Nebraska Department of Roads | |
---|---|
Estimate Summary to Contractor | |
Vendor ID: | 0B38 ROGGE GENERAL CONTRACTORS, INC. |
Contract ID: | K111 |
Estimate Number: | 0002 |
Pay Period End Date: | 09.12.2003 |
Contract Location: | ||
Palmyra Maintenance Facilty | Estimate Type: | PROG |
Contractor: | ||
ROGGE GENERAL CONTRACTORS, INC. | Date Let: | 05.07.2003 |
6101 SOUTH 58TH, STE A | Date Awarded: | 05.30.2003 |
Date Contract Executed: | 06.13.2003 | |
Date Notice to Proceed: | 06.13.2003 | |
LINCOLN NE 68516 | Date Work Began: | |
Phone: | Date Physical Work Completed: | |
(402)441-3100 | Date Accepted: | |
Escrow Agent: | ||
Surety Co: | ||
UNITED FIRE & CASUALTY INSURANCE COMPANY |
Counties |
---|
OTOE |
Project Number |   | PCT |   | Fed State Project Number |   | Description | |
---|---|---|---|---|---|---|---|
K111 |   | 0.000 |   | AFE K-111 |   | General Contract Work |
Total to Date | Prev to Date | This Estimate | ||
Current Contract Amt | Total Earnings | $280,014.03 | $133,621.02 | $146,393.01 |
$1,362,000.00 | Stockpiled Materials | $.00 | $.00 | $.00 |
Original Contract Amt | Gross Earnings | $280,014.03 | $133,621.02 | $146,393.01 |
$1,362,000.00 | Retainage | $-28,001.40 | $-13,362.10 | $-14,639.30 |
Escrow Amount | $.00 | $.00 | $.00 | |
Percent Complete | Securities Encumbered | $.00 | $.00 | $.00 |
20.56% | Net Earnings | $252,012.63 | $120,258.92 | $131,753.71 |
Liquidated Damages | $.00 | $.00 | $.00 | |
Incentives | $.00 | $.00 | $.00 | |
Disincentives | $.00 | $.00 | $.00 | |
Other Contract Adj | $.00 | $.00 | $.00 | |
Appl of Training Adj | $.00 | $.00 | $.00 | |
Training Rates Adj | $.00 | $.00 | $.00 | |
Fuel Adj | $.00 | $.00 | $.00 | |
Bituminous Adj | $.00 | $.00 | $.00 | |
Autopay Adj | $.00 | $.00 | $.00 | |
Gasoline Adj | $.00 | $.00 | $.00 | |
Other Adj | $.00 | $.00 | $.00 | |
Price Adj | $.00 | $.00 | $.00 | |
Substandard Item Adj | $.00 | $.00 | $.00 | |
Asphalt Adj | $.00 | $.00 | $.00 | |
Diesel Fuel Adj | $.00 | $.00 | $.00 | |
Petrol Adj | $.00 | $.00 | $.00 | |
Total for Adjustments | $.00 | $.00 | $.00 | |
Payment | $252,012.63 | $120,258.92 | $131,753.71 | |
Project Manager | Div. Head/Dist. Eng. | |||
Hitzeman, Don | 09.12.2003 | Sklenar, Michael J | 09.15.2003 | |
Constr. Estimate Eng. | Materials Eng. | |||
Schmailzl, Jim | 09.15.2003 | |||
Controller Div. Processed | ||||
Burling, Laurie | 09.16.2003 |
Detailed breakdown of stockpiled materials | ||||
---|---|---|---|---|
Total remaining for contract: | 0.00 |
1. Contracted | |||
---|---|---|---|
2. Current | |||
3. To date | |||
Item Nbr Item Code | Unit Price | 4. This Est | |
Item Description | Units | Qty | Amount |
PALMYRA MAINTENANCE FACILITY | |||
0001 5999.81 | 74,476.00 | 1.000 | 74,476.00 |
GENERAL CONDITIONS | LS | 1.000 | 74,476.00 |
1000 SERIES | 0.492 | 36,642.19 | |
0.090 | 6,702.84 | ||
0002 5999.82 | 169,985.00 | 1.000 | 169,985.00 |
SITE WORK | LS | 1.000 | 169,985.00 |
2000 SERIES | 0.247 | 41,986.30 | |
0.000 | 0.00 | ||
0003 5999.83 | 106,533.00 | 1.000 | 106,533.00 |
CONCRETE | LS | 1.000 | 106,533.00 |
3000 SERIES | 0.381 | 40,589.07 | |
0.000 | 0.00 | ||
0004 5999.84 | 209,880.00 | 1.000 | 209,880.00 |
MASONRY | LS | 1.000 | 209,880.00 |
4000 SERIES | 0.429 | 90,038.52 | |
0.429 | 90,038.52 | ||
0005 5999.85 | 27,205.00 | 1.000 | 27,205.00 |
STEEL | LS | 1.000 | 27,205.00 |
5000 SERIES | 0.767 | 20,866.24 | |
0.767 | 20,866.24 | ||
0006 5999.86 | 85,383.00 | 1.000 | 85,383.00 |
WOODS & PLASTICS | LS | 1.000 | 85,383.00 |
6000 SERIES | 0.025 | 2,134.58 | |
0.025 | 2,134.58 | ||
0007 5999.87 | 158,172.00 | 1.000 | 158,172.00 |
THERMAL & MOISTURE | LS | 1.000 | 158,172.00 |
7000 SERIES | 0.000 | 0.00 | |
0.000 | 0.00 | ||
0008 5999.88 | 83,951.00 | 1.000 | 83,951.00 |
DOORS & WINDOWS | LS | 1.000 | 83,951.00 |
8000 SERIES | 0.022 | 1,846.92 | |
0.000 | 0.00 | ||
0009 5999.89 | 69,501.00 | 1.000 | 69,501.00 |
FINISHES | LS | 1.000 | 69,501.00 |
9000 SERIES | 0.000 | 0.00 | |
0.000 | 0.00 | ||
0010 5999.90 | 8,469.00 | 1.000 | 8,469.00 |
SPECIALTIES | LS | 1.000 | 8,469.00 |
10000 SERIES | 0.000 | 0.00 | |
0.000 | 0.00 | ||
0011 3995.00 | 58,830.00 | 1.000 | 58,830.00 |
CONSTRUCT | LS | 1.000 | 58,830.00 |
13000 SERIES | 0.000 | 0.00 | |
0.000 | 0.00 | ||
0012 5999.91 | 151,145.00 | 1.000 | 151,145.00 |
MECHANICAL | LS | 1.000 | 151,145.00 |
15000 SERIES | 0.201 | 30,380.15 | |
0.126 | 19,044.27 | ||
0013 5999.92 | 158,470.00 | 1.000 | 158,470.00 |
ELECTRICAL | LS | 1.000 | 158,470.00 |
16000 SERIES | 0.098 | 15,530.06 | |
0.048 | 7,606.56 | ||
PALMYRA MAINTENANCE FACILITY | Contracted | 1,362,000.00 | |
Current | 1,362,000.00 | ||
In place | 280,014.03 | ||
This Estimate | 146,393.01 | ||
Totals for contract | Contracted | 1,362,000.00 | |
Current | 1,362,000.00 | ||
In place | 280,014.03 | ||
This Estimate | 146,393.01 |