE COMPANY |
Counties |
---|
KEYA PAHA |
Project Number |   | PCT |   | Fed State Project Number |   | Description | |
---|---|---|---|---|---|---|---|
80780 1001 |   | 0.000 |   | PEP-12-3(1008) |   | BITUMINOUS |
Total to Date | Prev to Date | This Estimate | ||
Current Contract Amt | Total Earnings | $1,065,722.72 | $474,346.92 | $591,375.80 |
$1,211,353.82 | Stockpiled Materials | $.00 | $.00 | $.00 |
Original Contract Amt | Gross Earnings | $1,065,722.72 | $474,346.92 | $591,375.80 |
$1,341,894.17 | Retainage | $-10,657.23 | $-4,743.47 | $-5,913.76 |
Escrow Amount | $.00 | $.00 | $.00 | |
Percent Complete | Securities Encumbered | $.00 | $.00 | $.00 |
87.98% | Net Earnings | $1,055,065.49 | $469,603.45 | $585,462.04 |
Liquidated Damages | $.00 | $.00 | $.00 | |
Incentives | $.00 | $.00 | $.00 | |
Disincentives | $.00 | $.00 | $.00 | |
Other Contract Adj | $.00 | $.00 | $.00 | |
Appl of Training Adj | $.00 | $.00 | $.00 | |
Training Rates Adj | $.00 | $.00 | $.00 | |
Fuel Adj | $.00 | $.00 | $.00 | |
Bituminous Adj | $.00 | $.00 | $.00 | |
Autopay Adj | $.00 | $.00 | $.00 | |
Gasoline Adj | $.00 | $.00 | $.00 | |
Other Adj | $.00 | $.00 | $.00 | |
Price Adj | $.00 | $.00 | $.00 | |
Substandard Item Adj | $.00 | $.00 | $.00 | |
Asphalt Adj | $.00 | $.00 | $.00 | |
Diesel Fuel Adj | $.00 | $.00 | $.00 | |
Petrol Adj | $.00 | $.00 | $.00 | |
Total for Adjustments | $.00 | $.00 | $.00 | |
Payment | $1,055,065.49 | $469,603.45 | $585,462.04 | |
Project Manager | Div. Head/Dist. Eng. | |||
Rau, Larry | 09.16.2002 | Bartos, Steve | 09.16.2002 | |
Constr. Estimate Eng. | Materials Eng. | |||
Bartos, Steve | 09.16.2002 | |||
Controller Div. Processed | ||||
Burling, Laurie | 09.17.2002 |
Detailed breakdown of stockpiled materials | ||||
---|---|---|---|---|
Total remaining for contract: | 0.00 |
1. Contracted | |||
---|---|---|---|
2. Current | |||
3. To date | |||
Item Nbr Item Code | Unit Price | 4. This Est | |
Item Description | Units | Qty | Amount |
GROUP 9 BITUMINOUS | |||
0001 0001.10 | 2.00 | 276.000 | 552.00 |
BARRICADE, TYPE III | BDAY | 276.000 | 552.00 |
225.000 | 450.00 | ||
146.000 | 292.00 | ||
0002 0001.30 | 2.00 | 138.000 | 276.00 |
TYPE B HIGH INTENSITY WARNING LIGHT | LDAY | 138.000 | 276.00 |
62.000 | 124.00 | ||
25.000 | 50.00 | ||
0003 0001.75 | 3.00 | 60.000 | 180.00 |
TEMPORARY SIGN DAY | EACH | 60.000 | 180.00 |
15.000 | 45.00 | ||
6.000 | 18.00 | ||
0004 0001.90 | 0.25 | 7,500.000 | 1,875.00 |
SIGN DAY | EACH | 7,500.000 | 1,875.00 |
3,397.000 | 849.25 | ||
2,393.000 | 598.25 | ||
0005 0002.45 | 4.00 | 965.000 | 3,860.00 |
TEMPORARY BROKEN LINES | STA | 965.000 | 3,860.00 |
967.000 | 3,868.00 | ||
206.000 | 824.00 | ||
0006 0003.10 | 170.00 | 90.000 | 15,300.00 |
FLAGGING | DAY | 90.000 | 15,300.00 |
78.000 | 13,260.00 | ||
46.000 | 7,820.00 | ||
0007 0003.20 | 360.00 | 45.000 | 16,200.00 |
FURNISHING AND OPERATING PILOT VEHICLE | DAY | 45.000 | 16,200.00 |
36.000 | 12,960.00 | ||
20.000 | 7,200.00 | ||
0008 0030.90 | 90,200.00 | 1.000 | 90,200.00 |
MOBILIZATION | LS | 1.000 | 90,200.00 |
1.000 | 90,200.00 | ||
0.000 | 0.00 | ||
0009 8008.00 | 46.72 | 2,300.000 | 107,456.00 |
ARMOR COAT AGGREGATE | CY | 2,300.000 | 107,456.00 |
2,899.000 | 135,441.28 | ||
2,899.000 | 135,441.28 | ||
0010 9004.89 | 632.51 | 964.527 | 610,072.97 |
COLD IN-PLACE RECYCLING | STA | 0.000 | 0.00 |
0.000 | 0.00 | ||
0.000 | 0.00 | ||
0011 9005.21 | 8.00 | 200.000 | 1,600.00 |
PATCHING BITUMINOUS SAND | SY | 200.000 | 1,600.00 |
0.000 | 0.00 | ||
0.000 | 0.00 | ||
0012 9052.00 | 0.89 | 92,980.000 | 82,752.20 |
ARMOR COAT EMULSIFIED ASPHALT | GAL | 92,980.000 | 82,752.20 |
85,920.000 | 76,468.80 | ||
85,920.000 | 76,468.80 | ||
0013 9053.90 | 1.00 | 409,770.000 | 409,770.00 |
EMULSIFIED ASPHALT FOR COLD IN-PLACE RECYCLING | GAL | 327,816.000 | 327,816.00 |
171,193.100 | 171,193.10 | ||
110,652.190 | 110,652.19 | ||
0014 9111.25 | 5.00 | 360.000 | 1,800.00 |
WATER FOR COLD IN-PLACE RECYCLING, APPLIED | MGAL | 288.000 | 1,440.00 |
251.515 | 1,257.58 | ||
131.641 | 658.21 | ||
4000 9004.89 | 582.51 | 0.000 | 0.00 |
COLD IN-PLACE RECYCLING | STA | 964.527 | 561,846.62 |
960.680 | 559,605.71 | ||
431.500 | 251,353.07 | ||
GROUP 9 BITUMINOUS | Contracted | 1,341,894.17 | |
Current | 1,211,353.82 | ||
In place | 1,065,722.72 | ||
This Estimate | 591,375.80 | ||
Totals for contract | Contracted | 1,341,894.17 | |
Current | 1,211,353.82 | ||
In place | 1,065,722.72 | ||
This Estimate | 591,375.80 |